Orcullo, Jr. vs. Civil Service Commission
Orcullo, Jr. vs. Civil Service Commission
*
G.R No. 138780. May 22, 2001.
_____________________
* EN BANC.
116
KAPUNAN, J.:
117
1
was to end on January 30, 2000. On September 23, 1996 or
six (6) months from his assumption to office, petitioner
received a Memorandum, dated September 20, 1996, from
one Jorge M. Briones, Assistant Director of CCPAP,
terminating petitionerÊs contractual employment with said
2
agency effective September 30, 1996.
In a Letter dated September 20, 1996, Undersecretary
Francisco F. del Rosario, Executive Director of CCPAP,
confirmed petitionerÊs termination as project manager of
CCPAP.
Aggrieved by his dismissal, petitioner appealed the same
to the Civil Service Commission (CSC).
On April 2, 1997, the respondent CSC issued Resolution
No. 972309 dismissing petitionerÊs appeal. The CSC found
that:
_________________
1Rollo, p. 40;
2Id., at 9.
3Id., at 46.
118
xxx
(4) Contractual personnel or those whose employment in the
government is in accordance with a special contract to undertake a
____________________
4 Id., at 61.
119
VOL. 358, MAY 22, 2001 119
Orcullo, Jr. vs. Civil Service Commission
120
___________________
6 Rollo, p. 58.
7Id., at 41.
8Id.
121
Petition dismissed.
··o0o··
© Copyright 2024 Central Book Supply, Inc. All rights reserved.