Ipa14 e 065
Ipa14 e 065
Kamal Hamzah*
Adam Fatchur Rohman*
Yoseph Itok Arseto*
Virzi Firmansyah*
The wellhead model in the PIM software The objective was that the pressure in each cluster
accommodates 3 type of wells i.e. Gas lift (G), ESP must be similar with the actual condition.
(E) and Natural flow (N). Water injection well can
be represented with natural flow model (N). The Model Application for Water Injection
performance well data must be imported from the Optimization
single well model that was already modeled by
using the generic nodal software. The integrated model (surface and well models) can
be used for optimization and simulation in order to
If there are no errors, the whole model can then be assess any changes in the network of water
run. The system network-optimizer technology is injection. The problem that frequently arises in
Kaji-Semoga Field is maintaining produced water the recommendation to install additional
tank level by shutting in some high water cut wells. pipeline to prevent high pressure drop or
However, the integrated model of water injection bottleneck in the pipeline system. Future
system can be very useful for the situation: development of the field related to the
increment of water injection system rate must
1. Determining the cause of low (or decreased) be considered as well.
water injection rate.
Restriction in the well can be caused by
Low water injection rate can be caused by formation damage, which may be caused by
several problems, i.e.: debris and small amounts of oil that
inadvertently have been injected along with
a. By upstream water injection system water. Scale growth in front of perforation can
problems, such as low efficiency of water also be one of the root causes of formation
injection pumps (WIP). This is indicated by damage. For preliminary evaluation, well that
low pressure discharge of the header or experienced formation damage would have
individual pump. The troubleshooting can lower injection rate compared to the adjacent
be focused at the pumps and the simulation wells in the same WHP. By this model, it will
can be localized at the field station. It can be easier to compare a well to others. For
be indicated by low tuning factor value in further investigation, hall-plot history of the
the pump model (flow, head and power). well will clearly told us the cause of low water
injection rate. Then, to overcome formation
b. By downstream water injection system damage on the well, stimulation of the wells by
problem. This is indicated by high acidizing can be conducted. The design of such
discharge pressure in the header or stimulation must consider these parameters:
individual water injection pump, caused by
restriction that occurred in the pipeline a. The target of injection rate required by the
network or at any well with low (or reservoir engineer in order to optimize the
decreased) injectivity index. pressure maintenance and waterflood
project.
For pipeline network analysis, after conducting
history matching at each node (e.g. each b. Wellhead pressure that can be generated by
manifold station, each manifold cluster, flow- the network at the well location. This can
line connection, and wellhead), it can be be simulated by the integrated network with
observed which network part has experienced the increment of flow rate (after acidizing)
pipe bottleneck by determining the velocity of in the pipeline that is directed to the well
the liquid (in this case in water single phase) location.
and the pipeline correction factor (L, D and U
factor). D factor of the pipeline that less than c. The influence on the rate increment on the
0.9 also indicates constriction ID because of whole water injection system. The
scale or other impurities growth that contributes stimulation priority will be based on the
to high pressure drop in the pipeline. It affected highest rate increment.
to low injecting WHP and yielded low water
injected rate. It’s experienced by wells in the 2. Redistribution of water injection network.
cluster L that was caused by flowline to cluster
L has D factor value about 0.78. Manifold Integrated simulation can accommodate and
Pressure at Cluster L is only 421 psig (as shown forecast the results of redistribution of the water
in table 1). Beside it, based on API RP 14E injection in the system to:
(1991) recommended practice concerning
Design and Installation of offshore production a. Mitigate problems such as pipeline leak due
platform piping systems, as shown in Figure 5, to corrosion or sabotage.
the recommended velocity of liquid flow
through pipeline is between 3ft/second until 15 b. Optimize performance to get a higher
ft/second. Figure 6 shows an example of liquid injection rate and prevent bottlenecking.
velocity in the network that exceeds 15 ft/s and
yielded high pressure drop (8 psig per 10 ft). c. Re-route water injection flow due to surface
This simulation result provides justification for network sabotage by local inhabitants.
Redistribution can be conducted by setting the e. Flow-line from manifold station until
open/closed valve that connects between the cluster R.
flow-lines. It also can be done by opening or
closing the valves that interconnect between The expected manifold pressure increment at
field stations. In Kaji-Semoga field, valve each cluster is shown in Table 1. The increment
connection between stations and fields can also water injection rate is expected about 20,000
be adjusted to optimize water injection of the BWPD.
whole system.
2. Additional water injection wells to reduce
RESULTS bottlenecking in the trunk-line. These wells are
located far from the field station. Three wells
In Kaji-Semoga field, the integrated model of water are already being proposed to be converted to
injection system is a very useful tool for evaluation, water injection wells.
optimization and troubleshooting in order to
increase water injection rate. Some 3. Installation of additional water injection pumps
recommendations for the water injection system to accommodate the future plan of water
optimization in Kaji-Semoga can be divided into injection rate due to increment of liquid lifting
short term plan and long term pan. The short term and water cut to combat oil production decline.
plan consists of:
After the short-term recommendations were applied,
1. Stimulation of wells that experiences formation for Kaji field station, as shown in Figure 8,
damage (can be observed by Hall-plot chart). In manifold system pressure has decreased from 1020
Kaji-Semoga, hydrochloric acid (HCl) acidizing psig to 980 psig (on average, based on trend line).
for stimulation is regularly conducted by using Average water injection rate has increased from
60 GPF (gallons per feet) acid. This is expected 65,000 BWPD to 70,000 BWPD and monthly VRR
to obtain a higher injectivity index to meet the for Kaji Field has increased from 0.911(August
required target of water injection. Figure 7 2012) to 1.048 (Jun 2013). Semoga Field monthly
shows the example of a Hall-plot trend in one VRR has increased from 0.818(August 2012) to
well in Kaji-Semoga field before and after 0.835 (Jun 2013) as shown in Figure 9. For the
stimulation. whole system at Kaji-Semoga field, liquid lifting
capacity has increased from 179,000 to 184,500
2. Redistribution of water injection flow to get the BLPD. The final objective to increase oil
maximum water injection rate of the system, by production by eliminating oil deferment 236 BOPD
adjusting the valve interconnection between due to water handling constraint has been achieved.
Kaji and Semoga field stations.
The long term plan consists of: The long term plan for upgrading the water
injection system in Kaji-Semoga field has not been
1. Installation of a new flow-line to re-route the applied yet. A proposal to the Indonesian
water injection flow in order to de-bottleneck Government has been issued and approved.
parts of the network (for some flow-lines that Currently, the upgrading is still under construction.
have liquid velocity exceed the maximum limit After the upgrade project has been completed, the
15 ft/s). Based on the model evaluation, it is capacity of the water injection system in Kaji-
recommended that additional flow-lines are Semoga field is expected to reach 220,000 BWPD.
required in these locations (as also described in
Figures 3 and 4):
CONCLUSIONS
a. Flow-line from jumper cluster AF until
1. Oilfield Water Injection Systems can be
jumper cluster Y.
modeled and simulated in Production Integrated
Model software as a tool to conduct system
b. Flow-line from manifold station until
optimization and troubleshooting.
jumper cluster L.
c. Flow-line from manifold station until 2. The water injection model includes
cluster D. performance data that cover subsurface
parameters (well and reservoir performance
d. Flow-line from manifold station until data) and surface parameters (pipe line and
jumper cluster U. water injection pump performance data).
3. Based on the water injection model, analysis The authors are also grateful to colleagues in P.T.
and evaluation can be performed, which have Medco Area Engineering Department Office that
resulted in optimization recommendations, were very kind and always supported completion of
including well stimulations and upgrading all of the jobs to finish this manuscript.
surface facilities equipment.
4. The results of water injection system REFERENCES
optimization based on water injection
integration model are: Aditama, P. et al., 2010, Construction and
implementation of integrated production Network
Increase in the water injection rate yielding Model in a complex onshore operation: Proceedings
an increase in VRR value. of SPE OGIC, p. 2-3.
The minimizing of oil deferment due to
maintain produced water tank levels. Malau, A. et al., 2011, Gas Field Production
An increase in oil production rate. Optimization Using Integrated Network Modeling –
Case Study of SSE Gas Management: Proceedings
ACKNOWLEDGEMENTS of Indonesian Petroleum association, 35th Annual
Convention & Exhibition, p. 3-6.
The authors would like to acknowledge the support
of Rimau Asset management of PT. Medco E&P
Indonesia, particularly Petroleum Engineering Recommended Practice for Design and Installation
Rimau manager who has encouraged all of his of offshore production platform piping system, API
subordinates to gain new knowledge as deeply as Recommended Practice 14E (RP 14E), Fifth
possible. Edition. (1991).
TABLE 1
Rate increased
after acid 60 gpf