Feasib Format
Feasib Format
Abstract
This guide provides rural residents with information about cooperative development feasibility studies. It denes the feasibility study and discusses their necessity and limitations. First steps in feasibility study development are described and key actions, including important components of a comprehensive study, are detailed. Also offered are criteria for selecting and working with consultants, information for developing assumptions, and study assessment factors. Key words: feasibility study, cooperative development, consultant, assumption, decision.
Vital Steps: A Cooperative Feasibility Study Guide John W. Brockhouse, Jr., and James J. Wadsworth completed the revision of this guide. The report was rst authored by James Matson in 2000 while he was employed with Rural Development. The authors acknowledge revision contributions from Bruce Pleasant, with USDA Rural Development in North Carolina, and James Matson, now a private consultant based in South Carolina. Publications and information are also available on the Internet. The Cooperative Programs Web site is at: http://www.rurdev.usda.gov/rbs/coops/csdir.htm December 2010
ii
Contents
The Cooperative Business Development Process . . . . . . . . . . . . . . . . . . . . . . . . . . . .1 Denition of a Feasibility Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1 What Is a Feasibility Study? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1 Why Prepare Feasibility Studies? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2 Lender Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3 Feasibility Study Limitations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 First Steps in Feasibility Study Development . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 Step 1Decide Whether To Proceed With a Study . . . . . . . . . . . . . . . . . . . . .4 Step 2Dene the Project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5 Step 3Group Commitment and Leadership . . . . . . . . . . . . . . . . . . . . . . . . . .5 Use of Advisors and Consultants . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6 Step 4Understand Sound Group Decision-making . . . . . . . . . . . . . . . . . . . .7 Feasibility Study Key Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 1. Deciding Who Will Conduct the Study (Consultant Selection Criteria) . . . . .8 Feasibility Study Working Relationships . . . . . . . . . . . . . . . . . . . . . . . .9 2. Development of Project Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10 3. Determining Components of the Feasibility Study Report . . . . . . . . . . . . . .10 Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12 Industry Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13 Marketing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13 Operational and Technical Characteristics . . . . . . . . . . . . . . . . . . . . .13 Financial Statements and Projections . . . . . . . . . . . . . . . . . . . . . . . . .14 Summary and Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . .15 Appendix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15 4. Accepting/Rejecting the Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16 5. Group Decisions After Accepting the Study . . . . . . . . . . . . . . . . . . . . . . . .16 Appendix ASequence of Events in Cooperative Development . . . . . . . . . . . . . . . .18 Appendix BThe Feasibility Study vs. the Business Plan . . . . . . . . . . . . . . . . . . . . .19 Appendix CSample Feasibility Consultant Selection Criteria . . . . . . . . . . . . . . . . .19 Appendix DUSDA RD Summary Guide for Feasibility Studies Included in Applications for Business & Industry Loan Guarantees (Instruction 4279-B) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .20 Appendix ESample Pro Forma Cash Flow . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21 Appendix FSample Pro Forma Income Statements . . . . . . . . . . . . . . . . . . . . . . . .23 Appendix GSample Pro Forma Balance Sheets . . . . . . . . . . . . . . . . . . . . . . . . . . .24 Appendix HSample Pro Forma Ratio Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . .25 References and Information Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17 Figure 1The Cooperative Business Development Process . . . . . . . . . . . . . . . . . . .2 Figure 2Guidelines for Group Decisions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7 Figure 3Key Actions for Feasibility Studies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8 Figure 4Criteria of a Good Feasibility Study Consultant . . . . . . . . . . . . . . . . . . . . . .8 Figure 5Questions for Developing Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . .11 Figure 6Example Outline of Feasibility Study Report Components . . . . . . . . . . . .12
iii
iv
cooperative development project to be completed, although there are some cases where projects are completed faster and others that take longer. The time needed to complete the feasibility study step varies widely from project to project, again depending on the characteristics of the group requesting the study, as well as the specific aspects of the venture, such as technological complexity, project scale, marketing conditions, member involvement, and financial planning factors, etc. However, a good rule of thumb for the feasibility analysis step for most development projects is 3 to 6 months.
concept is technically and economically feasible. Feasibility studies should also provide sensitivity analyses of the business given changes in key assumptions. One should note that a simulation or projection model, while useful, is not a substitute for a comprehensive feasibility study. This type of model is sometimes used in a pre-feasibility study done early in the project timeline to provide a first-cut evaluation of the proposed business idea. The feasibility study evaluates the project's potential for success. The perceived objectivity of the evaluation is an important factor in the credibility placed on the study by potential members, lenders, and other interested parties. For this reason, it is important to hire a consultant with no formal ties to equipment manufacturers or marketers, for example, so that an unbiased evaluation of operating potential and efficiency can be made. Also, the creation of the study requires a strong background both in the financial and technical aspects of the project. For these reasons, outside consultants conduct most studies, although the project leadership normally has input as well.
Feasibility studies for a cooperative are similar to those for other businesses, with one exception. Potential members use the feasibility study to evaluate how a cooperative business idea would enhance their personal businesses rather than to determine the return on investment they would receive on invested stock. A study conducted for an agricultural marketing cooperative, for example, must address the project's potential impact on members' farming operations in addition to analyzing economic performance at the cooperative level. In other cases, such as food cooperatives, the value to the member is access to consumer goods or services, possibly at lower prices, and is not based on the economic return to the cooperative itself. Cooperative businesses are developed first and foremost to serve members' needs and enhance their economic well-being. However, to do so, they must operate efficiently and compete effectively in the marketplace.
ational stage is a complex and time-consuming effort. Most ideas, whether a potential cooperative or an investor-owned business, do not develop into an operational entity. When ideas do make it to the operational stage there is a high failure rate (many within the first 6 months). Thus, before potential members invest in a proposed business project, they must determine if it can be economically viable and then they must decide if investment advantages outweigh the risks involveda feasibility study is the means by which these decisions are made. Without feasibility studies the percentage of startups that fail would be higher. Many cooperative business development projects are fairly expensive undertakings that can also be confusing to potential members. Proposed cooperatives often involve operations that substantially differ from those of the members' individual businesses, and cooperative operations may involve risks with which the members are unfamiliaranother reason that a feasibility study is so important. It should provide a clear understanding of project risk to help members decide whether to invest in the proposed business. Members participate in the development of the feasibility study and thus are educated about various aspects of the project, which will help them decide whether to move to the implementation stage. In addition, this knowledge helps prepare members of the steering committee to become the board of directors, as often happens if the project is implemented. While the costs of conducting a study may seem high to the potential members, they are relatively minor when compared with the total project investment that will be required. The expenditure for a feasibility study is actually inconsequential if it saves an unprofitable venture from going forward, thus preventing the larger capital investment needed to start most new businesses, as well as the time and effort involved, from taking place. And if the study shows that a project is indeed feasible, it provides the group with some concrete useful data that can be used in subsequent business plans and projections. Feasibility studies are useful and valid for many kinds of business development projects. Evaluation of whether to start a new business, by either new groups or established businesses, is the most common, but not the only usage. Studies can help groups decide to expand existing services, build or remodel facilities, change methods of operation, add new products, or even merge with another business. A feasibility study assists decision-makers whenever they need to consider alternative development opportunities.
Feasibility studies permit planners to outline their ideas on paper before implementing them. This can reveal errors in project design before implementation is made. Potential stumbling blocks can be identified and decisions made about whether they could be effectively addressed if the project goes forward. Applying the knowledge gained from a feasibility study can significantly lower overall project costs by keeping adverse designs and planning concepts from being made. A feasibility study presents and clarifies the risks and returns associated with the project so that prospective members can evaluate them. There is no "magic number" or correct rate of return a proposed cooperative needs to obtain before a group decides to proceed. The acceptable level of return and appropriate risk rate will vary for individual members depending on their respective personal situations and need for the proposed services of the cooperative.
Lender Considerations
A proposed project usually requires both risk capital from members and debt capital from banks and/or other financiers to become operational. Lenders typically require an objective evaluation of a project when they consider a loan investment, and a feasibility study often provides the first look at those aspects. While some groups often try to involve a lender early in the process, a feasibility study is often conducted with an eye toward explaining the project to potential financiers. Lenders have different requirements from the study than group members. Lenders are most interested in the project's ability to pay back loans while group members are interested in the benefits to them of using the cooperative. Many groups work with lenders with whom they have an established personal or business relationship. This may expedite the process of obtaining financing. Nevertheless, the lender must know and understand the unique aspects of cooperatives and fully understand the characteristics and potential of a proposed project. The feasibility study will help them in this regard. Lenders' primary concerns focus on repayment, their risk exposure, and a project's strengths and weaknesses. Lenders classify these concerns into the "5-C's": l Capacitywhat is the group's ability to repay the loan? l Capitalwhat assets are being financed with the loan and how much is requested?
Characterwho are the principals of the project? What is their background? l Collateralwhat is being used to secure the loan? How is it valued? l Conditionswhat additional factors can affect the loan? The odds for financing diminish if a lender does not fully understand the project and is unable to review the potential financial results through a sound economic and financial analysis. Success or failure of a business opportunity often hinges on obtaining adequate lender financing. For this reason, it is often a good strategy, if possible, to consult with potential lenders prior to conducting a feasibility study to determine what factors they will focus on given the type of project. Such a consultation can shorten the time that a lender needs to approve project financing, or even improve the ability of securing financing. However, while a feasibility study is important for providing information that will help in gaining finances from a lender, it should not be conducted merely to prove to them that a project is viable. It must only be undertaken when the proposed project is being seriously considered for implementation by dedicated potential members.
l
A study should not be conducted as a forum merely to support a desire that a project be successful. Rather, it should be an objective evaluation of a project's chance for success. Even studies with negative conclusions are useful for group decisions. As stated earlier, financiers may require a feasibility study before providing loans, but this should not be a study's only purpose. Although a study can enhance a banker's ability to evaluate a project, the primary goal should be to aid a group's ultimate decision on going forward, not only whether financing can be secured. A feasibility study will not determine if the project will be initiated, since that depends on the potential members, who will invest in and become the owners of the business. However, the information, data, and facts offered in a study, given realistic assumptions, provide the basis for a decision. Potential members must decide if the benefits justify the risks involved in their continuing the project and the study findings will assist them in that assessment. A study uses basic project assumptions to develop an analysis, shows how results vary when assumptions change, and provides guidance as to critical elements of a project. Conducting a study should provide the group with project-specific information to assist it in making decisions. This should lower the risk of continuing with a business development project that ultimately would fail.
study needs to be put off until another time because of a lack of support from prospective members, not enough capital to proceed, or any other given reason. Once the decision is made to invest the time and resources in a feasibility study, the group proceeds to define the project.
Here is an example of a project idea statement: A member-owned cooperative that will process and market members' soybeans for the farmers of ABC valley, to meet the area's high demand for soybean meal and soybean byproducts, and to provide strong valueadded economic benefits to members. The group then may provide some key points in addition to an idea statement to further clarify how the project will meet necessary economic, business, and technical factors.
mittee. An important prerequisite is that they be willing to join the proposed cooperative and commit to financing it and using its services. Chosen or volunteered leaders must be people that will be active participants in the development process as they will ultimately be responsible for making key decisions and plotting the project's direction within the steering committee. The steering committee must also ensure that all potential members involved feel free to voice their opinions and viewpoints about a project. Different perspectives are important considerations for developing a new business, and if alternative strategies or options are suggested and deemed important to evaluate, they should be brought into play during the feasibility study process so they can be properly assessed. In USDA's Cooperative Service Report 54, Creating 'Co-op Fever': A Rural Developer's Guide to Creating Cooperatives (see references or http://www .rurdev.usda.gov/rbs/pub/sr54/sr54.htm), author Bill Patrie mentions the following five characteristics of a project champion who provides strong leadership: 1. 2. 3. 4. Credibility Financial stability Basic knowledge of the industry Willingness to accept the servant leadership role 5. A developer, not a promoter Patrie defines these five characteristics (verbatim) as follows: 1. CredibilityIs the individual personally credible in his/her neighborhood? They need not be the biggest farmer or the most active in commodity associations, but they must be respected for their judgment. Avoid individuals who have tried every new idea that has come around and are suckers for anything new. I look for people who finish what they start and can take a long-term view. 2. Financial StabilityIs the individual capable of keeping his/her house in order? Producers who have failed before (especially if they have gone through personal bankruptcy) usually lack the credibility with other producers and lenders to lead the project. They must be able to devote time away from their personal business to help develop the cooperative. This criterion is extremely limiting because many producers lack the time it takes to do the work without jeopardizing their individual operations. I once worked with a cooperative whose interim board chair wanted to use
organizational funds to buy clothes. Her argument was that she would make a better impression on investors if she could afford to dress well. 3. Basic Knowledge of the IndustryIs the individual familiar with the industry in a comprehensive way? Most value-added cooperatives are also vertically integrated. The project champion must have a basic understanding of the entire industryfrom the first steps of production through processing to marketing to the final consumer. This is a tall order and can't be 1 easily filled. The "Madison Principles" are critical at this stage of leadership selection. Often, producers become enamored of a manufacturing technology or an available building and want to quickly close the deal to own the facility or the equipment. A true project champion must lead the group through a market analysis prior to analyzing processing facility and equipment needs. If an individual can't be found who has this basic understanding of the industry, then I look for a person who is willing to learn. 4. Willingness To Accept the Servant Leadership RoleThe project champion is often uncompensated. They will frequently be criticized, often unfairly, and sometimes insulted. Thin-skinned or quick-tempered people often do not last in the pressure-cooker environment of creating a new cooperative enterprise. I look for a project champion who has balance in her/his life. They must have patience, people skills, a good sense of humor, and a sense of what is ridiculous. 5. A Developer, Not a PromoterThis is development work, not promotion. Promotion may get column inches in the local paper and a 30-second spot on the 6 o'clock news, but it won't build a financially viable company. While enthusiasm is important, it can't replace critical common sense and solid business judgment. These five attributes are important in a project champion or leader of a cooperative development project.
The Madison Principles are 12 principles for cooperative development practitioners to follow. They were developed by the members of Cooperation Works! in Madison, Wisconsin, in 1985. See http://www.cooperationworks.coop/about/madison-principles.
directed rather than internally directed by prospective members, and in this case, potential conflicts may arise and the focus of the group's vision may be skewed. At the same time, a group should feel free to seek outside experienced consultants to help guide it through the development process, or perhaps to aid just a specific aspect of the process. For example, extension agents or lenders that interact closely with a group may be willing to help; accountants and lawyers may provide assistance in specific areas such as bookkeeping, legal structure, and drawing up legal documents; and advisors, such as USDA cooperative development specialists or development practitioners from a cooperative development center, can help the group with all or some aspects of the development process, and may even provide direct technical assistance with feasibility studies or business plans. Outside consultants are useful because of their experience and expertise with the development process and because they also work in an objective manner to ensure that all potential members' ideas, thoughts, and concerns are considered and that assumptions and information are accurate and realistic. (See the Feasibility Study Key Actions chapter for more information on choosing a consultant.)
In practice, this is not always easy to implement given the different personalities involved and the personal preferences for making decisions. Some may be slower to learn, need more time to contemplate before making a decision, or have aversions to high risk. On the other hand, some members may want to go ahead and make a decision before relevant information has been gathered and fully assessed. Balancing diverse aspects within a group can be difficult, but working to do so is paramount. Thus, decision-making often is one of the greatest initial challenges that a group faces in developing a project. Figure 2 presents some guidelines to assist groups with the decision-making process. Given the difficulty in making decisions, some groups or individuals try to avoid it. There is always more information that can be gathered, but there is also a cost to taking more time to deliberate. A decision must be made when further investigation costs more than new information is worth.
Unanimous agreement is not required to move forward; a consensus approach is better. Never decide to proceed based solely on negative reactions, such as resentment or envy toward middlemen, lenders, etc. A few reliable persons are superior to a larger number of doubtful persons. Base decision-making on economic and social realities faced by the cooperative. Make each decision only once.
l l
l l
l l
Understands cooperatives fully (their operations, governance, financial workings, etc.). Is willing to listen to the groups' ideas. Works closely with designated contact members of the steering committee or group. Is willing to revise study given feedback. Accomplishes the study within an agreed upon timeline. Works within the group's designated budget. Is a strong writer with skills in data analysis and spreadsheet design and presentation. Provides clear, useful information in the completed study.
Has previous experience conducting feasibility studies. Has experience with the industry to be stud ied, or access to experience and associated professionals. Works independently and objectively (e.g., of equipment manufacturers, marketers, etc.).
Consultants should have experience in the industry under study. Otherwise they may not correctly identify critical factors. Given business complexity, it is almost impossible for one person to have experience in all areas. Some consulting firms resolve this issue by having their feasibility specialist work with contracted industry experts. In any case, it is important to research many sources for all the pertinent information possible about an industry. A team approach may, in some instances, be utilized to develop a study. For example, a cooperative development specialist from the USDA or a practitioner from a cooperative development center could work jointly with industry specialists to create a feasibility study. The consultant should also understand the unique aspects of cooperatives. Tax implications, distribution of net margins (profits), management, and other business considerations (e.g., governance) of cooperatives differ from those of other businesses and the nuances of each must be properly presented. The consultant should avoid preconceived notions about how the project will function. The study should not be an "off-the-shelf" document assembled from previously created studies. Rather, the consultant should pay particular attention to the ideas that the group has developed and craft a unique study suited to the group's needs. The consultant should work closely with the group and be receptive to its suggestions. Also, the consultant should be prepared to make technical revisions or to correct errors given group recommendations and wishes. Revisions are a normal part of the study development process. Revisions should focus on the validity of the assumptions and the technical design of the study. Using an outside consultant brings objectivity to the feasibility study rather than merely providing the results that the group wants. Consultants have a legal
obligation to provide a responsible analysis. They should not be asked to alter the results merely to conform to members' desires for a project's viability. Timeliness is an important consideration when selecting a consultant. Projects are time sensitive. Usually, decisions to proceed await information provided in the feasibility study. So care and diligence required for a well-crafted study must be balanced against the desire for speed. A qualified consultant must be able to complete a well-designed study within a timeframe that serves the group's needs. On the other hand, the timeline must be realistic. And, a consultant can only progress as fast as a group makes the required decisions, provides information to the consultant, and carries out its other project responsibilities. Cost is an important factor. The expertise and skills that consultants offer a project must be weighed against their cost. A quicker timeline could increase a consultant's fee. Preparing a pre-feasibility analysis may decrease the effort required to complete the feasibility study and reduce the cost. Some public programs offered by the USDA's Rural Business-Cooperative Service, community development offices, the Small Business Administration, some cooperative development centers, and local business incubator programs provide technical assistance at little or no cost to groups creating feasibility studies. There are also grant programs available such as USDA's Value-Added Producer Grants program, which can provide funding for a feasibility study if a project meets the program's criteria and is selected. This program requires a one-to-one matching contribution from the applicant. A consultant should provide the data used to generate the financial tables and scenarios reported in the feasibility study and, preferably, an electronic spreadsheet format that can be easily manipulated. Although requesting this information can moderately increase the cost of a feasibility study, access to the actual data permits the group to use the information for later needs with greater flexibility. This data can also reduce the cost of creating the business plan, if the group proceeds to that stage. Additionally, it can decrease the effort required for revisions, if in the future the group changes the project's assumptions to differ from those in the study. Once the consultant has been selected, the group should provide detailed instructions on the study requirements. There should be a legally binding contract between the parties. The group should consult legal counsel for assistance. The contract should state clearly the requirements and role of both the group
and the consultant. It should have timelines, delivery dates, explicit deliverables, and what is to be accomplished before payment is made. Often, the consultant receives a downpayment before the feasibility study has been conducted. The balance is paid only after the study has been reviewed and accepted by the group (and possible financiers if appropriate). This gives the group more leverage to encourage timeliness or revisions. The contract should designate a third-party arbitrator to resolve any disputed items. A complex, large-scale project may require several consultants to complete various aspects of the study. Multiple consultants can reduce the group's dependency on a single person or company. It also can permit the group to select experts from several fields. However, it also can complicate the coordination and consistency of the information received. Before signing the contract, the group should discuss with the consultant arrangements for cost overruns, time delays, revisions, and what considerations will be made for these issues. Changes after signing the contract can be costly or delay the study results. All parties should be clear about what to expect prior to signing the contract and initiating the study. (See Appendix C for a point-award system for selecting a consultant based on select criteria.)
Members or outside financiers will often perceive the reliability of the entire study based on its least accurate piece. An otherwise well-conducted feasibility study could be viewed as inaccurate or useless because of a simple mistake. To prevent this, the feasibility study should be carefully examined for overall clarity and logical consistencyis the language appropriate; is the document well organized; and can someone who is not familiar with the project understand the study and its findings? Reviewers should confirm that the study's assumptions are clearly documented, well described, justified, and as accurate as possible. Although the contact members take the lead in working with the consultant, others should review the study carefully before the group decides to accept it. Advisors such as USDA cooperative development specialists or Extension agents can provide an objective review and offer insights on content or study assumptions. This outside review can be especially useful when the group has used consultants to prepare the report. Often, a series of draft reports are presented to the group as the study proceeds. Issues identified that warrant changes to the study are then conveyed to the consultant.
research and develop some of the assumptions may be necessary. Furthermore, some of the assumptions will have more than one option to study. That's where sensitivity analysis will come into play. Other questions that help determine proper assumptions might arise as well, depending on the type of project. It is up to the steering committee and those conducting the study to explore all avenues when determining the assumptions needed for a full analysis in a study. Considering more than one potential business structure and/or alternative business process is not a problem at this stage. However, it is important that an analysis be conducted in the feasibility study for each identified project scenario so that the steering committee or group can assess them.
Appendix D provides the USDARural Development summary guide for what a feasibility study should contain for a business applying for USDABusiness and Industry guaranteed loans (note that the criteria in the guide can be incorporated into a feasibility study).
10
Examples could be the technology of production, volume of inputs, the market for goods sold, marketing channel, personnel costs, prices paid, and capital costs. Figure 6 provides a general example outline of the major components a feasibility study might contain. This example includes eight major components, but the exact number and order of components for different studies could very well vary from these. In addition to the potential items listed in the outline below or others determined given the project, a study should include a title page, the name of the person(s)/firm who conducted the study, and a table of contents. General descriptions of each of the sample components included in Figure 6 are described in the following sections (sections include relevant outline items).
Executive Summary
I. Executive Summary A. Summary of the Important Findings and Recommendations
It is important to have a concise summary of the critical segments of the report in an executive summary at the front of the report. This will allow reviewers to gain a strong sense of the report's significant information and major findings before they proceed with reading the entire study. Each major part of the report should be briefly and clearly summarized. When applicable to the major findings and final conclusions, significant data reflecting concrete analysis should be provided, and a summary of the key recommendations listed. This segment of the report should provide a context from which the reader will be able to better decipher all the components and findings of the report. As a means of setting the foundation for the study, it is important to also identify the steps completed for the project up to the current point in time, and the names of those heavily involved (the steering committee members at least).
11
Introduction
II. IntroductionProject Description and Justification A. Description of the project B. General setting and need for project C. Work already completed, pertinent dates, and those involved in the project
This section is usually somewhat brief and simply introduces the cooperative project and provides some justification for its need. Information as to when the project process began and in what stage it is now should be offered. In general, size and scope of the project, membership aspects, methodology employed for data collection, marketing and economic conditions, competition, relevant technical factors, economic and community conditions, etc., can all be briefly
12
introduced to provide the reviewer/reader with an overall general conception of what the cooperative project entails.
Industry Background
III. Industry Background A. Basic background information on the industry B. Economic conditions of the industry C. Implications and feasibility of entering industry The state and status of the industry within which the cooperative will operate should be described in as much detail as possible and be broken down into geographic applicability (i.e., foreign, domestic, regional, local) to the project. The study should include charts and graphs of industry trends (e.g., volume, prices, byproducts, etc.), as well as a complete assessment of the competitive environment to properly define the need or fit of the cooperative within the industry sector. Pertinent data from industry organizations is helpful if it can be acquired. Government regulations and policies within the industry in question should be fleshed out and their relevance to the proposed business explained. Any regulations that might need to be met (e.g., environmental impact assessments, permits, etc.) should be clarified and analyzed. Costs associated with the government regulations and policies of an industry will need to be documented for the financial projections section.
products will be introduced and channeled into available markets. A description of potential customers, processors, handlers, etc. should also be provided. Procurement and sales strategies for commodities or goods to be purchased and/or sold should be described. This section should address market demand implications, marketing costs, transportation issues, coordination with others in the market chain (e.g., brokers, venders, manufacturers, processors, pooling, etc.), the quality and form of the products to be marketed, and an overall strategic assessment of marketing the product or products. When applicable, information from market outlook reports (e.g., USDA and other government agencies) that provide forecasts on specific crops, products, and industries are helpful for providing a context for the marketing plan. Relevant charts, graphs, and tables should be provided to present a clear picture of the marketing environment. If it's a value-added venture, the implications of marketing the resulting products should be defined. How those products fit into existing markets given competitors' similar products should be researched and reported. From the overall marketing analysis, an assessment of the feasibility of the proposed marketing plan should be included.
Marketing
IV. Marketing A. Market potential for goods to be handled or services to be provided B. Markets to be served (current and future) and their attributes C. Ease or limitations of entering the market D. Marketing plan (strategies to be followed, associated costs, summary of key actions) E. Overall assessment of the marketing situation and plan Various components of the project's proposed marketing plan, whether for products to be marketed or goods to be sold, need to described and analyzed. The marketing environment should be fully described. The description should include how the product or
13
study should address the ability of the project to operate efficiently within the scope of the project's parameters. It is important to provide information on the technical aspects of the project and to show how the proposed technologies will work within the context of the entire project. In projects with unproven technologies, this can be the most important aspect of a study and it provides a basis for close assessment. In projects with proven technologies, the study can serve to correct design flaws before costly mistakes are implemented. If the project requires construction of a sophisticated facility, such as a meatpacking or soybean processing plant, professionals such as architectural, engineering, or management specialists will need to be consulted early in the process. The needed expertise should be described in the feasibility study. Assistance that will be needed for loan agreements, legal contracts, and construction should be documented also. If a location has been selected, the study should address the implications of that locationis it efficiently situated for the potential labor supply, is it adequate for delivery and distribution channels, does it meet city/town ordinances and regulations, will permits be required, resources be available to cover its costs, etc.? If a location has not been selected, the feasibility study may provide some prerequisite stipulations, data, and standards by which to choose a location given the type of project, industry, and technology involved.
important to do a thorough and careful job with the financials. Financial projections are usually made for 3 years. Cash flow statements should be monthly, while income statements and balance sheets should be monthly or quarterly for the first year and then annual for the second and third years. Financial statements and projections stem from valid and objective assumptions. Financial assumptions, such as capital requirements, equity needs, prices, human resources needed, and other factors, will come into play here. Because the economics of the project are so important to project assessment, assumptions must be in line with the reality of the situation and should not be overly optimistic or simplistic. Assumptions such as price forecasts/projections should be based on solid facts, such as historical prices and changes that have occurred in the industry which may affect the outlook. The sources for the facts and the rationale for key assumptions should be well documented either in the report body or in an appendix. Most feasibility studies begin with pro forma cash flow statements based on the assumptions and other data collected about the project, such as equity collected, product volume, purchases, sales, and expenses, for example. Besides equity, revenue streams and operating costs, the pro forma statements must include repayment and interest on potential short-term and long-term debt and/or other investments in the project. The cash flow statements (usually done on a monthly basis) must clearly show when capital is introduced and when it is repaid. This is important for indicating the project's repayment capacity, a critical consideration for a lender or investor. For a sample pro forma cash flow statement, see Appendix E. Also included in this section are income statements, balance sheets, and sources and uses of funds statements (or statements of cash flows). These pro forma statements provide important information beyond the cash flow analysis. The plan for accumulating needed member equity adds even more information by providing dates, sources, and amounts of equity expected (this information will be likely obtained from a potential member survey). Another useful analysis to include is a ratio analysis where ratios are developed from the pro forma statements. For example, current ratios, debt ratios, assets turnover, return on net worth, return on investment, return on sales, etc., should be formulated and compared during the projected years. For sample pro forma operating, balance sheet, and ratio statements, see Appendices F, G, and H, respectively.
14
In the financial analysis, the study should show the impact of varying key project assumptions. This controlled variation, called sensitivity analysis, permits planners to view which project elements are the most susceptible to positive and negative changes. For example, what impact does a 10-percent reduction in sales volume have on net margins? The sensitivity analyses conducted should then be studied, and those that are potentially realistic should be developed into specific scenarios, which would involve looking at all aspects of how the proposed possible changes would affect the project. Both "worst-case" possibilities and optimistic scenarios should be created for comparison purposes. A comparison table and discussion should be developed so that it's easy to assess the differences between scenarios. The financial section should summarize all the findings of the financial analyses and provide an overall assessment of the financial and economic implications of the project. The financial impacts at both the cooperative and member level should be detailed.
investors, potential legal and governmental setbacks that could come into play, and time-critical factors, among others. If the study shows that the project is clearly feasible, this section should describe any important work that still needs to be done and actions that need to be taken (with relevant dates) as the group works toward a solid business plan and implementation. If the study found that more information, resources, etc. are needed before the project will be feasible, it should clearly state such discrepancies and provide recommendations for potential actions that could alleviate the issues.
Appendix
VIII. Appendix A. Appendices (additional spreadsheets) B. Important supplemental information C. Notes, credentials, and references The appendix of the report should include supplemental tables, spreadsheets, charts, and informationthat are related to the analysis and descriptions in the report's bodythat will provide the reviewer with a greater understanding of the project. Some examples of supplemental information, which will be highly dependent on the type of business being studied, might include: l Background information on assumptions used in the analysis if not fully described in the body of the study (some might be derived from potential spreadsheet data given as examples here). l Monthly inventory tracking spreadsheets for commodities to be handled, purchased,processed, sold etc. l Monthly sales price spreadsheets for commodities to be handled, purchased, processed, sold, etc. l Capital purchase and depreciation schedules for land, buildings, equipment, parts, etc. l Employee schedules and salary/wage information for any staff that will be hired (management, sales representatives, administrative staff, warehouse personnel, laborers, etc.). l Debt repayment schedules for different categories of borrowing (real estate, equipment, working capital, etc.). l Pro forma financial statements (cash flow, operating, balance sheet, etc,) for different scenarios studied, but that weren't a major focus in the body of the report.
15
Other industry or territorial information, such as commodity or product alternative uses and sources, commodity processing yield data, demographic data, competitive data and mapping, etc. l Credentials of those involved in developing or assisting with the study. l References used in the study and resources that will be useful as the project progresses. In some cases, this stated supplemental information will have been addressed in the study's main sections, so it won't have to be included in the appendix unless more information is deemed to be required.
l
should have the consultant revise it to reflect these changes or initiate a new study. This permits the group members to make decisions with all applicable information.
16
address any recommendations and limitations the feasibility study outlines before it takes the time and approves the expense that a business plan will take. If a decision is made to proceed with the project, the steering committee and group should first look at the study's recommendations to see what, if anything, needs to be accomplished before a business plan is developed. For example, does the study advise exploring joint ventures with processors or other industry partners or organizational structures (such as a limited liability company), obtaining marketing contracts from prospective members, getting attorney assistance to meet Federal or State security laws, researching other marketing avenues, etc.? Written records of the decision-making process should be made and retained. The steering committee and group have a legal responsibility for adequate due diligence. An attorney should be apprised of project developments as they occurin this case the acceptance, rejection, or need for further analysisof the feasibility study. The attorney needs this information to provide appropriate legal counsel to the steering committee and group as it proceeds. If all issues, recommendations, and limitations are fully explored, and the project is declared feasible, the group and steering committee proceed to develop a business plan (which is part of Step 7, in How to Start a Cooperative, CIR 7). Many components and analyses contained in the feasibility study will be used in the business plan. The steering committee and consultant should work to identify those parts that are relevant and acceptable for inclusion in the business plan. With the development of the business plan, the steering committee and group will work toward completing the remaining events/steps of development, as explained in CIR 7.
from USDA's Cooperative Programs (http://www.rurdev.usda.gov/rbs/pub/cir55/cir55rpt.htm. (Reference follows) Frederick, Donald, A. Co-ops 101, An Introduction to Cooperatives, Cooperative Information Report 55, Rural Development, U.S. Department of Agriculture, Washington, DC, April 1997, revised March 2005.
The Agricultural Marketing Resource Center has extensive information on value-added businesses available at www.agmrc.org. This site also provides links to resources for feasibility studies and business planning. Outside advisors can assist in the development process as well as be providers of other sources of background information. There are a number of cooperative development centers around the nation with the sole purpose of being practitioners of cooperative development. Some of these centers belong to the Cooperation Works! cooperative development network (http://www.cooperationworks.coop). However, there are centers outside of that network as well. Those interested in developing cooperatives can benefit from contacting a cooperative development center in their state or region (if there is one) for assistance. USDA Websites: U.S. Department of Agriculture: http://www.usda.gov/ USDA Cooperative Programs: http://www.rurdev.usda.gov/rbs/coops/csdir.htm USDA Cooperative Programs (publications):
http://www.rurdev.usda.gov/rbs/pub/NEWPUB.htm
USDA Rural Development: http://www.rurdev.usda.gov/ USDA Rural Development can also assist you from its State Offices. Please look up and contact the Rural Development State Office within your state:
http://www.rurdev.usda.gov/rbs/coops/cscontac.htm
Outside websites/resources: University of Wisconsin Center for Cooperatives: http://www.uwcc.wisc.edu/ Quentin Burdick Center for Cooperatives: http://www.ag.ndsu.nodak.edu/qbcc/
17
18
The business plan is created after the feasibility study. Project details, which required assumptions for the feasibility study, have been decided. Standard business plans include details such as key management personnel, business location, the financial package, product flow, and possible customers. The feasibility study should be an independent review of the project by one or more experts outside of the group. In contrast, the group itself typically develops its business plan internally, sometimes with the assistance of a consultant. It needs to be based on group members' vision for the business, since they will be the owners. The group revises the plan with information from bankers and investors once the project situation becomes more defined. Although this difference is not as important for project development considerations, the feasibility study is only used prior to implementation. In contrast, businesses continue to use and revise their business plans after a project has been implemented. The feasibility study refines the group's initial ideas, while the business plan uses information from the study to further prepare the project to evolve into an operating business.
* Adapted from USDA's Cooperative Service Report 54, Creating 'Co-op Fever': A Rural Developer's Guide to Forming Cooperatives.
19
Appendix D-USDA Rural Development Summary Guide for Feasibility Studies Included in Applications for Business & Industry Loan Guarantees (Instruction 4279-B)
A feasibility study by a recognized independent consultant may be required by the Agency for start-up businesses or existing businesses when the project will significantly affect the borrower's financial operations. An acceptable feasibility study should include, but not be limited to: (a) Economic feasibility. Information related to the project site; availability of trained or trainable labor; utilities; rail, air, and road service to the site; and the overall economic impact of the project. (b) Market feasibility. Information on the sales organization and management, nature and extent of market and market area, marketing plans for sale of projected output, extent of competition, and commitments from customers or brokers. (c) Technical feasibility. Technical feasibility reports shall be prepared by individuals who have previous experience in the design and analysis of similar facilities or processes proposed in the application. The technical feasibility reports shall address the suitability of the selected site for the intended use including an environmental impact analysis. The report shall be based upon verifiable data and contain sufficient information and analysis so that a determination may be made on the technical feasibility of achieving the levels of income or production that are projected in the financial statements. The report shall also identify any constraints or limitations in these financial projections and any other facility or design-related factors which might affect the success of the enterprise. The report shall also identify and estimate project operating and development costs and specify the level of accuracy of these estimates and the assumptions on which these estimates have been based. For the purpose of the technical feasibility reports, the project engineer or architect may be considered an independent party provided neither the principals of the firm nor any individual of the firm who participates in the technical feasibility report has a financial interest in the project, and provided further that no other individual or firm with the expertise necessary to make such a determination is reasonably available to perform the function. (d) Financial feasibility. An opinion on the reliability of the financial projections and the ability of the business to achieve the projected income and cash flow. An assessment of the cost accounting system, the availability of short-term credit for seasonal business, and the adequacy of raw materials and supplies. (e) Management feasibility. Evidence that continuity and adequacy of management has been evaluated and documented as being satisfactory.
20
Item
Mth 1
Mth 2
Mth 3
Mth 4
Mth 5
Mth 6
Mth 7
Mth 8
Mth 9
Mth 10
Mth 11
Mth 12
Totals
CASH RECEIPTS Cash sales** Credit collections Commission fees Interest income Loans/equity
TOTAL RECEIPTS CASH PAID OUT Purchases** Salaries Employee wages Payroll expense Bad debts Outside services Supplies Repairs & maintenance Advertising/promotion Car/travel Accounting & legal Rent Telephone Utilities Insurance Property taxes Other taxes Interest on loans*** Depreciation Miscellaneous Subtotal Principal payment*** Capital purchases Income taxes
21
22
Mth 1 Mth 2 Mth 3 Mth 4 Mth 5 Mth 6 Mth 7 Mth 8 Mth 9 Mth 10 Mth 11 Mth 12 Totals
Item
Other withdrawl TOTAL CASH PAID CHANGE IN CASH Beginning balance Ending balance
*May have multiple statements for different years. **May have more than one cash sale and purchases line (more commodities/products). ***May have more loan and interest payment lines if more loans are obtained.
INCOME Cash sales Commission fees Total sales Cost of goods sold GROSS MARGIN EXPENSES Salaries Employee wages Payroll expense Bad debts Payroll expense Outside services Supplies Repairs & maintenance Advertising/promotion Car/travel Accounting & legal Rent Telephone Utilities Insurance Property taxes Other taxes Depreciation Miscellaneous TOTAL OPERATING EXPENSES Operating income Interest expense NET MARGIN Unallocated earnings Allocated earnings
and inclusion depending on project.
* This example shows ve-year projections but many projects focus on just three years. Operating statement line items will vary in description
23
Current assets Cash Accounts receivable Inventory Prepaids (e.g., insurance) Other Total current assets Fixed assets Machinery & equipment Buildings Land Less: accumulated depreciation Total xed assets TOTAL ASSETS LIABILITIES AND MEMBER EQUITY Current liabilities Accounts payable Taxes payable Patronage refunds payable Line of credit Interest payable Total current liabilities Long term liabilities Machinery and equipment note Real estate and building Total long term liabilities Total liabilities Member Equity Common stock Preferred stock Allocated earnings nallocated earnings Per unit capital retains Total member equity TOTAL LIABILITIES & MEMBER EQUITY
* This example shows ve-year projections but many projects focus on just three years. Balance sheet line items will vary in descriptions and
24
Current ratio (current assets/current liabilities) Debt ratios (total debt/total assets) (total debt/member equity) Average collection period (receivables/sales per day) Total assets turnover (sales/total assets) Protability ratios Return on equity (net margins/total equity) Return on Invesment (net margins/Investment) Return on sales (net margins/sales)
* This example shows ve-year projections but many projects focus on just three years. Ratio analysis items will vary in descriptions and
25
Rural BusinessCooperative Service (RBS) provides research, management, and educational assistance to cooperatives to strengthen the economic position of farmers and other rural residents. It works directly with cooperative leaders and Federal and State agencies to improve organization, leadership, and operation of cooperatives and to give guidance to further development. The cooperative segment of RBS (1) helps farmers and other rural residents develop cooperatives to obtain supplies and services at lower cost and to get better prices for products they sell; (2) advises rural residents on developing existing resources through cooperative action to enhance rural living; (3) helps cooperatives improve services and operating efficiency; (4) informs members, directors, employees, and the public on how cooperatives work and benet their members and their communities; and (5) encourages international cooperative programs. RBS also publishes research and educational materials and issues Rural Cooperatives magazine.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all of its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, political beliefs, genetic information, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD).. To le a complaint of discrimination, write to USDA, Assistant Secretary for Civil Rights, Office of the Assistant Secretary for Civil Rights, 1400 Independence Avenue, S.W., Stop 9410, Washington, DC 20250-9410, or call toll-free at (866) 632-9992 (English) or (800) 877-8339 (TDD) or (866) 377-8642 (English Federal-relay) or (800) 845-6136 (Spanish Federal-relay). USDA is an equal opportunity provider and employer.