Shuttring, Deshuttering, Steel Fixing, P.C.C and R.C.C Work Jsa

shuttering work jsa deshuttering work jsa steel fixing work jsa r.c.c work jsa p.c.c work jsa shuttering, deshuttering, steel fixing. p.c.c and r.c.c work jsa civil work jsa jsa job safety analysis

Uploaded by

AKBAR ALI
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
554 views5 pages

Shuttring, Deshuttering, Steel Fixing, P.C.C and R.C.C Work Jsa

shuttering work jsa deshuttering work jsa steel fixing work jsa r.c.c work jsa p.c.c work jsa shuttering, deshuttering, steel fixing. p.c.c and r.c.c work jsa civil work jsa jsa job safety analysis

Uploaded by

AKBAR ALI
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Jubliant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

JSA NO. Department / Routine/ Non


Job Title: New/ Revised
Activity/ No… Routine

Reference work
Permit no:
JOB SAFETY Supervisor:
Prepared By:
ANALYSIS

Plant Location: Unit-1


Department: Project
Reviewed By:
Niacinamide

Job Description: R.C.C, P.C.C, shuttering, de-shuttering and steel fixing


work Approved By:

SEQUENCE OF TASK POTENIAL HAZARDS PREVENTIVE MEASURES

 Mobilization of  Unskilled workers,  Site safety induction should be provided to all new
Manpower  Unauthorized entry employees.
 Deploy experienced trained skilled worker for specific jobs.
 Job specific training should be given
 TBT to be taken on daily basis prior to start the job
Mandatory
 PPE’s should be provided viz. safety helmet, safety shoes,
reflective jacket etc.
 Safety Awareness/motivational programs shall be conducted
to workmen for more awareness on safety.
 Medical fitness is must for all workers.
 Gate pass compliance (As per JIL HR Dept) shall be complied.
 Storage of shuttering  Slip, trip & fall  All shuttering material should be stored properly with
material hazards may arise due sufficient stacking height.
to improper  Properly secure or tie store shuttering material
housekeeping at  Shuttering yard areas to be demarcated and barricaded.
shuttering material
storage area
 Manual handling of  Sharp edge or  Use mandatory PPEs safety shoes, helmet, gloves & goggles
shuttering material protruding nails etc.
 Lifting of excess  Bend / remove unwanted protruding nails. Use proper tool
weight to remove embedded nails, nails to be collected in proper
 Material falling on box, maintain good housekeeping.
feet.  Supervisor shall be ensure that no workman will lift more
 Slippery surface & than 20 kg for manually handling loads more than 20kg,
tripping hazard. deploy a team of required manpower.

Page 1 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

 Wrong posture.  Provide shoulder pad for material shifting.


 Ensure obstruction free accesses to work place.
 Ensure proper packing is provided below the stacked
material
 PPEs safety shoes with steel toe shall be provided.
 Shuttering material stack height to be limited to 1.2 mtr.
 Shuttering frame  Inadequate designed,  Skilled carpenter & fitter to be deployed for shuttering work.
making/formwork fabricated, and  Continue supervision to be provided.
supported form work.  Ensure proper tying or fixing of shuttering.
 Cut hazard  Support formwork or shuttering secured with both ends.
 Dust  The vertical supports shall be adequately braced or
 Trapping and pinching otherwise secured in position.
 Inadequate tying of  Avoid excessive stacking on shuttering material.
frames.  Provide the rubber / PVC insulated sleeve for the hammer.
 Rusted or spoiled nuts  After assembling the basic unit, adjustment screw shall be
and bolts. set to their approximate final adjustment.
 Protruding nails.  The centring frames shall be tied together with sufficient
 Uneven ground. braces to make rigid and solid.
 Do not used rusted or spoiled threaded nuts & bolts.
 Use of adequate PPE's are provided, proper communication
amongst crew.
 Ply wood cutting for  Wrong operation of  Ensure only valid & inspected ply cutter machine should be
shuttering work ply cutter machine. used by competent person.
 Dust  Inspect work locations and ensure closure of observations.
 Flying of small  Inspect hand tools before use, use right tool for right job.
particles.  Use of dust mask/Nose mask.
 Electrical shock  All electrical connection given through ELCB (capacity 30
 Defective hand tools mA).
 Flying Nail leading to  Electrical connection shall be taken only through authorized
bodily injury electrician.
 Ensure joint free cable is used for the electrical connection
and protection
 Maintain good housekeeping in the area.
 Deploy trained persons, use of adequate PPE's.
 Access way should be free from obstacles.
 Electric supply cable should be having industrial/waterproof
pin top.
 Tool box talk conducted by concerned engineer or
supervisor before start of work.
 Work permit should be taken before start the work,
 Only skilled person are allowed to execute ply wood cutting
work.
 Use of safety glasses, Hand gloves, Appropriate PPES, restrict
unauthorized person at workplace.

Page 2 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

 De-shuttering work  Failure of scaffolding.  Ensure continuous supervision during deshuttering work.
 Fall of shuttering  Proper inspection of scaffolding by certified inspector,
material required strengthening, supporting before start of work.
 Contact with bare  Barricade the deshuttering area.
nails,  Only authorized persons are allowed.
 Access block,  Do not keep loose material on working platform
 Improper material  Follow proper sequence while shuttering / deshuttering
storage work.
 Use of steel toe safety shoes.
 Conduct tool box talk before starting the work.
 Ensure access way should be free from obstruction.
 After Deshuttering, all nails must be removed from shutter
material or sharp point of nails must be bend or sheared off.
 Properly stack de-shuttering material.
 Provide safe & unobstructed access way.

 Work inside the  Injury to person inside  Ensure that work permit procedures are followed.
confined space the confined space  Ensure that in & out record in confined space entry should be
 Oxygen mentioned.
deficiency/hazardous  Gas testing shall be carried out to ensure toxic gases.
gases  Ensure the confined space check list then start the work.
 Property damage  Competence, training, supervision and suitability.
 Personnel/equipment  Proper ventilation either through natural or fan.
fall in confined space
 Wear appropriate PPE
 Awkward Access/
 Confined space attendant still attend outside of confined space
Egress
until person working inside the confined space.
 Personnel /equipment
fall in, collapse of  Ensure proper good condition of ladder.
excavated adjacent  Ensure proper entrance & exit of confined area
 Keep access always clear from obstructions.
 Ensure the excavated area hard barricaded
 Remove all of loose items from excavated adjacent to avoid falling
 Ensure proper shoring or maintain slope to avoid collapse of
excavated area.
 R.C.C and P.C.C work  Dermatitis disease  TBT conducted before starting the work.
 Personal injury  Ensure work under supervision.
 Body or eye injury  Ensure all equipment in good condition and inspected by competent
 Loss of eye person.
 Slip/Trip hazard  Wear mandatory PEEs like rubber gloves, gum boot, safety goggles,
 Sprain and strain on body goggles etc.
parts.  Wash the effected body parts with water immediately after concrete
 Noise burn.
 Trapping of legs inside  Engage only trained worker for concreting work.
reinforcement mats.  Use hearing protection when noise level exceeds more than 85db.
 Concrete burn

Page 3 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS
 Rebar installation/steel  Hand injury  Conduct tool box talk before start the work.
fixing work  Cut/puncture/hand  Make sure all protruded nail remove before wooden material lying at
injury the ground.
 Slip/Trip/Fall  Cover re-bar to avoid tripping where access is necessary. Wire mesh
 Property damage will be installed on top of rebar mats to minimize slip, trip and fall
 Pinch point hazards.
 Heat  Remove all unwanted material and secure properly to keep access and
egress free from obstruction.
Stress/Exhaustion  Wear appropriate PPEs before starting the work.
 Back injury  Tool must be inspected before used.
 Competent person must be deploy
 Ensure area are clear and materials properly stack within the
working area.
 All rebar’s that is protruding must be capped and kept
secured
 Workers will be oriented about the proper posture and
positioning during the execution of the job.

 Mobilization and  Driver unaware about  Vehicle fitness certificate to be checked.


demobilization of T.M site conditions may  Vehicle internal inspection is conducted.
cause of incident lead to  Accessories required with the vehicle should be checked (ex.
property damage or Wheel stoppers).
injury  Access is free from obstruction.
 Unfit Vehicle comes on  Signal man is in continuous contact with the TM driver.
site may leads to  Mandatory PPE's is provided (Safety shoes, helmet, goggle and
property damage & jacket etc.)
bodily injury  Ensure that 10 feet clearance around TM.
 Access blocked due to
TM may leads to
problem in case
emergency situation
 Movement of miller
struck with person.

 Concrete compaction  Fall/slip/trip  Pre start work tool box talk discuss and understand the hazard on the
using vibrator machine  Eye injury area.
 Property damage  Ensure all workers train and competent to perform task.
 Wear mandatory PPEs like hand gloves, goggles, gum boot, helmet etc.
 Vibrating tool causing  Ensure cable should be proper routed at working area and free from
finger/hand injury joint.
 Electric shock  User take regular breaks from the activity alternate the task between
 Excessive noise different people.
 Provide ELCB in distribution board.

 Work during night  Poor Illumination  Night work permit to be taken from concern engg.and safety
shift  fall of person dept.
 fall of machinery  Ensure proper illumination during dark hours. (50 lux on
access & 110 lux on work location)
 Electrical cable should lead min 2 m height. No exposed

Page 4 of 5
Format No.: EHS-006/F06-00 Effective Date:
Jubliant Infrastructure Limited-Bharuch

Annexure-6
JOB SAFETY ANALYSIS

electrical wire.Earthing.
 Route shall be illuminated.
 Ensure continues supervision provided at work place. Avoid
extra hours working.
 Housekeeping  Slip, trip hazards  Ensure entire area shall be cleaned after job is completed.
Remove unwanted material from site after close the job.
 Erection material should be proper stacking.
 In Case of Emergency  Confusion  Emergency assembly point, emergency access should be
defined & always free from any obstructions.
 Emergency contact details to be displayed at prominent
locations of site.
 Emergency vehicle must be available at work locations
during all working hours.
 All workers shall aware / trained about site emergency
procedure.

Day-1 Day-2 Day-3 Day-4 Day-5 Day-6

Permit issuer

Permit acceptor

Prepared by- Permit Issuer and Permit Acceptor Reviewed by-Plant Manager/ Safety
officer

Approved By HOD

Page 5 of 5