Bsibv Itp 08-2 Itp For CWC Dpe Rev. 0
Bsibv Itp 08-2 Itp For CWC Dpe Rev. 0
com
2018.10.09 14:41:46
+04'00'
Site Project Quality Document
INSPECTION AND TEST PLAN - CONCRETE WEIGHT COATING
BREDERO SHAW INTERNATIONAL B.V, RAK
Customer Project PO Number
TechnipFMC AQAM Development EPCI 077607C004-230-PO-5530-012-7010
C: Record & Raise Documents H: Hold Point N: Non-Destructive Testing V: Visual 1: 100%
Legend D: Dimensional Inspection I: Random Inspection R/A: Review/APPROVAL W: Witness 2: 10%
E: Examine/Endorse Documents M: Monitor T: Destructive Testing WFO: Witness First Off S: Surveillance
Approval Inspection
DP-PL-
BSIBV Production Test
No. Activity Description 17 Rev. Method / Acceptance Criteria Verifying doc
QP 08-2 Frequency BSIBV TP FMC DPE / TPI
10
Note: The large Iron Ore particle shall not be more than 9.5 mm.
Water used in the mix shall be potable and shall comply with the
requirements of BS EN 1008. The mixing water shall be clean and
free from injurious amounts of acid, alcohol, alkali, oil, salt or any
organic material. Water shall be suitable for use in concrete. Salt QF 08-7 /
4.3 /
3 Water 2.3.4 water or brackish water shall not be used. Water that is potable RF 033 / QF First day of production H R R
7.2.4
does not require testing for compliance. 01-3
Confirm pipe number and length is still visible. The pipe number
9 Verify Pipe Identity 2.4 QF 001 All Pipes H W1 R
shall be entered to tally track system.
The diameter of each coated line pipe shall be obtained at five (5) or
more points, spaced at approximately equal intervals with the
distance between the end points at least 80% of the coated length.
QF 08-1
Concrete Thickness The tolerance on the concrete coating thickness shall be ±10% of
14 7.3.1 3 (Computer All Pipes H W1 R
Tolerances the nominal concrete thickness.
Database)
The fully saturated submerged weight of each coated line pipe shall QF 08-1
15 Concrete Weight Tolerance 7.3.2 3.8 be that stated with a tolerance of ±10 kg/m on any one pipe and a (Computer All Pipes H R R
tolerance of ±10% on each day's production of line pipe. Database)
The internal surface of the pipe shall be clean and there shall be no
18 Concrete Cut Back 5.4 2.7 visual damage to the concrete coating. The Cut back shall be 240 QF 08-4 All Pipes H W1 R
mm - 0 / +10mm, this is from the bevel end of the each pipe ends.
Freshly coated pipes shall be placed in the curing area and covered
19 Fog Cure 5.5.4 2.7 by tarpaulins. Identify each bay, record curing start time and % QF 08-5 All Bays H M R
humidity.
Verification of Anode The thickness of anode shall be verified with concrete coating
All Anode Installed
20 Thickness with Concrete 5.3.2 2.5 thickness visually. Anode shall not be protruded above Concrete - H W1 R
Pipes
Coating Thickness Coating.
5.5.1 / Initial compressive strength of the cube shall be 16 MPa after 24 Once at first day of
21 Initial Compressive Strength 3.6 QF 08-10 H W1 R
7.2.6 hours. production
Minimum compressive strength shall be minimum 37 MPa after 7 4 cubes for each sample
days. taken at every 4 hours
Compressive Strength on
22 7.2.6 3.6 QF 08-10 or at mix change or after H W1 R
Cubes
Minimum compressive strength shall be minimum 50 MPa after 28 all shutdown periods (7
days. & 28 Days)
One core shall be tested at 7 days and the other at 28 days. The
cores shall have a minimum compressive strength of not less than
30 MPa after 7 days and 40 MPa after 28 days.
Compressive Strength on 3 core samples per 15
23 7.2.6 3.6 QF 08-10 H W1 R
Cores The minimum diameter of the core shall be at least 35mm. A single line pipes coated
core diameter shall be used throughout the coating operation. Three
cores shall be taken, one at each end within 1-2m from pipe end
and one at middle 2 m
6"X 6" Coupon shall have a minimum of 4 days cure prior to testing.
The maximum water absorption shall not be greater than 5% by
weight. Once per 24 Hrs (day) Pipe full-scale water absorption test Once per shift and after
24 Concrete Water Absorption 7.2.8 3.5 QF 08-8 H W1 R
shall be carried out at start of production in accordance with BSIBV mix changes
test method TM -27. Pre-qualification test or first day’s one
production pipe shall be performed full-scale Water Absorption test.
concrete.
28 Repairs - Spalling 7.4.2 2.9 QF 08-6 All repairs H M/R M/R
around the entire pipe circumference throughout the length of
damaged area.
steel until the surface is level with the coating around the repair.
irrespective of width.
Core holes shall be manually repaired using stiff mix similar to the
31 Repairs to core holes 7.4 2.9 mix used in the coating process; Cosmetic repair shall be carried QF 08-6 All repairs H M M
out in the field after curing.
3.13 /
Inspection release notes shall be submitted to BSIBV from TPI,
34 Weekly Release Appendix QF 032 (IRN) Once per week H H H
when all QC Documents are approved.
2
Appendix The pipe identification shall be checked against the packing list prior
36 Packing List Verification TF 014 All pipes H H H
2 to load out.