Module 02 Updated
Module 02 Updated
Information Technology
Enterprise Systems
Enterprise Systems
Week 3
Characteristics of Business Processes
Required Reading
1. Chapter 2 (Enterprise Process Management Systems:
Engineering ProcessCentric Enterprise Systems using
BPMN 2.0 by Vivek Kale)
Recommended Reading
1. Dunn, C., Cherrington, J., & Hollander, A. (2005). Enterprise
information systems: A pattern-based approach (3rd ed.)
Weekly Learning Outcomes
1. Business Process
2. Process Performance
3. Process Cycle Time
4. Process Costs
5. Process Quality
6. Measuring Process Performance
1. Business Process
1. Business Process
• A business process is a set of logically related tasks performed to achieve a
well-defined business outcome.
2. Flow units:
• A flow unit or job is an item that flows throughout the process.
2. Process Performance – Cont.
4. Resources
• Resources are tangible assets that are usually divided into
two categories: capital and labour.
2. Process Performance – Cont.
5. Information structure
• describes the information that is needed and available in order
to perform activities or to make managerial decisions.
2. Process Performance – Cont.
• The inventory within the framework of the process depends on the difference
between the inflow rate and outflow rate.
• A stable process is one in which the average inflow rate is the same as the
average outflow rate across an extended period of time; that is R = Ri = Ro
2. Process Performance – Cont.
• The average cycle time is the average across all flow units that exit the
process during a specific period of time.
• Average inventory is the number of flow units within the process boundaries
at any point in time.
➢ The average inventory equals the average flow rate times the average cycle time;
that is, I = R*T.
➢ Example.
3. Process Cycle Time
1. Theoretical cycle time
• The theoretical cycle time of a process is the minimum amount of time
required for processing a typical flow unit without any waiting.
• It is the sum of the times of those activities that the flow unit passes through and
where specific kinds of tasks are undertaken to process it.
• Activity time is the time required by a typical flow unit to complete the
activity once.
2. Critical path
A process flow is presented using a diagrammatic technique like a
flowchart. The longest path in the process flowchart is the critical
path.
• All activities that constitute the critical path of the process flowchart are
called critical activities.
3. Process Cycle Time – Cont.
3. The critical path method is based on calculating a variable called the
slack time of activity.
A. Forward schedule - calculates the earliest possible start time (ES) and
the earliest possible finish time (EF) of each activity within the process.
1st activity, ES = 1, where 1 means 1-time unit.
Other activities, ES = 1 + max(EF) of immediate predecessor
activities. EF = ES + d + 1, where d is duration time of the activity
B. Backward schedule - calculates the latest possible start time (LS) and
the latest possible finish time (LF) for each activity of the process.
1st activity, LF = EF
4. Slack time (S): The slack time of an activity is the amount of time
that could be spent in addition to the duration time of the activity,
without causing a delay to the start times of immediate successor
activities.
S = LF − EF = LS − ES
• Adding waiting times to the theoretical cycle time of the appropriate path.
• Obtaining the average cycle time of the process by finding the path whose
overall length (activity plus waiting) is the longest.
3.1 Computing Cycle Time – Cont.
2.Using value-adding and non-value-adding activities.
The actual process capacity will always be less than the theoretical
capacity due to:
• Resource breakdowns: A machine may become unavailable due to a
breakdown or a human resource may be absent.
• Preventive maintenance: Machines require regular maintenance to operate at
maximum efficiency; this scheduled preventive maintenance makes the resource
unavailable for processing.
• Process flow inefficiencies: A resource may become idle due to the
unavailability of work.
• Demand variation: As described earlier, the mismatch between demand and
capacity can cause underutilization.
3.3 Process Capacity – Cont.
The flow unit on its way through different activities is processed by a number of
resource pools with predetermined capacities;
• The pool with the lowest capacity is termed the resource bottleneck of the process.
• Since the capacity of a process cannot be better than the process’s bottleneck
resource pool, this effectively makes it the defining capacity of the whole process.
ρp = R / Rp
R is the throughput
Rp is the theoretical capacity of a resource pool
3.3 Process Capacity – Cont.
The theoretical capacity can be improved by:
1. Decreasing the unit load on the bottleneck resource pool (i.e.,
work faster, work smarter)
2. Variable costs, which are the costs per work unit and therefore
vary with the number of sales.
5. Process Quality
Quality can be defined from the two different perspectives:
c. Taguchi method: Any deviation from the target is undesirable. Normally, any value
that fell within the lower and upper specifications was considered good.
➢ The quadratic loss function says that any deviation from the target value results in a loss.
5. Process quality - Cont.
2. Deliver quality products and services by having processes that produce no
defects and demonstrate little variability.
• The underlying principle of statistical quality control is that all processes
exhibit variation in their output.
• Some of the variations are called common cause variations and are due
to the inherent characteristics of the process.
• Another variation is the result of special causes that can be attributed
to a specific problem.
• Statistical process control uses control charts to monitor processes.
• The design of a quality process involves instituting the correct feedback loops
so as to constantly monitor and control the process.
• The usage of control charts helps to maintain process variability within a small
range of values within which the variability is explained only by common
cause variation.
5. Process quality - Cont.
3. Improve the quality of their processes by establishing continuous
process improvement programs (e.g. DMAIC, Six Sigma) that run parallel to
the core business processes.
The analysis teams need to identify improvement opportunities to:
• Eliminate waiting time (a waste)
• Eliminate wasted movement or effort
• Minimize inventory
• Eliminate repair and rework
• Minimize material movement
• Minimize inspections
• Reduce the variety of inputs, processes, and outputs
• Reduce cycle time
• Improve machine reliability
• Improve flexibility of resources
6. Measuring Process Performance
A process performance measurement system focuses on an
individual business process, rather than on the entire
company or an organizational unit.
6. Measuring Process Performance – Cont.
• Two performance indicators can be identified: time (as an input factor) and
service quantity (as an output factor).
• Quality indicators describe the degree to which the actual product attributes
and properties conform to the underlying product specifications.
• Strategic performance
(e.g., fulfilling the vision)
• Process performance
(e.g., quality, cycle time)
• The layer connecting the two hierarchical levels depicts those performance
indicators that impact both levels (e.g., customer satisfaction, flexibility, and
productivity).
6.2 Frameworks for Measuring Process Performance - Cont.
Additional References
1. Dunn, C., Cherrington, J., & Hollander, A. (2005). Enterprise
information systems: A pattern-based approach (3rd ed.)
Thank You