4th Year Design Project Report (Extract)
4th Year Design Project Report (Extract)
Excerpts from
Final year individual project
Design report
Mimi Tam
1
NOTES
www.mimitam.myportfolio.com
2
CONTENTS
Process documentation 5
Structure & tectonics 15
Environmental design 27
4
PROCESS DOCUMENTATION
5
A study of Ilimelgo vertical farm, France, 2017, by
Ilimelgo Architectes.
THE
THE VERY
VERY START
START
06.02.2023
6 02 2 23 - 18.02.2023
1 2 2023
6
DESKTOP REVIEW
19.02.2023
7
ITERATION
20.02.2023 - 09.03.2023
9
TECTONIC EXPLORATION
11.03.2023 - 30.03.2023
10
0
Sectional perspective needs further
development - what activities are
happening in each space? What are
the light fittings like? Could investigate making
Graphics on the plans clearly Elevations are lively and convey the the planting façade
convey the scheme but the atmosphere well, but the colour does accessible for maintenance
greenery could stand out more not reflect the timber materiality by increasing the ‘balcony’
depth.
TECTONIC REVIEW
Perspective views need further development - 31.03.2023
need to start looking at materiality etc.
11
REFINING THE DETAILS
01.04.2023 - 04.05.2023
12
2
FINAL REVIEW
05.05.2023
Structural strategy 16
Structural components 17
Construction details
The vertical farms 20
The food hall 24
15
STRUCTURAL STRATEGY
OVERVIEW
Concrete planks
(7000x7000x200mm)
Pad foundations
With carbon reduction as a key driver of the OGFM, it is crucial for the structure to be low in embodied carbon. Hence,
glulam and CLT has been selected as the primary structural material. A regular grid enables structural components to
be modular, which facilitates off-site construction. This is further explained on pg. 62-63.
16
STRUCTURAL COMPONENTS
17
18
Food hall
(I, J)
South façade
vertical farms
(F, G, H)
F.
G.
I.
J.
19
THE VERTICAL FARMS
Construction details
3.5m
4.2m
3
4
20
F.
H.
G.
21
FAÇADE DETAILS
1:10
1
5
1 2 3 4 5 6 7
3
6
4
22
VERTICAL FARM FLOOR CONSTRUCTION
1:25
1 2 3 4 5
0 0.25 0.5 1m
23
THE FOOD HALL
Construction details
24
J. Mezzanine floor & balustrade detail
1. 20x600x600mm porcelain tile
2. 20mm polyethylene matting (Schluter)
3. 20mm fibreboard
4. 95mm floor joist
5. 25mm sylodyn
6. 125mm acoustic insulation with underfloor
heating
7. 250mm CLT floor
8. 25mm Baux acoustic wood wool panels, hung
on suspended grid
9. 15x50mm steel RHS railing baluster
10. 25mm cedar veneered plywood
11. 15x15mm steel SHS (shelf support)
12. 15mm red cedar panel, oiled finish
13. 350x550mm glulam beam
14. 15x55mm steel RHS railing
15. 5mm steel wire
16. 8mm steel ring connector
Detail precedent:
ASI Reisen Headquarters, Natters, Austria, Snohetta, 2020
14 15
10
11
1 2 3 4 5 6 7
12
16
13 8
0 0.25 0.5 1m
25
26
ENVIRONMENTAL DESIGN
27
EMBODIED CARBON OVERVIEW
Key strategies from LETI
Build for the future: adaptability DfMA (Design for Manufacturing and Assembly)
» Using a regular structural grid and a framed structure » Using modular, repeatable façade systems to allow for
to allow for future adaptability off-site construction
» Centralised plant system and plant rooms (e.g. » Using pre-fabricated structural elements (e.g. concrete
centralised MVHR instead of isolated systems) slabs)
» Considering whole life cycle during design » Using pre-fabricated WC pods and kitchen work
stations
28
OPERATIONAL CARBON OVERVIEW
Passive strategies
FOR
MF
0.89
ACT
OR
Urban farming Hybrid ventilation & heat recovery Geothermal & renewables
The incorporation of urban farming elements not only The building is zoned into 3 ventilation zones according to A ground source heat pump is used for radiant heating
contribute to urban greening but also helps improve spatial function. Natural ventilation strategies are adopted and cooling, as it is a low-carbon energy source. BIPVs are
building performance and resource efficiency. More details as much as possible in warmer months, and mechanical integrated into the façade and additional PV panels are
can be found on pg. 94. ventilation with heat recovery is used in colder months. located on the roof to harvest solar energy.
29
NATURAL VENTILATION
Level 2 6°C
In winter, the pivot windows and louvres are closed
to retain heat within the vertical farms. Trickle vents
remain open to let sufficient fresh air in. The air gap
between the two layers of glass heats up due to solar
gains and acts as a barrier to heat loss, which helps
Winter conditions
maintain a warmer temperature indoors.
L1
G/F
Louvres opened
26°C
Zone 1: Mixed mode ventilation
In summer, the pivot windows and louvres are open to
Zone 2: Mechanical ventilation
allow fresh air in. Fresh air displaces the stale air within
Zone 3: Natural ventilation the vertical farms, which exits via the pivot windows at
Summer conditions a higher level.
30
NATURAL VENTILATION
How does a wind catcher work? Wind catcher and stack effect
Louvres on the opposite side of the Louvres automatically open on the side facing
prevailing wind closes prevailing wind to create a negative pressure
inside the building to suck cooler air in Hot air rises to the top, Direction of prevailing wind
eventually escaping from
the roof window
Louvres are closed on On the side facing onto
the sides not facing the prevailing wind, louvres
prevailing wind opened to draw air in
-ve +ve
negative positive
pressure
-ve +ve pressure
-ve
NW NE
>3 mph
>7 mph
>12 mph
SW SE >17 mph
>24 mph
S
>31 mph Above: stack effect in the circulation atrium -
Oxford: southwestern prevailing wind cool fresh air sinks and hot stale air rises
31
MECHANICAL VENTILATION
MVHR duct sizing and layout
Duct sizing is dependent on the air flow requirements and duct cross-sectional Exhaust
area: outlet
Air flow (m3/s) = Air speed (m/s) x cross-sectional area (m2) Fresh air
inlet
Exhaust
Ducts with circular cross sections (as opposed to rectangular cross sections) are
outlet
selected as they allow air to pass through with less friction. According to CIBSE AHU
Guide B (Part 3 - Ductwork), a maximum air speed of 10m/s is allowed. From this Plant Fresh air
inlet
information, the duct sizes for zone 1 and zone 2 can be calculated as follows:
Zone 1:
Air flow requirements given building regulations part F: 10 L/s per person
Assuming maximum occupancy of 100 people per floor:
10 x 100 = 1000L/s = 1m3/s
Cross sectional area required = 1/10 = 0.1m2
AHU
Diameter of ducts = (0.1 / π )0.5 x 2 = 360mm Plant
Zone 2
AHU
300mm Plant
550mm
Diagram above: section showing duct layout in zone 1 (main occupied spaces). Zone 1: Mixed mode ventilation
The runout ducts are designed to run parallel to the primary beams so that they can be directed
back to the main branch located within the service corridor.
32
SERVICES
BAUX acoustic
wood wool panels
Suspended strip lights
MVHR ducts
MVHR branch ducts run parallel to main beams (as illustrated on pg. 84) and connect to
Recirculating extractor hood
the main ducts which runs along the service corridor. The main supply and extract ducts
connect to the AHU units, located in the AHU plant room on each floor.
Lighting grid
Ventilated cable trays run parallel to MVHR ducts and support electric conduits. Strip lights
are suspended from the ceiling and are spaced at 3.5m intervals.
Fire sprinklers
Due to the presence of cooking activities and the open plan of the building, a sprinkler
system will be installed. The sprinkler pipework runs parallel to the MVHR ducts.
Water pipes
Water pipes run vertically in risers and through the service void of floors to the open Water pipes &
kitchen islands and back-of-house kitchens. For more details regarding water systems, electric cables
refer to pg. 37.
Vertical farm as a
thermal buffer
Thermal zoning
Not all parts of the building have the same temperature
requirements. From early design stage, it has been identified
OUTDOORS
that some spaces can be uninsulated and tolerate greater
INDOORS
temperature variations. These spaces include:
Ground floor of the market hall, which is designated for fresh
produce vendors. These products are better sold in an open-
air environment due to moisture and scents.
Vertical farms. These spaces are unoccupied most of the
time and are thermally isolated from the occupied spaces.
Summer, outside temperature 30°C
Buffer spaces
The vertical farms act as a thermal buffer for the indoor
occupied spaces. Although a controlled environment
would benefit plant growth, plants can thrive in a wider
temperature range (compared to a typical indoor space).
OUTDOORS
INDOORS
34
BUILDING FABRIC
U-values
Building fabric performance plays a key part in passive design and helps reduce heat loss and hence operational
energy demand. The building envelope is carefully designed to avoid any thermal bridges: for instance, the use of 2
layers of insulation (rigid and flexible wood fibre) allows the insulation to be lapped to reduce gaps. All construction
build-ups are designed to achieve Passivhaus U-value standards (U ≤ 0.15), as shown in the tables below.
Material Thickness Conductivity Resistance Material Thickness Conductivity Resistance Material Thickness Conductivity Resistance
(mm) (W/mK) (m2K/W) (mm) (W/mK) (m2K/W) (mm) (W/mK) (m 2K/W)
Rse 0.04 Rse 0.04 Rse 0.04
Red cedar cladding 25 0.12 0.21 Red cedar cladding 25 0.12 0.21 Softwood decking 30 0.12 0.25
Void with battens 30 - 0.18 Void with battens 30 - 0.18 void with pedestals 150 -
Waterproof Waterproof Drainage layer 50 0.27 0.19
membrane 5 0.04 0.13 membrane 5 0.04 0.06 Waterproof
Wood Ƕbre Wood Ƕbre membrane 2.5 0.04 0.06
insulation board 40 0.043 0.93 insulation board 40 0.043 0.93 Wood Ƕbre rigid
Wood Ƕbre Wood Ƕbre insulation 220 0.036 6.11
insulation batts 180 0.036 5.00 insulation batts 180 0.036 5.00 Vapour barrier 2.5 0.04 0.06
OSB 15 0.12 0.13 Vapour barrier 5 0.04 0.06 CLT 150 0.12 0.18
Void with battens 40 0.18 CLT 150 0.12 1.25 Rsi 0.13
Red cedar panels 20 0.12 0.17 Rsi 0.13
Rsi 0.13
Thickness 360 Sum 7.127 Thickness 430 Sum 7.864 Thickness 605 Sum 7.021
U-value 0.140 U-value 0.127 U-value 0.142
35
URBAN FARMING
Benefits and synergies
36
WATER SYSTEMS
To allotment
irrigation outlets
Mains supply
Clean water supply Rainwater Recirculating hydroponics/ Storage tanks/ water
Supply outlets Treated grey water drip irrigation system treatment plant
1. Rainwater collection
1.
Rainwater falling on the roof decking or soil substrate passes through the
drainage layer, which removes coarse debris. The water is then brought
down gravity-fed pipelines to the treatment plant for further filtration before
it is stored or fed into the hydroponics system. Rainwater Soil substrate & Mains supply
roof drainage layer
The volume of rainwater collected can be calculated using the equation from 2.
Building Regulations part G (Table A5.1):
Daily rainwater yield =
Collection area x annual rainfall x yield coefficient /365
Collectable roof area = 1077m2
Annual rainfall in Oxford = 660mm = 0.66m Water taps
Yield coefficient of flat green roof = 0.5
3.
Daily rainwater yield = 1077 x 0.66 x 0.5 /365 = 0.974m3 (974L)
Irrigation
(roof garden / allotments)
3. Hydroponics
A drip irrigation system is used for the hydroponics farm and vertical
fruit farms. Drip system is considered the most water efficient amongst
hydroponics systems, and is especially versatile as it can support the
growth of larger plants. It is water efficient because excess water drained
from the hydroponics medium is fed back to the reservoir and continuously
Storage tank Toilets Sewage
recirculated. The water in the reservoir is regularly replaced.
37
Mimi Tam
[email protected]
www.mimitam.myportfolio.com/