C MUO ley WZ Nats)
PMP
FormulasINTEGRATION
MANAGEMENT
Present Value (PV)
Bigger the better.
Payback Period
Net Investment / Average Annual
cash flow
Net Present Value (NPV)
The PV of the total benefits
(income or revenue) less the costs.
The result - amount of money to invest today
PV= FV/(1+R)an (PV) for n years at r'% interest in order to end
up with the target sum (FV - Future Value)
Length of time it takes the
company to get back the
initial cost of producing a
productéervice.
Shorter the better
NPV is a much more precise
capital budgeting method than
payback period. bigger the
better
“DTECHCANVASSInternal Rate of Return (IRR)
The interest rate at which the present IRR is a more precise (and
nara more conservative) capital
value of the cash flows equals the initial | oudgeting method than
NPV.
investment. Tip: Interest from Bank A/c | Pigg" the Petter
Benefit Cost Ratio
_ Cost Benefit Analysis.
BCR = (Revenue / Cost) Beeeeteneey
Return on Invested Capital
Net Income (after tax) from proj /
Bigger the better
Total Capital invested in the project
Economic Value Add Benefit Measurement
EVA = Net Operating Profit After Tax
Cost of Capital =
— Costof Capital — (Investment [Ree CHNE Speers]
Bigger the better
Capital X % Cost of Capital)
Opportunity Cost
value of the project not selected smaller the better
Ps = §)7ECHCANVASSWorking Capital
Current Assets - Current Liabilities
Return on Sales (ROS)
NIBT / Total Sales (OR) NIAT / Total Sales
Return on Assets (ROA)
NIBT / Total Assets (OR) NIAT / Tota
Assets
Return on Investment (ROI
NIBT / Total Investment (OR) NIAT
/ Total Investment
Discounted Cash Flow
Cash Flow X Discount Factor
Bigger the better
Ps = §)7ECHCANVASSSCHEDULE
MANAGEMENT
Triangular Distribution / 3P Estimate
(P+M+0O)/3
Weighted 3P Estimate / PERT (Program
Evaluation & Review Technique) / Expected
Value (modified BETA distribution)
(P+ 4M + O)/6
Standard Deviation (o)
(P - O)/6
Variance (v)
(P - O)/602
Ps = §)7ECHCANVASSTotal Float / Slack
(There is a start formula & a finish
formula; & both begin with Late)
ES - Early Start; EF - Early Finish;
(LS - ES) or (LF - EF) LS - Late Start; LF - Late Finish;
TF - Total Float
Activity Duration
(EF - ES) or (LF -LS)
Forward Pass: (Add 1 day to Early Start)
EF = (ES + Duration - 1)
Backward Pass: (Minus 1 day to Late Finish)
LS = (LF - Duration + 1)
en §=§$ > TECHCANVASSPROCUREMENT
MANAGEMENT
Sharing Ratio
Y% / Z% (eg. 80%/20%)
Target Price (TP)
TP =TC+TF
Final Price (FP)
Actual Fee (AF) = TF + Z% * (TC-AC)
Actual Fee (AF)
(P - O)/602
Ps = §)7ECHCANVASSContract related formulas
Savings = TC - AC
Bonus = Savings x Percentage (Seller’s Share Ratio)
Contract Cost = Bonus + Fees
Total Cost = AC + Contract Cost = AC + Fees + Bonus
AF - Actual Fee (Profit)
TC-Target Cost
TF -Target Fee
AC - Actual Cost
COST
MANAGEMENT
on-) * P%C - Planned % Complete.
PV (P%C) * BAC | aVicatcocalied scws
9, * A%C - A ctual % Complete.
EV (A%C) * BAC EVis also called BCWP.
NEGATIVE is over budget,
CV EV-AC POSITIVE is under budget.
Ps 8 §)TECHCANVASSSV
EV-PV
CPI
Ev /AC
SPI
Ev/PV
EAC
ETC
(BAC / CPI)
AC + Bottom-up ETC
AC + (BAC - EV)
AC + (BAC - EV)/ CPI * SPI
EAC -AC
NEGATIVE is behind schedule,
POSITIVE is ahead of schedule
CPI >1, Efficiency in utilizing the resources allocated to the
project is good
<1, Efficiency in utilizing the resources allocated to the
project is bad
SPI >1 Mean more work was completed than was planned;
<1 Mean less work was completed than was planned
Used if no variances from BAC (or) project will
continue at the same rate of spending. = same
as AC + ((BAC- EV) /CPI)
Used when original estimate was fundamentally
flawed. AC +a new estimate for remaining work
Used when current variances are thought to be
atypical of future. AC + (remaining value of work
@ budgeted rate)
Used when current variances are thought to be
typical of future. AC + remaining budget modified
by performance
Amore accurate way is to re-estimate cost of the
remaining work from the bottom-up.
Ps = §)7ECHCANVASSVAC
How much over or under budget will we be at the
BAC - EAC end of the project?
TCPI(BAC)
Values for the TCP! index of less than 1.0 is
(BAC - EV) / (BAC - AC) good because it indicates the efficiency to
complete is less than planned.
How efficient must the project team be to
complete the remaining work with the
TCPI (EAC) remaining money?
Values for the TCPI index of less than 1.0 is
(BAC — EV) / (EAC - AC) good because it indicates the efficiency to.
complete is less than planned.
How efficient must the project team be to
complete the remaining work with the
remaining money?
Cost Aggregation
Contingency Reserves: to address cost impacts of
remaining risks after risk response planning (Known risks).
Project Estimates + Contingency Reserves = Cost Baseline
Management Reserves: extra funds set aside to cover
unforeseen risks (unknown risks).
Cost Baseline + Management Reserves = Cost Budget
/ Project Funding Requirement
Ps = §)7ECHCANVASS[N(N-1)]/2
EV-AC
Download Full (Ebook) Achieve PMP Exam Success: A Concise Study Guide for the Busy Project Manager by Margaret Y. Chu, Diane Altwies, Edward Walker ISBN 9781932159370, 1932159371 PDF All Chapters