Internfinalreport 170201060447
Internfinalreport 170201060447
Quality
&
EHS (Environment Health and Safety)
Of
Submitted to
K.P.SREEHARI
(Head Quality and EHS)
Submitted by
Bachelor of Technology,
Civil Engineering,
CERTIFICATE
This is to certify that the report titled “Quality and EHS (Environment
Health and Safety) of Hyderabad Metro Rail Project “has been
prepared and submitted by BANALA BHANU PRASAD a bonafide
student of National Institute Of Technology, Warangal which embodies
the work done by him under my supervision.
Internship Coordinator:
1
Hyderabad Metro Rail Project
ACKNOWLEDGEMENT
This internship has been a very good experience for me in the way that it has
given me the chance to understand the real world outside the classroom. I’ve
learnt a lot about the office environment and site environment and my
interpersonal skills & self-confidence have improved significantly.
I would like to thank Mr. Sudioto Lahiri, Head, Human Resources Department, L
& T Metro Rail (Hyderabad) Limited for giving this opportunity to do internship in
the prestigious organization under Metro Rail Project.
I express my sincere gratitude to Mr. K.P. SREEHARI, Head Quality and EHS, L & T
Metro Rail Hyderabad Limited, for sharing his great experiences, exemplary
guidance, continuous monitoring and constant encouragement throughout the
course of internship.
I would take this opportunity to thank Mrs. KOWSALYA T.S. Assistant General
Manager, S.N.SRINIVASA SARMA, Manager and PRAKASH KUMAR.R, Safety
Manager whose help and support made possible the successful completion of this
internship project.
I thank Dr. C.S.R.K. Prasad, Professor and Head, Transportation Division, Civil
Engineering Department, NIT, Warangal for his cooperation and encouragement
for taking up a summer internship.
I also thank Mr. Indranil, Chief Surveyor and Mr. Rashpal, Head Quality, L & T
Infrastructure IC, for their support to learn the surveying methods and the quality
control methods, tests in the quality lab, etc.
I specially thank all the people whom I met during the course of internship for
sharing their knowledge, experience and helping me to learn the procedures and
processes adopted in the execution of the project.
2
Hyderabad Metro Rail Project
Index
1. Introduction……………………………………………………………….…………01
2. Need for Metro Rail System in Hyderabad………………….………..01
Formation of HMRL
Financing the Project
Manual of Specifications
3. Project details…………………………………………………………….…………03
4. Concession Agreement…………………………………………….…………..05
5. L & T Metro Rail (Hyderabad) Limited…………………….…………….10
6. Quality Management System & EHS……………………………………..18
7. Surveying………………………………………………………………………………17
8. Geotechnical investigation…………………………………………………..21
9. Design of The Super Structure……………………………………………..24
Foundation
Piers
Segments
Stations
10. Casting Yards…………………………………………………………………………27
11. Quality Control Lab……………………………………………………………….28
Materials tested in the lab
Equipment present in the lab
12. Batching Plant……………………………………………………………………….31
13. RMS (Ready Made Steel) Plant………………………………………………32
14. Construction of Piers…………………………………………………………….36
Marking for foundation coordinates
Laying of CLSM
Construction of foundation
3
Hyderabad Metro Rail Project
Construction of pedestal
Starter of the pier
Pier/ pier cap
15. Segments casting…………………………………………………………………42
Formwork for segments
Reinforcement of segments
Sheathing and fixing of guide cones
Surveying
Procedure for casting of pier head segments
Procedure for casting of segments in long line
Parts of the segment
16. Parapets………………………………………………………………………………50
17. Erection of Segments…………………………………………………………..51
18. Stressing of Segments………………………………………………………….53
19. Cast in-situ spans………………………………………………………………...55
Punjagutta cast in-situ span
20. ROB (Rail Over Bridge)………………………………………………………….58
21. Stations…………………………………………………………………..……………59
Important components of stations
Construction of stations
Application of sealants
22. Track work…………………………………………………………………………….66
23. Rolling stock………………………………………………………………………….67
24. Depots…………………………………………………………………………………..69
25. Conclusion…………………………………………………………………………….71
4
Hyderabad Metro Rail Project
Introduction:
Hyderabad is the state capital of Telangana. It is centrally located on the top of
Deccan Plateau. Hyderabad is underlain by pink and grey granites. It has
undulating topography with varying elevations ranging from 460m to 560m Mean
Sea Level (MSL). It falls in Zone II (low seismic zone), with a zone factor of 0.1.
Hyderabad is a mega city covers 625 sq.km of municipal area and has population
of 11.8 million.
Based on the success of the Mass Rapid Transit Systems (MRTS) internationally
the government of Telangana consider the implementation of a MRTS to be the
best solution for Hyderabad. Based on the PHPDT (peak hour peak direction
traffic) Metro rail was selected for Hyderabad. Metro rail has the capacity to carry
30,000 passengers PHPDT.
Formation of HMRL:
To construct elevated Metro Rail System in three high density traffic corridors of
Hyderabad, the government of Telangana and Municipal Administration and
Urban Development Department formed an organization Hyderabad Metro Rail
5
Hyderabad Metro Rail Project
Limited (HMRL) for undertaking Hyderabad Metro Rail Project. Hyderabad Metro
Rail Ltd is the owner of the project.
Hyderabad metro rail limited decided to develop the project on DBFOT basis in
PPP mode. The HMR project is the world’s largest project under Public Private
Partnership, with investment of over Rs17000 crores. Typically a Public Private
Partnership (PPP) involves a contract between a public sector authority
(Concessioning Authority) and a private party (Concessionaire), in which the
parties jointly share substantial financial, technical and operational risk in the
shareholders of SPV usually consists of the Contractor(s) companies as well as a
major partner (Financial Body). SPV arranges finance for the project with internal
and/or external investors. The sources of funds for a PPP project include private
capital (loans), government (both state and central govt.) funding a unique
package by way of VGF (Viability Gap Funding) equity of 30% of the total project
cost as capital to meet the funding gap, other funding sources include
property/real estate development on state/central government’s property
granted for long term lease to developers. A consortium of 10 banks led by State
Bank Of India sanctioned the entire debt requirement of the project.
Manual of specifications:
6
Hyderabad Metro Rail Project
Figure 1: Flow chart showing the relationships of the government, client and
independent engineer.
Project Details:
The Hyderabad Metro Rail Project in its first phase has a total rail corridor length
of 71.16km with 66 stations and comprises elevated viaduct structures over its
complete length. The project is divided into three high density traffic corridors.
7
Hyderabad Metro Rail Project
8
Hyderabad Metro Rail Project
Concession Agreement:
Government prescribed the technical and commercial terms and conditions and
invited bids (the Request for proposals RFP) from the bidders shortlisted pursuant
to the RFQ for undertaking the project.
After evaluation of the bids received, Government accepted the bid of Larsen and
Toubro Limited and issued its Letter of Award (LOA).
9
Hyderabad Metro Rail Project
L & T incorporated a Special Purpose Vehicle (SPV), L & T Metro Rail (Hyderabad)
Limited (LTMRHL) to implement the Project on Design, Build, Finance, Operate
and Transfer (DBFOT) basis. L & T Metro Rail Hyderabad Limited signed
concession agreement with government of Telangana on 4 th September 2010.
10
Hyderabad Metro Rail Project
Performance security is effect for a period of one year, but shall be released
earlier upon the concessionaire expending on project construction an
aggregate sum that is not less than 20% of the total project cost.
Right of way:
The concessionaire has given rights on the site, license, access and right of
way.
- Procurement of site.
11
Hyderabad Metro Rail Project
12
Hyderabad Metro Rail Project
- Concessionaire should look after the safety of the works, provide safety
environment on or about the rail system.
- Expenditure on safety requirements shall be borne by the
concessionaire.
- Safety certificate prior to COD: The government not later than one year
prior to the scheduled completion date on the likely COD notified by the
concessionaire, as the case may be appoint commissioner of railway
safety under applicable laws to observe any or all the tests.
Traffic census and sampling:
- Traffic census and train operations shall be done by the concessionaire.
- Traffic survey, traffic samplings are done by the concessionaire.
- Computer systems and networks are installed by the concessionaire.
Independent Engineer:
- Government appoints Independent Engineer.
- Independent Engineer shall submit regular reports to the government
on the project.
- Remuneration is paid by the government and termination of the
appointment shall be done by the government or by the concessionaire.
ISO 9001:2008
13
Hyderabad Metro Rail Project
L&T incorporated a Special Purpose Vehicle (SPV) L&T Metro Rail (Hyderabad)
Limited (The Company) to implement this Hyderabad Metro Rail Project on
Design, Build, Finance, Operate and Transfer (DBFOT) basis. This company is a
subsidiary of L&T Infrastructure Development Projects Ltd. (IDPL) an
infrastructure development arm of Larsen & Toubro Ltd.
The special purpose vehicle LTMRHL has setup a quality management system
based on ISO 9001: 2008. This international standard promotes the adoption of a
process approach when developing, Implementing and improving the
effectiveness of a quality management system, to enhance customer satisfaction
by meeting customer requirements.
Project control: Deals with the cost estimation and time management of
the project
Quality Management & EHS: Responsible for maintaining quality
management system in the organization and to ensure the project to
complete on time, within budget, and confirming to International Standards
of Health and Safety aspects.
14
Hyderabad Metro Rail Project
15
Hyderabad Metro Rail Project
Finance & Account: All the financial matters and accounts are dealt with
this department and maintain the accounts.
Legal & Secretarial: Interacts with board of directors of the company,
handle all complaints of stakeholders, resolute and comply the legal
aspects of the project with governing bodies.
Human Resources & Administration: Arrange human resources where
required, motivate employs to get organizational growth.
Administration: Arranges travel, accommodation, and transport for
executives, maintain relations with news media, networking with
government agencies.
Corporate Communication & Advertising: Deals with the advertising of
corporate companies in the stations, rolling stock, viaduct and
communicating with them.
Information Technology: Ensures IT infrastructure supports all network
facilities. Identifies and sources all IT application that would be best suited
to the organizations business requirements. Provides technology vision and
leadership for developing and implementing IT initiatives.
Administration others: Looks after the services like security, drivers,
pantry, Soft services and facilities for the organization.
16
Hyderabad Metro Rail Project
L&T believes that no job or no task is more important than worker health and
safety. The company’s prestige lies in the safety measures followed by the
company to avoid accidents to the workers. If a job represents a potential safety
or health threat, every effort will be made to plan a safe way to do the task. An
EHS management system is established in this organization to prepare safety
manuals and make everyone to follow them while doing any activities in site/work
place. Top management is responsible for the safety management system to be
maintained in the organization. The company has set some safety policies and
implementing them by providing all the safety requirements.
In the safety manual guidelines are set to ensure that adequate safety
precautions to be taken to avoid accidents, harmful effects while doing an
activity.
17
Hyderabad Metro Rail Project
For a project quality, time/cost and safety are three important aspects. Those
three are like the sides of a triangle, even if we remove any one side it doesn’t
complete a triangle.
A safety manual is prepared and in that manual guidelines are given to ensure
that adequate precautions to be taken to avoid accidents, harmful effects and
occupational health while doing any activity.
These guidelines should obey certain legislation, laws and Indian statutory
requirements. Few of them are:
The three terms which we usually see in the safety manuals are:
18
Hyderabad Metro Rail Project
2. Hazard:-A situation with the potential to cause harm includes human injury,
damage to property, plant or equipment, damage to environment or
economic loss.
3. Risk:-It is a chance of something adverse happening and its severity. It is
the combination of probability or frequency of likelihood the occurrence of
a defined hazard and the magnitude of consequences of the occurrence.
Fire: Fire is a chemical reaction formed by the combination of heat, fuel and
oxygen. Without any one it cannot happen.
Fire is categorized into different classes: Class A, Class B, Class C, Class D and
Class E based on the type of fuel involved in the fire. For different types of classes
different fire extinguishers should be used. For example if the fire is caused by
shock circuit we should not use water to put off fire, it is very dangerous. And for
fire caused by flammable liquids we should not use water, we have to use foam or
some other things which should not spread the fire.
Before allowing the workmen to work in the site workmen safety induction,
workmen screening, P.P.E. (personal protection equipment) are given. Safety
induction like pep talks, tool box talks are given frequently in the morning to the
workmen by Safety Incharge. For every work to be carried out permit system
19
Hyderabad Metro Rail Project
should be followed, when it is on roads permission from the traffic police has to
be taken. Without work permit no one is allowed to do the job. Every
incident/accident is recorded and proper investigation is done to take preventive
measures so that the same incident/accident will not occur.
All the reportable accidents are reported and used in calculating accident
frequency rate.
Total man hours worked is the product of number of workmen and the total
number of days and the hours worked by each workman.
Accident frequency rate is the number of reportable accidents per one million
man hours worked.
EHS committee meeting will be held within every month, where all the SHE
committee members will be discussing and finding solutions to different problems
facing by workers, sub-contractors, etc. The main aim of this committee is to
achieve zero accidents/incidents.
SURVEYING
A great survey has been done for the fixing of alignment in the three corridors
and establishment of DGPS/DGNSS based Main Reference Station, Traverse
Reference Station (Network Pillars), Primary and Secondary Ground Control
Points (Primary and Secondary Pillars) all along the proposed Hyderabad Metro
Rail Corridors.
Procedure:
Initially all the three metro corridors had been inspected to assess the suitable
locations for the establishment of primary and secondary pillars and other work
related logistics. Satellite images were used for fixing the Traverse Reference
Stations. These stations are decided on the basis of Geography, safety and
distribution of all the three proposed corridors.
21
Hyderabad Metro Rail Project
Master Reference Station is important and for the safety purpose it is established
in Cyber Gateway tower in Hitech City which is owned by L&T. For better accuracy
of MRS readings were recorded continuously for 36 hours with the help of two
receivers at two different locations from the same set of satellites.
During DGPS observations the following points were observed for better
accuracy:
22
Hyderabad Metro Rail Project
Observation of all traverse reference station was carried in the form of well-
formed and closed network of triangulation. For safety purpose additional
Traverse pillars are established. Pillars of the required dimensions are
constructed. For the purpose of height control of these pillars these are
connected to well establish bench mark situated at Survey of India Campus,
Uppal.
Primary and Secondary control points were established all along the alignment of
the three corridors with the help of DGPS/DGNSS and total station. These pillars
are constructed in a way that inter-visibility between pair of pillars, safety of the
pillars is considered.
These Primary DGPS control points were concrete pillars with 50X50 cm and
Secondary Control Points were concrete pillars with 15X15 cm. All Traverse
Reference Stations, Primary Control and Secondary Control Points possess a
23
Hyderabad Metro Rail Project
minimum of 60cm height and embedded upto minimum depth of 45cm into the
ground (15cm protruding above the ground). Steel plates are used for reference
position was grit/sand blasted and then coated with one coat of metallic primer
and two coats of epoxy paint. In order to ensure the accuracy of positional
reference, reference point on the base plates were made through machine cut.
24
Hyderabad Metro Rail Project
GEOTECHNICAL INVESTIGATION
As the project is to construct the elevated metro rail system the soil conditions
should be well known.
The geotechnical investigations have been carried out all along the proposed
three corridors in two phases.
1. Preliminary boreholes and
2. Confirmatory boreholes.
These holes are driven based on different codes and specifications.
Preliminary boreholes have been drilled along the alignment at spacing of
approximately 100mts. The depth of these boreholes ranges from
approximately 6.0m to 17.0 m.
150mm diameter bores were advanced using rotary drilling techniques.
Standard penetration tests have been carried out at typically 1.0m to 1.5m
spacing. Cores of rock strata were recovered and total core recovery and
rock quality designation values have been reported.
Laboratory tests were done on representative soil samples from the split
spoon sampler for classification.
On rock cores both uni-axial compression tests and point load tests have
been carried out on both soaked and unsoaked specimens. Chemical
analysis has been carried out for pH, chloride, sulphate, carbonate and
salinity content.
Confirmatory boreholes have been driven at the pier locations, for these
boreholes SPT N values for soil and completely weathered rock strata and
CR and RQD for rock strata are available. Laboratory test results are not
available for the confirmatory boreholes.
During the geotechnical investigations water table was not met in any of the
boreholes, with max depth of boring being about 17.5m below ground level.
The soil profile is completely weathered rock underlain by granite bedrock.
At some locations boulder layers have also been observed.
Based on the type of strata encountered during investigation different codes
have been adopted for calculating the bearing capacity.
The weathering of rock mass is classified into six grades:
Grade I, Grade II, Grade III, Grade IV, Grade V and Grade VI based on the degree
of weathering.
25
Hyderabad Metro Rail Project
Sand Strata: Here only dense and very dense sands (with SPT N values greater
than or equal to 30) are considered for as suitable for open foundations.
Angle of shearing resistance of sand is estimated using the correlation with SPT N
value as per code of IS 1640 Determination of breaking capacity of shallow
foundations.
26
Hyderabad Metro Rail Project
Residual soils with N< 60: These soils are cannot be considered as intermediate
geomaterials as per IRC: 78 Notification number 68. Young’s modulus is calculated
as per this code for these types of soils.
Trial pits: Trial pits are dug usually during site investigations. These are dug at
90m c/c distance through the existing road median to identify the utilities in the
sub surface. The area of the trial pit is 9.0m along the road X 6.0m across the
road. Excavation upto a depth of 2.5 m is done. This area is barricaded as per
Construction Work Procedure for safety Barricading. If any utilities are identified
the further excavation is stopped and LTMRHL is initiated. During excavation care
should be taken that underneath utilities ate not get damaged. The excavated
material should be disposed off in a suitable place. After excavation this pits were
filled with backfill as explained in the Construction Work Procedure.
27
Hyderabad Metro Rail Project
28
Hyderabad Metro Rail Project
Piers:
Where ever plan alignment of the elevated guide way is not matching with central
median, cantilever pier shaped (reinforced) pier or portal beam with piers resting
on central median / footpath shall be provided. Such portal shaped beams shall
generally be monolithic with piers at its both ends. There are five types of piers
are constructed.
1. Normal pier (Circular and Rectangular): A normal pier is the standard pier
which is the usual support provided for the viaduct. It is also called an
intermediate pier. Circular pier are constructed in the Moosi river places.
29
Hyderabad Metro Rail Project
30
Hyderabad Metro Rail Project
31
Hyderabad Metro Rail Project
CASTING YARDS
There are two casting yard for casting of segments. 1. Uppal Casting Yard and 2.
Miyapur Casting Yard. Except construction of foundations and erection of piers on
site rest of the works are done in the pre casting yards and erected in the sites.
32
Hyderabad Metro Rail Project
corrections and the batching is done in the mixer and discharged into the
concrete transit mixer. Before dispatching to the site the concrete is tested and
before placing it inside the structure the concrete is tested.
33
Hyderabad Metro Rail Project
34
Hyderabad Metro Rail Project
BATCHING PLANTS
Working of batching plant: There are two concrete batching plants of L & T
infrastructure Independent Company in Uppal pre casting yard CP 60 and CP
30.
CP 60 batching plant has a capacity to produce 60 cubic meters of concrete in
one hour and CP 30 has a capacity to produce 30 cubic meters of concrete per
hour. The batch size of CP 30 is 0.5m3 and for CP 60 is 1m3. Each plant consists
of three storage silos of 100MT- two silos for cement and one silo is for fly ash.
A chiller plant is also there to supply chilled water to the batching plant. These
plants are calibrated once in 30days.
35
Hyderabad Metro Rail Project
36
Hyderabad Metro Rail Project
37
Hyderabad Metro Rail Project
38
Hyderabad Metro Rail Project
39
Hyderabad Metro Rail Project
Gantry cranes: Three gantry cranes are present in this RMS plant two are of
5tons capacity and one is of 10 tons capacity. These are used for loading
and unloading of the bars from the trolleys and distributing to the casting
yards.
40
Hyderabad Metro Rail Project
CONSTRUCTION OF PIERS
1. Marking of foundation coordinates.
At first survey works has to be carried out on the live road and with the
help of Total station and the control points on the road the barricading line
is marked, then the foundation corners coordinates are marked for
excavation.
For the construction of foundation the coordinates of the foundation are to
be taken from the design team. Statutory work permits are obtained from
the traffic police department, Greater Hyderabad Municipal Corporation
and other Government bodies.
Marking of open foundation as per coordinates shall be done as per the
GFC drawing at site in the barricading zone by lime powder before start of
excavation. Excavator/ Pneumatic equipment shall be used to excavate the
earth crust.
No excavated soil shall be kept near the excavated area.
Excavation shall not be done till PCC bottom, i.e., the excavation shall be
done 100 mm above bottom level of PCC by mechanical excavator.
Remaining depth till the PCC bottom shall be excavated manually. Surface
shall be compacted and leveled manually by sprinkling water and making
the area free from any loose particles.
2. Laying of CLSM:
After the excavation has been done to the required depth as indicated in
the drawing, the geologist will inspect the foundation and will co-relate
41
Hyderabad Metro Rail Project
with the data observed during the confirmatory bores with the actual strata
observed at site and shall confirm the foundation level. The geologist then
allows site to proceed with PCC or CLSM through a checklist prepared by
him.
CLSM: Controlled Low Strength Material is first time used in metro rail
projects. This CLSM is prepared in batching plant and transported to the
site as per CWP.
The controlled low strength material shall attain 5MPa strength at 28days
when the cube of size 100mm X100mm X 100mm is tested as per IS-516.
The suggested mix design for CLSM is given below.
42
Hyderabad Metro Rail Project
Reinforcing steel shall conform to the dimensions and shapes given in the
approved Bar Bending Schedules.
The reinforcement is tied at every intersection with GI binding wire (min 18
Gauge).
The reinforcement is arranged as per drawings given by the designer and
after completion inspection has to be made by the client then concreting is
done.
Lap length shall be as given in the GFC drawing and shall be staggered.
Couplers may be also be used. Wherever used, couplers shall be staggered
at least by the distance of lap length shown in drawings. Only cover block
made of grout / concrete shall be placed at suitable locations to maintain
clear cover.
Shuttering is done as per CWP and to avoid leakages of cement slurry foam
or masking tapes is used at the corners. Shuttering is free from foreign
materials and coated with mould releasing agent.
Concreting is done after inspection of the form work and the
reinforcement.
4. Construction of pedestal:
Starter for pedestal shall be fixed with foundation shutter and same for pier
shall be continued during pedestal operation.
Cover blocks shall be provided in between surface of formwork and
reinforcement.
Check for the coordinates by surveyor and inspection for reinforcement is
done.
43
Hyderabad Metro Rail Project
Concreting M35 is done for the pedestal and after attaining sufficient
strength the shuttering is removed.
The exposed reinforcement is coated with the slurry of inhibiter solution
for protection against rusting.
Construction joint shall be prepared by cleaning by an air-water jet or wire
brooming on the concrete which is still soft enough that laitance can be
removed, but hard enough to prevent aggregate from loosening. If the
concrete for some reason is set before the construction joint preparation,
then in such situation the joint shall be prepared using a wet sand blast or
ultra-high-pressure water jet.
5. Starter of the pier:
The pier is constructed in stages.
The reinforcement is done in the site, the cut and bent bars are brought
from the RMS (readymade steel plant). Stirrups and links shall be tied with
main vertical reinforcement at specified spacing as per GFC drawing.
HDPE pipe of dia. 160 mm dia. as shown in the drawing shall be placed at
the center of the pier as drainage spout with outlet flushing with the one
side of pier shutter as per approved drawing and the other end protruding
above the pedestal top.. The drain pipe shall be held in place with a link or
ring tied to the reinforcement at 1 m interval. The drain pipes shall be
joined using couplers with snap fit.
The height of the starter is based on the height of the pier, Starter
formwork shall be fixed with supporting arrangement as per system
formwork document.
Cover of 50mm is placed at regular intervals.
Earthing rod with plate shall be placed as shown in the GFC drawing and
welded as per drawing.
The starter shutter shall be checked for its axis coordinates.
44
Hyderabad Metro Rail Project
45
Hyderabad Metro Rail Project
side of pier shutter as per approved drawing and the other end protruding
above the pedestal top.
SEGMENTS CASTING
46
Hyderabad Metro Rail Project
Segments are the basic building blocks which make up the entire viaduct
structure; they are of box girder type, trapezoidal shape with a hollow space in
between. Segments are casted in the pre casting yards by L&T Infrastructure
Independent Company (a contractor of LTMRHL). There are two casting yards
present in this project one in Uppal casting yard and the other in Miyapur casting
yard. M45 grade of concrete is used for casting these segments. The concrete for
Uppal casting yard is supplied from the concrete batching plant located there.
There are four types of segments in used in this project. 1. Pier head segments, 2.
Intermediate Segments, 3. Station Segments and 4. ROB segments.
Typical sequence of segments of a 31 meter span is:
47
Hyderabad Metro Rail Project
Outer shutter: For long line moulds outer shutter is fixed on both sides of
the soffit and it is fixed providing locking arrangements and it can be moved
in with the help of turn buckles.
48
Hyderabad Metro Rail Project
Inner form: The ventral void is achieved in the segment with the help of
inner form. It has turn buckles for shuttering and de-shuttering and hinges
to resist the concrete pressure load during curing.
Bulkhead panels: Bulkhead panels are used for casting pier head segments
and these are placed on both sides. These are arranged with the help of
gantry cranes. These are supported by turn buckles.
49
Hyderabad Metro Rail Project
Reinforcement of segments:
TMT Fe500 bars are used for reinforcement; the bars are supplied to the steel
bending yard directly from the manufacturer. These bars are tested as per
inspection and test plan. The reinforcement is cut and bent shall confirm to the
dimensions as per the approved BBS for that particular segment. Reinforcement is
tied in a typically fabricated reinforcement jig, care should be taken that there is
no sagging in the reinforcement. At the stressing ends guide cones are inserted
into a helical coils of specified diameter to oppose the bursting force during
stressing. Reinforcement is tied with GI binding wire (18 Gauge) and cover block
made of grout (M45 grade) only is tied at suitable locations to maintain minimum
cover. Projected reinforcement is coated with slurry of inhibiter solution and OPC
at a ration 0.5-0.6: 1 and mixed thoroughly. After completion of the cage
fabrication, the same shall be offered for engineering inspection. The
reinforcement is transported to the segment casting bed with the help of gantry.
HDPE pipes are fixed in the reinforcement cage as per drawing. In the drawing the
X, Y and Z (profile) coordinates of the ducts are given. The HDPE duct shall
inserted in guide collar provided to accommodate the HDPE duct and the joint is
sealed with tape to avoid ingress of slurry during concreting. For proper matching
of center line of duct for previously cast segment to be cast to avoid ingress of
slurry during concreting, a rubber cone shall be inserted inside the HDPE pipe of
match cast segment. The joints shall be sealed by glass putty.
50
Hyderabad Metro Rail Project
Surveying activity:
Advanced total station of 1sec accuracy and auto level capable to read upto 1mm
are used for geometry control surveying. Two survey towers are constructed at
both ends of the bays to control alignment of segments. The survey department
has already established a system of station (on either side of the bay). The
coordinates of the design point are pre calculated and recorded in the memory of
total station. Setting out works are done and the orientation shall be fixed from
this survey stations.
At first marking of both axis lines are given before starting of any activity on each
mould. The surveyor will check for the position and level of the bulkhead and
soffit are in right position and level as per pre calculated level and coordinates
and accordingly if necessary soffit levels and position will be adjusted. Six
surveying plates are fixed on each segment at 150mm from edge and 4.25m from
the center of the segment.
After casting the segment the surveyor will check the bulkhead position at the
center and level at 4.25m from the center. After recording the data, surveyor will
punch the coordinates on the insert survey plates as per theoretical coordinates.
These coordinates and levels are recorded and entered into the worksheet to
calculate the twist error and alignment data for the next match cast segment to
get the corrected casting coordinates.
51
Hyderabad Metro Rail Project
2. The side shutters are fixed and mould releasing agent is applied to the form
work.
3. The reinforcement cage is placed in the mould.
4. Guide cones are fixed on the bulkhead and the bulkheads are fixed on the
both sides.
5. Profiling of the sheathing pipe as per coordinates is done.
6. Internal shutter is aligned and fixed.
7. For lifting pipes are provided in the reinforcement in the slab portion.
8. Internal shuttering is fixed and jacked.
9. Before concreting initial surveying is done for checking the alignment and
the levels of the bulkhead, soffit and the profiling of the sheathing.
10.Concreting is done in layers at first the bottom slab is concreted and then
moved to the top slab.
11.Web concreting is done in three layers, this concreting shall be done in two
layers moving from the ends to the center, care should be taken that while
vibrations are done the profile of the sheathing should not be disturbed.
12.The top surface is smooth finished except in the area of shear connectors.
13.Curing is done for 14days by covering the top surface with hessian cloth
and regular sprinkling of water.
14.After attaining 20MPa strength the shuttering is removed and after match
casting the next segment attaining 25MPa the segment is taken to curing
yard for 14 days.
15.Segment IDs are painted on the inner face at both ends bulkhead and
match cast face with yellow paint after removal of external shutter and
before lifting.
16.IDs are given as, for example:
segment ID: C3NU-P12-P13-S2-10
C3 is corridor 3
NU is stations id
P12-P13 is the span between pier number 12 and 13.
S2 is the segment type, 10 is the segment number.
17.These segments after giving IDs are stacked in the stacking yard and
transported to the site in the trolleys.
52
Hyderabad Metro Rail Project
53
Hyderabad Metro Rail Project
4. Future stressing blocks: These blocks are present inside the segment, when
there a need for further stressing in future these blocks are used.
5. Shear keys: These are the projections and depressions present on the
segment. The segment has one female and one male shear keys. The male
shear key will match cast with the female shear key of the next segment.
54
Hyderabad Metro Rail Project
7. Survey plates: These are the steel plates of dimensions 50mm X 50mm and
thickness of 5mm fixed 150 mm from edge and 4.25m from the center of
the segment in six places. The theoretical coordinates are punched on
these plates and the segments are erected with respect to these
coordinates in the site.
8. Wide bearings: Wide bearings are provided to the pier segments where the
load coming on to them is more, i.e. when there are sharp curves the load
coming on the pier segment is more.
PARAPETS
All the parapets are casted in the casting yard only. These parapets are erected on
the sides of the viaduct segments with the help of parapet launcher after erection
55
Hyderabad Metro Rail Project
of segments. The parapet reinforcement projected out is tied with the parapet
stirrups of the segment and concreting is done by fixing formwork. On these
parapets OETS masts are erected.
ERECTION OF SEGMENTS
Procedure:
1. For erection of segments work permits from the traffic police, Greater
Hyderabad Municipal Corporation and other local governing bodies has to
be taken. Segments are generally erected during night.
56
Hyderabad Metro Rail Project
57
Hyderabad Metro Rail Project
STRESSING OF SEGMENTS
The segments are stressed with the help of steel strands by hydraulic jack
and anchored. Post tensioning is done in the segments after they are erected on
temporary supports on the piers. The tendons are stressed, anchored and
grouting is done to the tendons.
LRPC (Low Relaxation Pre-stressed concrete strands) are used in this
project. Two types of strands are present, 1. 19T15 and 2. 12T15
In 19T15 strands there are 19 no of strands of 15.5 mm diameter
Pre stressing is the important activity in this project. All the stressing activities are
done by a special team. The strands are stored above 200mm from the ground
level and covered with tarpaulin to protect it from rain/dust. The wedges, anchor
58
Hyderabad Metro Rail Project
blocks, bearing plates, jacks and pumps are stored in closed containers. Proper
safety measures are to be taken/followed during the stressing operation.
Stressing Procedure:
1. The strands from the coil dispenser are pulled and required numbers of
strands per tendon are cut into required lengths.
2. The required numbers of strands are pushed into the tendon one by one.
After pushing the required number of strands as per the drawings the
additional lengths are cut with high speed abrasive cutter by maintaining
requires stressing lengths (0.75 m) on stressing end and dead end (0.25 m).
59
Hyderabad Metro Rail Project
5. The ram area of the jack is given, the pressure given by the jack is in Kg/cm 2
but the designer gives the stressing force in KN and the theoretical elongation
in mm, the designed force is to be converted into jack pressure in Kg/cm 2.
6. The actual area of cross-sectional and modulus of elasticity of the strands are
given by the manufacturer at the time of purchasing. By taking these values
into account the modified elongation lengths are calculated.
Due to space constrains and to cross a junction or fly over continuous spans are
used in this project. These spans are casted in the site hence called as cast in situ
60
Hyderabad Metro Rail Project
spans. Continuous spans are adopted to reduce the amount of reinforcement and
cost. There are around eleven cast in situ spans proposed in this project. Few of
them are changed to pre-cast segment spans after revision of designs.
Punjagutta Cast in situ continuous span:
To cross over the existing flyover in Punjagutta a 3 span continuous cast in situ
superstructure is proposed. The total span length is 128 meters and rests on four
piers. It is constructed in three stages stage I, stage II and stage III.
61
Hyderabad Metro Rail Project
5. Reinforcement is supplied to the site and as per the Bar Bending Schedule
released the reinforcement is fixed at the site as per the reinforcement
drawings.
10.Pot bearings are used in this span, these bearings carry huge loads.
11.The reinforcement is exposed out from the stage I span and stage II span
which is used to overlap with the span of stage III. Construction joints are
provided at the ends of stage I and stage III to join with Stage III span. Neto
bond is used to join the old cement concrete surface of stage I and stage II
with new cement concrete of stage III span.
12.Concrete is supplied to the site as per the concrete requisition slip and
concreting is done. Curing is done till the concrete attains the required
strength.
13. Future blisters, deck blisters and deck blisters are provided for stressing
and stressing is done in an order as mentioned in the drawings.
ROB
Rail Over Bridge (ROB)
The alignment of the metro rail has to cross the existing railway tracks of south
central railway. For this purpose special construction method is followed for the
construction of viaduct over the existing railway tracks. There are eight ROB’s in
this project:
In corridor I there are two ROB’s at Malakpet and Bharatnagar.
In corridor II there is only one ROB at Secunderabad.
In corridor III there are four ROB’s at Chilkalguda, Alugadda bavi, Oliphenta and
Begumpet.
63
Hyderabad Metro Rail Project
As the span is more at the ROB’s continuous spans are casted at the site or
erected with pre cast segments depending on the ease of construction. The
depth of the ROB segments is high compared to the normal segments.
At Oliphenta ROB the alignment has to cross existing railway tracks of South
Central Railway. The length of the span is about 83 meters. As the length of the
span is more a steel truss structure is proposed. The steel structure is placed on
the pot/pipe bearings. A large pier is constructed on both ends of the span for
which huge pile foundations are constructed. A clearance of about 12 meters is
provided between the bottom level of the steel structure and the rail level of the
existing tracks.
STATIONS
The stations are built over the existing roads of the city, which cannot be widened
beyond a point due to presence of existing buildings. There are 66 stations in all
the three corridors for phase I.
Corridor I : Miyapur to LB Nagar – 27
Corridor II : Nagole to Shilparamam – 23
Corridor III : JBS to Falaknuma – 16
Stations are constructed on single piers along the alignment. The main structures
of the stations are casted in the casting yard and erected in the site. These
64
Hyderabad Metro Rail Project
stations are designed in such a way that a clearance of 5.5 meters is provided for
the vehicles to pass underneath them. Service roads are also provided on either
side of the road depending on the availability of the land near the stations. Track
level is gradually increases towards the station so that the train coming to the
stations decreases its speed easily.
Each station a concourse level and a plat form level, one has to take ticket from
the concourse level and enter into the platform level to take the train. The
platform level is covered with a steel roof structure. The stations are provided
with amenities like escalators, lifts for physically handicapped, toilets, etc. for the
passengers. The stations are provided with all lifesaving facilities like fire
protection systems, emergency lightening, CCTV monitoring, etc.
At the concourse level we have facilities for disabled, facilities of vending water,
cool drinks, public access telephones and other retail areas.
For a typical station there are 10 piers, 9 spans, 62 spine segments, 112 wings and
54 PL beams. Five spans are 13.4 m length and four spans are 17 m length. The
platform slab rests on the PL beams and the slab is casted in the site.
The stations due to space constrains are having the following three types of sizes
approximately:
The station has different rooms for operation and maintenance, station manager
room, auxiliary substation rooms, etc. Each station is provided with Pump room
65
Hyderabad Metro Rail Project
and Sump rooms to supply water into the stations in case of any fire accidents.
Rain water harvesting pits are also present in each station.
1. Piers: These station piers are different from normal viaduct piers, these
piers are casted in the site and have lager dimensions. Station piers follow
different nomenclature. There are always 10 piers for each station. These
10 piers are named alphabetically – A,B,C,D,E,F,G,H,J,K.
2. Pier arm: Pier arms are casted in the site, they are the horizontal beam
placed between the two segments on the pier head. Post tensioning is done
for fixing them tightly. On the pier arm PL beams are erected on which
platform slab is casted.
3. Corbels: Corbels are the projection outwards of the station pier on which
the concourse level is built. The entire load of the station is transferred
from corbel to the piers. Bearings are provided on the corbels.
66
Hyderabad Metro Rail Project
4. Spines: Spines are the pre casted segments which are erected between two
piers on the corbels. These form the base for the concourse level. Post
stressing is done for the spine segments and one duct is left for future
stressing.
5. Wings: These are also the pre-casted segments which are joined to the
spines. These are joined to the spine by post tensioning, they mainly carry
the loads of the block masonry of the exterior walls of the station.
6. PL Beams: These pre casted beams are erected on the top of the pier arms,
and run parallel to the station. The platform level slab and the loads on the
platform are carried to the pier arm by these beams.
7. Station arms: There are four arms in a station, these are the structures
which provide access to the concourse floor. Escalators, lifts, stair cases are
provided in these structures. Stair cases are may be pre casted or cast in
situ depends on the site conditions.
Construction of Stations:
Construction of Piers: The piers are constructed as per the approved drawings
submitted. The surveyor marks the foundation layout for excavation. After
excavation the PCC is laid and markings are made for the footing on PCC. The
reinforcement is sent to the site as per the BBS released. The formwork is fixed
and the reinforcement is tied as per the drawings. After casting the footing the
center line is marked by the survey team for started, and the formworks is
67
Hyderabad Metro Rail Project
fixed and the reinforcement is tied. Similarly the whole pier is constructed in
the site as per the drawings.
After gaining the strength to the concrete post tensioning activity is done in
the pier arms. Then the cantilever brackets are dismantled now the pier arms
are rested on the pier head. The station LG is erected with the help of cranes
on the pier arm. The spine segments are transported from the casting yard to
the site and are lifted as per sequence with the help of slider beam and placed
on temporary packing. The segments are glued with epoxy glue and temporary
stressing is done with hydraulic jacks and mac alloy bars. The stressing ducts
are covered with ‘O’ rings while applying glue. The HT strands are inserted into
the ducts, bearing plates and wedges are fixed followed by stressing. After
stressing, grouting is done with grouting equipment. The span is released by
removing all temporary stressing’s mac alloy bars, stressing brackets and
rested on temporary bearings/packing. Now the platform level beams are
erected on one side, they all are rested on temporary bearings and tied
together for lateral stability with temporary struts. Similarly the other side PL
68
Hyderabad Metro Rail Project
beams are also erected. From the PL beams the wing segments are lifted had
kept in holding position still the stressing of transverse ducts and stitch
concrete is done. The permanent bearings are fixed on the corbels and levels
are checked. The complete span is then shifted to the permanent bearings
from the temporary packing/bearings. All the stressing activities done are as
per the drawings- in the drawings the sequence/order of stressing of segments
with details are provided.
After erection of spines and wings the PL beams are fixed in the correct
position. The formwork for the platform level slab is fixed and slabs are casted.
The block masonry walls are constructed, pre casted stair cases are erected in
the pier arms.
A water pump room and water sump rooms are provided below the ground
level. From these rooms water is pumped to the station in case of any fire
accident. For construction of these room excavations are done till the ground
achieves certain bearing capacity to withstand the load of these rooms.
69
Hyderabad Metro Rail Project
A LCPT (light cone penetration test) is carried to check whether the soil is
suitable to construct the structure or not. In this test blows are given to the
rod to which a cone is attached from a fixed height with 10kg weight hammer.
The first 150mm penetration blows are neglected, for next 54 blows the
penetration should be less than 300mm if it is more than 300mm further
150mm excavation is done. After getting the required soil bearing pressure
PCC works is laid, and then raft markings are done on the PCC slab. The
reinforcement is fixed for raft and concreting is done. After that the columns
and walls are constructed. All these works are done as per the drawings. After
construction of the water sump room water ponding test is done.
Water pond test: The tank is filled with water and the water level is marked,
the readings of the water level are noted for seven days. The maximum
allowable fall in water level is 40mm, if it is greater than 40mm the water is
removed and grouting is done in the identified leakage areas.
The stations are covered with overlapped fabricated steel roof structure
covering the platform level. This roof structure is erected by Truck mounted
crane from the trailer to the platform level.
70
Hyderabad Metro Rail Project
In the concourse level gaps are provided between the block masonry and the
RCC members (PL beams, Segments, pier arms). This gap is filled with sealants.
Sealants are used to avoid the load transfer from one structure to other.
Application of sealant is of two types: 1. Fire rated and 2. Non fire rated. Fire
rated sealants are used in the internal walls whereas non-fire rated sealant is
used in exterior walls.
Application of sealants:
1. The gap between the block masonry and the RCC member is cleaned with
wire brush and air blower or air compressor to remove any loose materials
or dust.
2. For Fire rated sealants the gap is filled with rock wool of thickness
mentioned in the drawings. Then the circular baker rod is inserted into the
gap leaving a gap from the wall to apply silicon sealant.
3. For Non-fire rated sealants the gap is little high than fire rated sealant, the
gap is filled with poly ethylene filler board and a circular baker rod is
inserted in the gap. The silicon sealant is applied with the silicon gun.
Masking tape is applied to both the side surfaces of the RCC member and
block masonry.
TRACK WORKS
71
Hyderabad Metro Rail Project
Two sets of tracks are laid on the viaduct structure. The tracks are laid on
balastless plinth beams; these beams are casted in the site with M50 on the
viaduct. The tracks are continuous tracks welded at joints. Tracks are aligned in
such a way that continuous electrical contact is made between the train and
traction power. The gauge of the tracks laid is 1435mm (standard gauge). At
the depots test tracks are constructed for testing the trains before putting
them to passenger operation to ensure safe and reliable train operation.
ROLLING STOCK
72
Hyderabad Metro Rail Project
73
Hyderabad Metro Rail Project
DEPOTS
There are three depots for the maintenance and stabling of the trains for the
three corridors.
For corridor I Miyapur depot, for corridor II Falaknuma depot and for corridor III
Uppal depot. A work shop is established in Uppal depot. The other depots have
basic facilities for schedule preventive maintenance and minor corrective
maintenance. Each depot has equipped with facilities and resources for the
efficient and effective maintenance of the rail system assets.
74
Hyderabad Metro Rail Project
75
Hyderabad Metro Rail Project
The trains are washed properly every night after returning from the revenue
services. Internal cleaning is also done every day.
Regular inspections, analyzed data downloaded from the train are checked
regularly.
CONCLUSION
76
Hyderabad Metro Rail Project
For construction of this Hyderabad Metro Rail Project the management has
established a Quality Management System to monitor the quality of the works of
the project. Systematic procedures are followed for every activity in the execution
of the projects. Risk assessment is done for every activity to identify the risks
involved in it to complete the job and proper measures and safety procedures are
followed to mitigate the risks.
All the works and the materials used in the project are in accordance with the
standards and international codes as specified it the Manual of Specifications and
Standards.
Documentation of every work is done for the smooth running of the organization
and are maintained.
In Hyderabad Metro Rail Project they are using three types of technologies cast in
situ for foundation and pier, pre cast for viaduct and station segments and post
tensioning of the concrete members. Foundations and piers are cast in situ
because they provide more strength than pre cast members. Post tensioning is
done for strengthening concrete to improve seismic behavior, reduces deflection
and vibration, and improves crack control and water proofing properties.
The project will integrate multi-modal public transportation with urban spaces,
and thus undertake infrastructure development of Hyderabad. The metro is an
urban rejuvenation and redesign effort to transform Hyderabad into a people-
friendly 'green' city.
77