Grey Structure Process

The document outlines the key steps and timeline in a typical grey structure process for building construction over 150 days. It involves: 1) Excavation, foundation work, and termite spraying in the first 15 days. 2) Wall construction for the ground floor over days 15-30 and slab pouring on day 35. 3) Repeating wall and slab construction for the first floor from days 55-60. 4) Internal and external plastering, installation of overhead tanks, and other finishing works through day 150 to complete the grey structure.

Uploaded by

bkgboqdraftsman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

Grey Structure Process

The document outlines the key steps and timeline in a typical grey structure process for building construction over 150 days. It involves: 1) Excavation, foundation work, and termite spraying in the first 15 days. 2) Wall construction for the ground floor over days 15-30 and slab pouring on day 35. 3) Repeating wall and slab construction for the first floor from days 55-60. 4) Internal and external plastering, installation of overhead tanks, and other finishing works through day 150 to complete the grey structure.

Uploaded by

bkgboqdraftsman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Grey Structure Process:

Marking For
Foundation

Day-1

Material Excavation Anti-Termite


Procurement for
Day-2 Spray
Foundation

Earth Fill/Back Fill Foundation Still Water Proofing

Preparations DPC DPC

Day 15

Material Earth Fill


Procurement for
Day 20
(Ground Floor Wall)

Steel, Crush, Sand Wall G.Floor Steel Door


Chokhaths
And Other Material Day 30
If Required
Procurement for slab

Slab Pouring

G.Floor

Day 35

Material Curing
Procurement for

(First Floor Wall)


G.Floor Electric & Plumbing
Conduit Wall F.Floor Steel Door
Chokhaths
Day 55
Steel, Crush, Sand & Other
If Required
Material Procurement for
slab

Slab Puring

F.Floor

Day 60

Preparation For Ground Curing Boundary Walls,


Floor Plaster, Fix Saftey
Grill If Required Underground Tanks
& Other Works

F.Floor Electric & G. Floor Internal Construction of


Plumbing Conduit Mumty if Required ,
Plaster Overhead Tank &
Parapet wall
Day-85

Laying Main Sewerage of First Floor Internal

House & Complete Plaster

External Concealed Day -100

Earth Compaction Sides & Rear Material


External Plaster Procurement for
Ground Floor Floor PCC , Order MS
Day 115 Main Gate
Front Elevation Second Stage
Termite Proofing
External Plaster
before Floor PCC
Complete

External Floor PCc Floor PCC Internal Waterproofing, Treatment


Preparations and Material Procurement
Day 130
for Roof Top

Completing Plumbing Completing Roof Floor PCC External


Conduit and Conduction
Day 135
pressure test for leakage

Coonstruction of Conduit Minor Grey MS Gate Installation


Slabs, Bases parution wall
Finishing Touches
wherever required
Day 140

Grey Structure

Complete Day 150