0% found this document useful (0 votes)
111 views

03 Method Statement For Foundation.

This document provides recommendations for installing steel structure pier foundations with stub angles for a 132kV transmission line project in Jizan, Saudi Arabia. It outlines responsibilities for quality assurance personnel, project engineers, foremen, equipment operators, and safety officers to ensure construction activities are performed according to specifications. Safety precautions like using personal protective equipment and developing method statements and hazard identification risks assessments are required. The QA/QC plan specifies that only certified equipment will be used, tower site locations will be clearly marked, and materials and work will be inspected and tested per the client's standards and specifications.

Uploaded by

Ramu Sekar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
111 views

03 Method Statement For Foundation.

This document provides recommendations for installing steel structure pier foundations with stub angles for a 132kV transmission line project in Jizan, Saudi Arabia. It outlines responsibilities for quality assurance personnel, project engineers, foremen, equipment operators, and safety officers to ensure construction activities are performed according to specifications. Safety precautions like using personal protective equipment and developing method statements and hazard identification risks assessments are required. The QA/QC plan specifies that only certified equipment will be used, tower site locations will be clearly marked, and materials and work will be inspected and tested per the client's standards and specifications.

Uploaded by

Ramu Sekar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

Method Statement Lattice Steel Structure

Foundation
Table of Contents
Sl. No. Description Page
1.0 Scope 03 of 13
2.0 Reference 03 of 13
3.0 Responsibilities 03 of 13
4.0 Environmental Control Plan 04 of 13
5.0 Safety Precaution 04 of 13
6.0 QA/QC Plan 05 of 13
7.0 General Requirements for Foundations 05 of 13
8.0 Full Scale Foundation Uplift Test 06 of 13
9.0 Auguring 07 of 13
9.1 Auguring with Casing 07 of 13
9.2 Auguring without Casing 07 of 13
9.3 Auguring & Concreting with Permanent Casing 08 of 13
10.0 Reinforcing Steel Cage 08 of 13
11.0 Form box / Shuttering Installation 09 of 13
12.0 Stub Angles 09 of 13
13.0 Grounding 10 of 13
14.0 Concrete 10 of 13
15.0 Construction Joint 11 of 13
16.0 Curing 11 of 13
17.0 Protective Coating 11 of 13
17.1 Surface Preparation 12 of 13
17.2 Coating Application 12 of 13
17.2.1 Concrete Surface Below Grade 12 of 13
17.2.2 Concrete Surface Above Grade 12 of 13
17.3 Film Thickness and Testing 13 of 13
18.0 Test Cylinders 13 of 13
19.0 Back Fill 13 of 13
20.0 Quality Assurance 13 of 13

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
Method Statement Lattice Steel Structure Foundation
1.0 Scope:

This document provides general recommendations for selection of methods and


procedures that have been found practical for the installation of steel structure
pier foundations with stub angles for CONSTRUCTION OF 132KV OHTL WORKS FROM
ABU QAEED SUBSTATION TO AL HAQU SUBSTATION IN JIZAN.

2.0 References:

All referenced Standards, Specifications and similar material shall be the latest
issue (including all revisions, addenda and supplements) unless stated otherwise.
Standards and Specification:

Bare, Copper –Clad Steel Grounding Conductor and


10-TMSS-05 Rev. 01
Ground Rod
70-TMSS-03 Rev. 01 Normal Weight Ready-Mix Portland Cement Concrete
TCS-Q-113-03 Rev. 01 Cast-In-Place Concrete
TCS-P-122.05 Rev. 0 Steel Structure Foundation
TCS-P-122.21 Rev. 0 Transmission Line Structure Details for 68kV to 300kV
TES-P-122.06 Rev.0 Transmission Structure Foundation
TES-P-122.10 Rev.0 Transmission Line Grounding
PTS-20SO129 Scope of Work and Technical Specification
Standard Test Method for Individual Piles Under Static
ASTM D-3689-90
Axial Tensile Load

3.0 Responsibilities:

The QA/QC Personnel together with approve third party and SEC representative
are responsible for inspection of material, sampling and testing. Closely monitor
the activity for improper use of tools and equipment during execution. Check for
the validity materials, tools and equipment certificates prior to work execution.
Make sure all quality inspection checklists and testing procedures are being
followed on or before work execution as per SEC specification.

The Project/Site engineer is responsible for issuing copy of all related IFC
drawings, HIRA (Hazard Identification and Risk Assessment), installation
procedure, PTW (Permit to Work) and educating the construction crew involve of
the content it pertains prior to work execution. Then closely monitor the Tower
Foundation activities and other related issues as per SEC specification.
The foremen are responsible in facilitating the Tower Foundation activities with
complete needed proper/ correct tools materials and equipment. Conduct tool
box meeting before the work starts, securing the working area with safety

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
barriers, danger/ warning sign and maintaining housekeeping before and after
work execution.

Certified Equipment operators are responsible for the working conditions, such
as proper used of personal protective equipment, equipment maintenance and
operation for everyone safety as per specification and standards.

The safety officer is responsible for inspecting site conditions prior to work
execution to determine if hazards are present, identifies the damaged
equipment, defective tools and to establish procedures and policies to overcome
those hazardous situations for everybody safety. The safety officer inspects the
validity of Technicians, operators, tools and equipment’s TUV/ Calibration
Certificates, then inform for renewal a month before it expires. Has the authority
to stop the activities, if an unsafe condition occurs.

4.0 Environment Control Plan:

The Approved Guidelines for the Noise Level shall be maintained during the
execution of soil investigation and related activities.

During Foundation Works care should be taken to avoid disturbing the natural
sources such as tree/ plant cutting.

Removal of Waste material form the work spot to the store yard shall be
monitored, during and after completion foundation activities.

5.0 Safety Precaution:

Light vehicle shall have 4-wheel drive mode towards tough terrain access.

Qualified and Trained personnel are assigned as per the job requirement.

Required PPE safety shoes, safety goggles inclusive of High visibility Vest shall be
strictly adhered for all working personnel at job site.

Prior to each construction activity, Method Statement and HIRA will be prepared
and issued to the concerned personnel

The Method Statement and HIRA will be clearly explained to every individual
involved.
The Method Statement and HIRA will be signed by the involved personnel and a
copy to be kept at the work spot for any time verification.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
6.0 QA/QC Plan:

Availability of current approved Route Plan drawings indicating revisions shall be


issued to the key personnel at job site.
The proposed Auger Machine should be third party certified before induction at
the site.
The markings along the route shall be cleared indicated in the plotted tower site
locations.
The structure/ tower spotting shall be with required ground & road, power and
pipe line clearances.
The Method Statement, ITP and HIRA will be prepared, issued and get signed by
every individual before every allied activity involved in the foundation work.
QA/QC shall monitor & maintain following activities:
• Qualified and motivated manpower

• Dependable construction equipment.


• Required personnel selected on the basis of their skills and experience.
• Suitable personnel shall be physically and mentally fit.

• Training/ Testing of craftsmen.


• Preparation of procedures and job instructions.
• Construction equipment maintenance/ materials control.

• Verifying contracts documents and specifications and standards.


The QC and Project Engineer shall be present along with Client/ SEC
Representative during inspection.

7.0 General Requirements for Foundations:

It is the responsibility of Raissy to locate underground facilities such as gas,


water, sewer lines, drain lines, electric power and telephone cables, etc., which
may be encountered in digging or drilling holes and to perform work in such a
manner as to prevent damage to such facilities. In case of any damage, the
Contractor shall repair immediately all such facilities, to the satisfaction of the
facility Owner.
The foundations for tangent structures shall be placed so that the longitudinal
axis of the structure cross arms will be lie in a plane perpendicular to the center
line of the transmission line. The foundations for angle structures except the
terminal structures shall be placed so that the cross arms will be lie in a plane
bisecting the interior angle formed by the two intersecting center lines. The

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
footings for terminal structures shall be placed so that the transverse axis of the
structure cross-arms shall be parallel to the transverse axis of the gantry
structures placed in the substation.

Drilling of the pier holes shall be to the depth and dimensions indicated on the
approved drawings.

Top soil, stumps, bad material shall be removed. All excavated materials suitable
for backfill shall be placed in graded embank in the immediate area of the
structure. Materials found to be unsuitable for backfill or grading shall be
disposed of at an approved disposal facility by SEC.

8.0 Full Scale Foundation Uplift Test:

One (1) Tangent type structure and one (1) Heavy Angle type structure pile
foundation for the proposed line shall be carried out prior to final construction of
the foundations.

SEC approved Specialist on foundation testing with adequate experience and


knowledge of foundation testing shall undertake the full-scale uplift load test.

The load testing shall be as per the ASTM D-3689-90 in guide lines with the
Project Standards and Specifications.

All latest calibration test reports for Hydraulic jacks, Load cells, dial gauges and all
load measuring devices that are required /used for testing shall be provided.

Soil pier holes shall be drilled with suitable types of drilling equipment to
produce the required depth of drilling. The methods and equipment used shall
be such as to leave the sides of the drilling free from appreciable quantities of
loose material, which would prevent intimate contact of concrete with firm soil
and/or rock. The bottom of borehole shall be clean so that end bearing of the
footings will be on the firm soil. The borehole shall be protected with a
temporary casing if required of 6mm minimum thickness maintained at a height
of 500mm above existing ground line.

9.0 Auguring

9.1 Auguring with Casing:

In areas, where sufficient ground water is encountered to cause standing water


in the boreholes, if possible, water shall be pumped out from the borehole to the
elevation of the top of the hole and pumping shall be continued as necessary to
ensure placement of all concrete under dry conditions if possible.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
Temporary casings shall be required at all locations of high water table in layers
of fine, collapsible sand. Casings shall also be required at locations where the soil
will not stand alone without support. Casings shall be of sufficient strength and
rigidity to maintain the required verticality of the boreholes against the earth and
water pressures that may be encountered, and shall be installed carefully to
assure that soil around casing is not disturbed. The method of holding casing in
the pier hole shall be such that it will not allow the casing to sink in the ground.

The vibrator-driving hammer shall be used for installation & removal of casings if
the casing depth is more than 10m & in subkha areas. While driving by vibrator-
driving hammer the casing shall be checked for 900verticality. When casing top is
at the proper elevation and the vibrator-driving hammer is removed, the auger
shall be centered over the hole and the soil in the casing shall be removed. The
casing shall be driven until the top is about 500 mm above the structure pad.

It shall be ensured that concrete inside the temporary casing is sufficient to fill
level up to the construction joint before removal of casing and tremmie required
up to the bottom of the borehole is used for concreting.

The steel casing is to be removed; the concrete shall be poured up to the


construction joint. The steel casing shall be removed concurrently with the
placement of concrete.

9.2 Auguring without Casing:

If the pier does not require a steel casing, the auger operator can set up the
center of the cutting blades of the auger so it is centered over the nail or tack of
the foundation center and after checking that it is in plumb both ways on the
Kelly bar, drilling can begin. If the soil is satisfactory and no caving occurs, the
hole can be completed to the required depth and the other holes completed in a
similar manner. The excavated soil shall be kept away from around the boreholes
to permit working and shoring, as well as to keep the soil from slipping back into
the borehole. After completion of the borehole, the steel-reinforcing cage shall
be placed carefully and concreting shall be poured using tremmie required up to
the bottom of the borehole.

9.3 Auguring & Concreting with Permanent Casing:

When Soil is sabkha (frequently water logged) type which is very weak (SPT < 6)
and dicing chemicals are present in high concentration in soil and ground water,
then auguring will be done with permanent casing based on the soil investigation
reports & recommendations.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
10.0 Reinforcing Steel Cage:

The installation of steel reinforcement shall be in accordance with the referenced


specifications, standards and IFC drawings.

The steel rebar shall be covered with tarpaulins at storage yard and at the job
site.

The steel reinforcing bar cage shall either be assembled at the storage yard and
hauled to the job site or the proper steel bars be hauled and assembled at the
job site. Both of these methods shall be acceptable and satisfactory. The vertical
reinforcing bars and horizontal ties shall be spaced and assembled as shown on
the approved construction drawings

The reinforcing bar cage shall be properly located and held in position by using
concrete blocks of proper dimensions 75 x 75mm Size and wired into place at
about 750 mm to 1000 mm intervals on the outside of the cage. They shall be
placed in several locations around the cage to position the cage in the center of
the hole.

Reinforcement bars (re-bars) shall be carefully formed to the dimensions


indicated on the approved construction drawings. All re-bars shall be bent cold
before being placed in the forms. Re-bars with kinks and bends shall not be used.
No heating of re-bars shall be permitted. Re-bars shall be accurately positioned
and secured against displacement by using annealed iron wire of suitable size at
all intersections.

Pier cages shall be made, as described in the approved construction drawings. No


visible deformation of the cage shall be allowed. The cages shall be accurately
positioned and secured against displacement during the placement of concrete.
The method of securing pier cages shall be such that it will not allow the
reinforcement to sink in the ground.
Steel cage should be bind tightly and balance installation of lifting sling to
prevent deformation and displacement during lifting activity. Upon insertion of
the steel cage to the steel casing, steel hook is being used to support steel cage
attached to steel casing to prevent settling.

Fabrication and bending, where required, shall be in accordance with the


approved drawings and within the tolerances cover as -12.5mm and longitudinal
location + or – 50mm for bends and discontinuous end shall be + or -12.5mm.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
11.0 Form box / Shuttering Installation:

Form box/ Shuttering shall be installed before concreting. Structural calculation


shall be done before the fabrication of form box/ shuttering to determine the
thickness of the steel plate, the capacity of the block out and the capacity of the
bolts as stiffeners. After all calculation are made and probed to be safe,
fabrication shall start.

Installation of form box/ shuttering shall be supervised by a competent person.


The plumpness of the shuttering shall be checked and all the block out shall be
checked if properly installed based on approved structural calculations.
Scaffolding shall be installed for easy access of the workers.

12.0 Stub Angles:

Stub angles shall be placed in the tower footings as shown on the approved
drawings, and shall be supported in proper position by means of a rigid template.
The stub angles shall be held rigidly in a manner to prevent displacement during
placing of the concrete. All stub angles shall be set accurately to the grade and
alignment indicated on the approved drawings with a tolerance of horizontal
distance between stubs of 10 mm in diagonal and 5 mm in tower face.

The stub angles and the setting template shall be assembled together into place
to obtain proper setting location for each stub angle. The stub angle setting
template shall be furnished as part of the steel furnished by the steel supplier or
shall be fabricated separately for the intended purpose. The templates shall be
adjustable for different spacing and batter as required for tower type under
construction.

The concrete shall be poured after all the adjustments and checks have been
made as required. The top surface shall be crowned and given trowel finish.

13.0 Grounding:
All grounding requirements shall be in accordance with the SEC Standards TES-P-
122.10 and TCS-P-122.21. All grounding materials shall be Copper clad steel.

The conductor for bonding foundation stub angle with the rebars and ground rod
prior to concreting shall be coated with two (2) coats of coal tar epoxy and
mastic taped. Grounding conductor connected from the stub angle to the ground
rod shall be embedded in the concrete foundation and buried 500mm from the
ground level.

The grounding of the terminal structure (last structure before the gantry take-off
structures) shall be connected to the substation

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
14.0 Concrete:
Concrete shall conform to severe exposure condition per the requirements of
PTS-20SO129, 70-TMSS-03 (Rev.01) and TCS-Q-113-03 (Rev. 01).

SEC-SOA approved ready mix concrete company shall provide the required
concrete for Ist stage & IInd stage concreting.

The measuring mixing and placing of concrete shall conform to the latest
requirements of ACI 318 and ACI 304. Concrete shall have a minimum 28-day
compressive strength of 38 MPa based on testing of cylinders by third party
testing agency. Required slump shall be 175 + 25mm. Water cement ratio shall
be 0.36 (maximum).

For Ist stage concreting hopper with tremmie pipe up to the bottom of the pier
shall be used for directing the flow of concrete down the center. Concrete shall
be consolidated by use of vibrators of required size up to the bottom of the pier
in dry condition.

For IInd stage concreting, the form shall be kept in good condition until placement
of concrete is completed. The placing of concrete shall be accomplished with
0.3m tremmie pipe to prevent segregation of the aggregates. Concrete shall be
consolidated by use of vibrators of required size to ensure good compaction of
the concrete into a dense homogeneous mass without honeycombs.

If groundwater is up to 2m head from the bottom of the pier, it will be pumped


out with a dewatering pump, before starting of pouring concrete with tremmie
or using concrete pump. If groundwater is more than 2m head from the bottom
of the pier, or not able to drain out the water with dewatering pump, concrete
will be poured continuously with tremmie or using concrete pump, the excess
water/concrete slush will be flow off at ground level till good mass concrete is
seen at top of pier. Stability of boreholes shall be ensured during concreting &
prior to poring. The overflow water shall be discharged to settling pit and
allowed to recharge / evaporate as explained in the attached method statement.

Excess water and concrete sludge will be drained to settling pit. The dimension of
the settling pit will be having an approximate dimension of 3 meter width, 4
meter length and 1 meter depth.
All concrete, which has not been placed within the allowable time after all the
ingredients have been introduced into the mixer, shall be rejected. The
temperature of the mixed concrete shall not exceed 32°C.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
15.0 Construction Joint:

During 1st Stage concreting the concrete shall be poured and stopped at the level
of construction joint &the construction joint key shall be installed as shown in
the approved drawings.

Nitobond EP or equivalent approved bonding agent shall be used for the cold
joint during IInd stage concreting in compliance with approved manufacturer’s
Data Sheet.

16.0 Curing:
The curing shall be carried out in accordance with project specification PTS-
20SO129 and SEC-SOA Standard TCS-Q-113-03 (Rev. 01) & TCS-P-122-05 (Rev. 0).
Once the second stage is completed and form box is completely stripped, the
concrete pedestal will undergo curing. The concrete pedestal will be wrapped
with 2 layers of burlap sacks and water will be sprayed on it. To maintain the
moisture of the burlap sacks, a plastic drum full of water with a very small hole in
it for the water to drain in form of drops. The plastic drum will be refilled daily.
The concrete pedestal will be cured for 21 days.

17.0 Protective Coating:

The protective coating shall be carried out in accordance with project


specification PTS-20SO129 SEC-SOA Standard TCS-Q-113-03 (Rev. 01) &
TCS-P-122-05 (Rev. 0).

Concrete foundation shall be applied with the following concrete protective


coating materials, a minimum of thirty-five (35) days after concrete placement.
Manufacturer’s recommendation shall be strictly followed in all aspects of
surface preparation, priming, coating application (first and succeeding coats and
interval therein) and curing and safety practices.

The protective coating shall be prepared with the following steps:

17.1 Surface Preparation:

The surface to be coated shall be prepared prior to application of the coating


material. Surface cracks, shallow spalls and holes on the concrete surface shall be
filled with mortar. It shall be repaired by cutting “U” grooves using chisel or
similar tools. The surface shall be free of dirt, loose materials, laitance, oil,
grease, wax black-white carbonate deposits and yellow-white sulphate deposits
and other deleterious materials shall be removed from the surface to reach solid
gray concrete underneath.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
17.2 Coating Application:

17.2.1 Concrete Surface Below Grade:

Below grade surface of concrete shall be coated with minimum of two (2) coats
of coal tar epoxy. The second coat shall be applied within the time interval
(between successive coating application) specified by the manufacturer.

The application of coal tar epoxy will depend upon the type of concrete
foundation adopted by the contractor. For open excavation (spread footing, pile
cap), all concrete surfaces in direct contact with the earth shall be applied with
coal tar epoxy. For augured pier type foundation, coal tar epoxy shall be applied
from the last construction joint or bottom level of the anchor bolt or stub angle
up to the structure pad finished grade level.

17.2.2 Concrete Surface Above Grade:


All exposed surfaces above structure pads grade level shall be coated with
elastomeric materials (polyurethane water-proofing membrane). The coating
application shall extend continuously down to 500 mm below structure grade
level. This coating shall be applied after curing of the coal tar epoxy. Coating
materials shall be either spray-applied or brush applied.

The interface between the steel monopole and the concrete foundation shall be
properly coated with polyurethane coating membrane and shall extend 500 mm
above the top of the non-shrink grout. Similarly, the steel stub angles/concrete
foundation interface shall be covered with polyurethane coating membrane and
it shall extend 500 mm above the top of foundation.

17.3 Film Thickness and Testing:


The total dry film thickness (DFT) shall be obtained upon application and
subsequent curing shall be:
• Above Grade Application: 1 mm for the specified material (Priming Coat and
Subsequent Coats (except top coats), Aromatic Formulation = 500 microns
DFT. Top Coat, Aliphatic Formulation = 500 microns DFT.
• Below Grade Application: 0.6 mm for the specified material (A two-
component, high-solids coal tar and epoxy resins).
18.0 Test Cylinders:
Concrete cylinders shall be filled and witnessed by the Project Manager & RAISSY
QC and testing shall be made by SEC-SOA approve Third Party Independent
Testing Laboratory, in accordance with ASTM C39, 'Standard Test Method for
Compressive Strength of Cylindrical Concrete Specimens" & as per project
specification & Standards.

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022
19.0 Back Fill:
The backfilling shall be in accordance with project specification PTS-20SO129
SEC-SOA Standard TCS-P-122-05 (Rev. 0).
20.0 Quality Assurance:
Assurance of inspections for both materials and workmanship at each stage of
the work, focusing attention on such items:
• Establishment of correct location for the structure (span length, radial
distance, elevation etc.)
• Type of structure, height of basic body and leg/body extensions etc.
• Suitability of location for the proposed type of foundation
• Method of Statement, ITP and HIRA
• IFC Drawings, Standards and Specification
• SEC Representative will be informed for inspection/witness on each stage of
concrete and testing
• Suitability of excavated material for backfill

• Excavation depth, casing depth


• Setting of templates and placement of stub angles/anchor bolts
• Distance between adjacent and diagonally opposite stub angles

• Stub angle slope / batter


• Quality of concrete, pouring, testing & curing

Contractor: RAISSY HGPT Co. Ltd. Client: SEC-SOA


Project Title: Construction of 132Kv D/C OHTL Between Abu Qaeed 132kV S/S and Al Haqu ContractNo.4400016383
132kV S/S
Document No.: RAISSY-WMS/WP-03 Issue No.: 01 Rev. No.: 00 Date: 20.06.2022

You might also like