0% found this document useful (0 votes)
12 views

CVL742-Module 1, Part 4 Activity Definition and Dependency

The document discusses project scheduling and activity definition. It explains that activities refer to specific tasks or items of work, and should be defined separately if they involve different resources or are not continuously performed. Activities have start and end dates, durations, resource requirements, and logical relationships. More detailed activity definition allows for more realistic scheduling and control. The document outlines different methods for defining activities, including work breakdown structures and considering internal and external dependencies between activities.

Uploaded by

Ahmad Shaghasi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views

CVL742-Module 1, Part 4 Activity Definition and Dependency

The document discusses project scheduling and activity definition. It explains that activities refer to specific tasks or items of work, and should be defined separately if they involve different resources or are not continuously performed. Activities have start and end dates, durations, resource requirements, and logical relationships. More detailed activity definition allows for more realistic scheduling and control. The document outlines different methods for defining activities, including work breakdown structures and considering internal and external dependencies between activities.

Uploaded by

Ahmad Shaghasi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 31

CVL742

Project Management
Module 1 (Part 4)
Schedule Development:
Activities and their Sequence

Instructor:
S. Madeh Piryonesi, PhD

1/21/2024 S. Madeh Piryonesi, Project Management 1


Project Activities
• Activity or Task are used interchangeably

• Activity refer to specific, defined items of work and construction


process
• In construction defining activity is not independent from
construction method
• Example: pump concrete or use bucket?

1/21/2024 S. Madeh Piryonesi, Project Management 2


Activity Definition
• Define separate tasks for activities that involve different
resources, or those that do not require continuous
performance
• For example:
o Place and cure concrete ➔ Place concrete and cure concrete
o Prepare and check drawings ➔ Prepare drawings and check
drawings
• A schedule activity has:
o Start and end
o Cost, duration and resource requirements
o Logical relationships to other activities

1/21/2024 S. Madeh Piryonesi, Project Management 3


Activity Definition
• Usually more detailed definition allows more realistic scheduling
and better control
• For example, the activity of placing concrete on site would have
sub-activities associated with
o Placing forms
o Installing reinforcing steel
o Pouring concrete
o Finishing the concrete
o Removing forms
o Curing concrete
• You can even add more: cleaning concrete forms
1/21/2024 S. Madeh Piryonesi, Project Management 4
Activity Definition
Discussion:

• Think about decomposing our last sub-activity, i.e., cleaning


concrete forms, into smaller sub-activities.

1/21/2024 S. Madeh Piryonesi, Project Management 5


Activity Definition
• Activities may be defined subjectively or even anecdotally
• A more objective and systematic approach is to use WBS
• PCWBS and FWBS method

1/21/2024 S. Madeh Piryonesi, Project Management 6


Project Control WBS: Deliverable-
Based Decomposition

Deliverable-oriented decomposition

1/21/2024 S. Madeh Piryonesi, Project Management 7


Functional WBS: Function-Based
Decomposition

Deliverable-oriented decomposition

1/21/2024 S. Madeh Piryonesi, Project Management 8


Activity Definition: PCWBS and FWBS

Project control WBS


Functional WBS

Deliverable-oriented decomposition

1/21/2024 S. Madeh Piryonesi, Project Management 9


List of Activities
Duration Resources

Deliverable-oriented decomposition

1/21/2024 S. Madeh Piryonesi, Project Management 10


Activity Sequencing

Source: PMP Project Management Professional Study Guide, Third Edition (Certification Press)
1/21/2024 S. Madeh Piryonesi, Project Management 11
Steps for Scheduling
Work
List of Activity
Breakdown Network
Activities Dependencies
Structure

Activity
1
Activity
2

1/21/2024 S. Madeh Piryonesi, Project Management 12


A Schedule Must be Precise

1/21/2024 S. Madeh Piryonesi, Project Management 13


Activity Dependency
• Dependencies (or relations) among activities means that the
activities must take place in a particular order
• Many natural sequences exist for construction activities due to:
oRequirements for structural integrity
oRegulations
oOther technical requirements

1/21/2024 S. Madeh Piryonesi, Project Management 14


Types of Dependency
• Mandatory (necessary) dependencies
• Discretionary dependencies
• External dependencies
• Internal dependencies

1/21/2024 S. Madeh Piryonesi, Project Management 15


Types of Dependency
• Mandatory (necessary) dependencies usually cannot be modified.
They are:
o Contractually required or
o Inherent in the nature of the work
➔Example: Walls must be built after the foundations

• Discretionary dependencies may be modifiable


o Are based on best practices or project preferences.
o May be modified
➔Example: All electrical works should start after the completion of painting
➔Example: Two activities that may require the same piece of equipment

1/21/2024 S. Madeh Piryonesi, Project Management 16


Types of Dependency
• External dependencies: Relationship between project activities and
non-project activities
o Usually cannot be modified
➔Examples: delivery of equipment from a vendor, the deliverable of another
project, the decision of a committee, lawsuit, or expected new law

• Internal dependencies: A relationship between one or more project


activities.
o May be modifiable.

1/21/2024 S. Madeh Piryonesi, Project Management 17


Activity Sequencing
• The project schedule can be visualized after the activities are
sequenced.
• Activity Diagramming Method (ADM) also called AOA is a
method of constructing a project schedule network diagram that
uses arrows to represent activities and connects them at nodes to
show their dependencies
• Older network diagramming methods used “Activity-on-Arrows
(AOA)”
• More recent methods are based on “Activity-on-Nodes”

1/21/2024 S. Madeh Piryonesi, Project Management 18


Activity Diagramming Method
Activity on Arrow (AOA)
• The arrow method is ‘event oriented’
• Events are shown as nodes and signify start and finish of activities
(events have no time duration)
• Activity is the work required to proceed from one event or point in
time to another event

Start event Finish event


Activity name
1 2
Activity duration

1/21/2024 S. Madeh Piryonesi, Project Management 19


Activity Diagramming Method
Activity on Arrow (AOA)
• The end event of preceding activity is linked to the start of
succeeding activities
• When activity X is followed by activity Y, only one event is needed to
show the end of activity X and the start of activity Y

Start event of X Finish event of X Start event of Z Finish event of Z


Activity X Activity Y Activity Z
1 2 3 4

1/21/2024 S. Madeh Piryonesi, Project Management 20


Activity Diagramming Method:
Activity on Arrow (AOA)
• Activities are drawn from left to right (no right to left)
• It is assumed that succeeding activity cannot start until the preciding
activity is completed (finish-to-start links)

Start event of X Finish event of X Start event of Z Finish event of Z


Activity X Activity Y Activity Z
1 2 3 4

1/21/2024 S. Madeh Piryonesi, Project Management 21


Activity on Arrow (AOA) Example 1
• Activities A and B are independent; Activities C and D cannot start
until activities A and B have been completed; Activities C and D are
independent

1 4
A
C

3
B D
5
2

1/21/2024 S. Madeh Piryonesi, Project Management 22


Activity on Arrow (AOA) Example 2

• Let’s now assume that the start of activity C depends only on the
completion of activity A (so C is independent of B)
X is a dummy activity

1 4 1 3 5
A C A C
X
B 3 D B D
2 5 2 4 6

1/21/2024 S. Madeh Piryonesi, Project Management 23


Activity on Arrow (AOA) Method
• Dummy activities serve another purpose in arrow networks
• They are needed to identify activities by their correct event numbers

A
1 1
B A
X
3 C B C
4
2 4 6

1/21/2024 S. Madeh Piryonesi, Project Management 24


Precedence diagramming method (PDM)
Activity on Node (AON) Method
• The precedence method has widely replaced AOA method as the
preferred scheduling technique
• AON method is activity-oriented (no events at all)

Preceding Succeeding
activity activity

Dependency Placing
Installing
formworks concrete

1/21/2024 S. Madeh Piryonesi, Project Management 25


Precedence diagramming method (PDM)
Activity on Node (AON) Method
• The process of constructing an AON network is similar to that of
AOA
• The flow of works progress from left to right
• Dependency lines may be drawn up and down, but never from right
to left
• To show the direction of the workflow arrowheads are attached to
dependency lines
• Dummy activities are not required to maintain the logic of network
(milestones are like dummies)

1/21/2024 S. Madeh Piryonesi, Project Management 26


Example of PDM or AON Method
• Create a precedence network for the following activities.

A D F
Start C
End
B E G

1/21/2024 S. Madeh Piryonesi, Project Management 27


Precedence Diagraming vs Activity
Diagramming
Activity A Activity B
▪ Activity-on-Arrow (AOA) or or
Activity 1-2 Activity 2-3
▪ Activities are shown by arrows 1 2 3
▪ It is an event-oriented method
Event 1 Event 2 Event 3

▪ Activity-on-Node (AON)
▪ Activities are shown by nodes
▪ It is an activity-oriented method A B

1/21/2024 S. Madeh Piryonesi, Project Management 28


Sequencing Activities: Types of
Dependencies
Finish to Start Finish to Finish
(FS) (FF)
Example: Example: Drawing
Construction of a the lines on a road
wall cannot start cannot finish until
Activity FS Activity FF
until the 1 placing the
1
foundation is pavement is
Activity
finished. finished.
2 Activity
2

1/21/2024 S. Madeh Piryonesi, Project Management 29


Sequencing Activities: Types of
Dependencies
Start to Start Start to Finish SF is not
(SS) (SF) common in
construction.
Example:
Painting cannot
SS Activity Example:
start until the
1 Handover
scaffolding Activity Activity works are
begins. 1 2
Activity examples of
2 such
SF
dependency.

1/21/2024 S. Madeh Piryonesi, Project Management 30


Dependencies with Lead and Lag
• Lead pushes the dependent activity to an earlier time: (–)
• Lag delays the dependent activity: (+)
• Assume A and B with durations of 5 and 3 days
19 19

Activity FS – 2 Activity FS + 2
A 20 –2 =18 A 20 +2 = 22

Activity Activity
B B
15 16 17 18 19 15 16 17 18 19

18 19 20
20 21 20 21 22
22 23 24
22
1/21/2024 S. Madeh Piryonesi, Project Management 31

You might also like