ARSP 03 Module 1 v2
ARSP 03 Module 1 v2
• Pre-project phase
• Planning and design phase
• Contractor selection phase
• Project mobilization phase
• Project operations phase
• Project closeout and termination phase
Special Demands on the Project Manager • Just as there are advantages to using a
functional placement, there are also
• Acquiring adequate resources disadvantages:
• Acquiring and Motivating Personnel o A primary disadvantage of this
o The most effective team members have arrangement is that the client is not the
some common characteristics: focus of activity and concern.
▪ High-quality technical skills o The functional division tends to be oriented
▪ Political, and general, sensitivity toward the activities particular to its
▪ Strong problem orientation function.
▪ Strong goal orientation o Occasionally in functionally organized
▪ High self-esteem projects, no individual is given full
o Four development phases of a team: responsibility for the project.
▪ Forming o The same reasons that lead to lack of
▪ Storming coordinated effort tend to make response to
▪ Norming client needs slow and arduous.
▪ Performing o There is a tendency to suboptimize the
project.
Attributes of Effective Project Managers o The motivation of people assigned to the
• Credibility project tends to be weak.
o Technical Credibility o Such an organizational arrangement does
o Administratively Credible not facilitate a holistic approach to the
• Sensitivity project.
• Leadership, Ethics, and Management Style
• Ability to Handle Stress
Construction Administration
• Shop Drawing Review
• Contractor RFI Responses
• Issue Clarifications
• Weekly Site Meetings
• Process Change Orders
• Prepare Punch Lists
• Building Commissioning
• Post Occupancy Reviews
1. PERT/CPM pinpoints the particular work The PERT/CPM diagram should be updated
operations whose completion times are periodically to account for:
responsible for controlling the complete date. 1. Time discrepancies
2. It provides a means of speeding up a project 2. Deliveries
without excessive costs for overtime. Without 3. Weather
the use of PERT/CPM when speeding up the 4. Change orders
project overtime expenditures may be in total 5. Unexpected events or conditions
waste.
3. It gives a time leeway or float available for Updating of the diagram is based on the number of
each of the non-critical work operations. The days the project is out of schedule.
information on float time will give the project
manager that opportunity to maneuver in their Controlling and Monitoring
planning and control of the operations.
4. It establishes time boundaries for operations Flexibility and updated re-computations brought
with possibilities of shifting resources, about by changing conditions is the key to a
equipment and manpower to meet time successful network programming. To keep the
requirements. schedule more up to date and meaningful, the
following output should be done by the contractor.