CONTRACT PRACTICE Lecture Notes-Saudi Arabia
CONTRACT PRACTICE Lecture Notes-Saudi Arabia
&
CONTRACT ADMINISTRATION
Delivered by
ASMY SHERIFF
MRICS, AIQS, LLM, CCMP, MBA, MCIOB, BSc(Eng)
CHECKLIST
Valuing change –
Sectional Completion/Partial variations/compensation
Principles of contract law
Possession events
Dispute avoidance and
2 Legislation Determination /Termination
resolution
Roles & responsibilities of parties Defects liability/rectification period Final Accounts
Third party rights –
Extensions of time Liquidated/delay damages
Legislation/Collateral Warranties
Letters of intent – Comfort
Change procedures
letters/Consent to spend Claims/Loss and Expense
/Recognition of contract
Performance security – Named/Nominated
Materials on/off site
Bonds/Parent Company Guarantees subcontractors
Insurances Advance payments Completion
Standard forms of main and Retention – retention bonds Defects liability/rectification
subcontract period
Interim valuations and payment
Assignment/Novation provisions
8
1987
1999 Q
Contract Practice - Third party rights /Collateral Warranties
Privity of contract
ȍ Means the terms and conditions of a contract cannot be enforced to a person who is
not part of that contract 9
ȍ This mechanism would prevent any liability arising between the contractor and
occupier without the existence of a collateral warranty, so collateral warranty
mechanism mainly being used to overcome the privity to the contract.
Collateral warranties
ȍ Are agreements which are associated with another 'primary' contract.
ȍ They provide for a duty of care to be extended by one of the contracting parties to a
third party who is not party to the original contract.
Q
Contract Practice - Roles & responsibilities of parties
It can be helpful to pay for goods or materials that are not on-site. But it does put the client
at risk, like if the contractor goes bankrupt and the items aren't delivered even though
payment has been made. 14
Change procedure
In typical construction work the Employer or the
16
contractor itself shall provide the change procedures
to be followed. This shall be agreed by the parties.
Simplified change management process ( check project finance competency for detailed one)
ṏ Identify changes
ṏ Change order
ṏ Client approval
ṏ Issue instruction for changes
ṏ If these changes affect the contractor's cash flow or if the amount of the change is very Q
large, the engineer can release the money on account.
Contract Practice – Delay
19
CONTRACT PRACTICE
&
CONTRACT ADMINISTRATION
Delivered by
ASMY SHERIFF
MRICS, AIQS, LLM, CCMP, MBA, MCIOB, BSc(Eng)
Contract Practice – Delay
Delay
The term 'delay' is used in the context of construction contracts to suggest that
the works are not progressing as expected and, as a result, completion may not be 22
completed by the completion date indicated in the contract terms.
ȍ Contractor’s delay
ȍ Excusable none excusable
ȍ Employer’s delay
ȍ Compensable none compensable
ȍ Neutral delay
ȍ Critical none critical
ȍ Concurrent delay - two or more
ȍ Concurrent none concurrent
delays happen at the same time or
effect felt at the same time
Contract Practice – Delay
ṏ Quantum meruit claim - This expression means fair remuneration The owner of a building who has
.
been unjustly enriched by work undertaken by a builder on its property may be obliged to pay a quantum meruit for this work.
ṏ Ex-gratia claim – when no contractual provision allows for such entitlement the employer pays
because of sympathy. Ex: No clause for fluctuation buy paying out of sympathy.
Acceleration Claim
In general, the architect has no power to instruct the contractor to accelerate work.
The contractor’s obligation is to complete the work within the time specified. 27
ö Directed Acceleration
Contract Practice – Claims
Entire Agreement
29
The Contract incorporates the entire agreement between the parties and replaces all
former conversations, representations, undertakings, and agreements. No other
documents can be considered as a related to the contract.
Contract Practice – Security / Guarantee
In guarantee, the first obligation is for the contractor to fulfil its obligations.
Q
But in a bond, bank has an obligation to pay without waiting contractor’s action
Contract Practice – Security / Guarantee
Deductible
Amount of claim not covered - Deductibles are how risk is shared between
you, the policyholder, and your insurer. This amount will be deducted from
your insurance entitlement.
Subrogation
Right of the insurance company to sue whoever is responsible for
causing loss to the insured 34
Contract Practice – Security / Guarantee
35
Advance payment
Generally, there is a negative cash flow for most part of the project, reduce finance
cost to Contractor If the employer and the contractor agree that the employer should 37
make an advance payment to the contractor, the amount agreed upon and the date for
payment must be included in the contract's appendix, together with a schedule
outlining the times and amounts of repayments. If a bond is necessary, one is
available.
For this process before issue AP, the CA should make sure that
Domestic Contractor – Appointed by main contractor as per his own requirements subject
to approval
Named – Appointed by MC from the list provided by the Employer
Nominated – Appointed by the Emp but contract with MC 38
Q
When issuing nomination contract to Main Advance payment to the Nomination
contractor for any of the provisional sum contractor
provide with
ṏ Make sure that Main contractor
ṏ Nomination letter (MC)did not claim the portion of PS
ṏ Nomination subcontract's final offers within his advance payment of X%
ṏ All the tender documents issued to the ṏ If MC claimed that amount too
nomination subcontractor within its advance payment ,
ṏ Post tender clarification instruct the MC to pay accordingly
ṏ Negotiation records and MC should pay it
ṏ Discounts ṏ If MC did not claim this amount then
ṏ Drawings the relevant amount should be paid
ṏ Specifications to the MC and MC shall pay the
ṏ Any other documents
Q
relevant to the NS. For the purpose
of this the MC and Client should
Q
have supplementary agreement
Contract Practice – Interim Payment
Determination / Termination
Decision or, more commonly, the bringing to an end of the contract, for example, the Q
determination of a dispute. In the context of building contracts to refer to the ending
of the contractor’s employment. In some situations, ‘termination’ is used instead of
‘determination’ but the effect is same.
Contract Practice – Contract
ȍ Performance: when both parties have fulfilled their obligations under the contract, e.g. the builder has completed the
Discharge of contract
- Release from
obligations.
contractual
ȍ Mutula Agreement: where both parties agree to treat the contract as at an end Frustration
ȍ Breach : a breach committed by either party before termination of the contract or being discharged from the contract.
ȍ Operation of law: Ex: the contract falling under the Limitation Act, bankruptcy of one party or the object of the contract
becoming illegal during its currency.
ȍ Replacement of one contract by another: (novation) usually accompanied by a change in the identity of one of the parties
ȍ Frustration
Contract Practice – Provisional Sum
44
Provisional sums;
Q
Contract Practice – Write your SOE
45
THANK YOU
46