Electric Motor Check Sheet

This document provides a checklist for motor testing with 18 items to check, including safety procedures, equipment inspection, electrical connections, protection devices, and motor operation tests. The checklist includes spaces to record measurements of current, voltage, temperatures, and vibration over time during motor operation, as well as run-up time, starting current, run-down time, and rotation direction. Sign-off sections are provided for the contractor and commissioning team.

Uploaded by

Rsilvester
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
433 views

Electric Motor Check Sheet

This document provides a checklist for motor testing with 18 items to check, including safety procedures, equipment inspection, electrical connections, protection devices, and motor operation tests. The checklist includes spaces to record measurements of current, voltage, temperatures, and vibration over time during motor operation, as well as run-up time, starting current, run-down time, and rotation direction. Sign-off sections are provided for the contractor and commissioning team.

Uploaded by

Rsilvester
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

MOTOR CHECK LIST Date

Tag Description: Tag Number:

Location: System Number:

No. Description of Check Initial / NA


Ensure that safety barriers and signs are in place before testing begins and that unauthorised personnel
01 are removed from the area.

Ensure that the external surfaces of the equipment are clean and free from damage.
02
Check that the manufacturer's documentation for the engine bay/starter and associated protection and
03 safety devices is complete and available.

Confirm that the fuse/MCB ratings are in accordance with the latest design drawings.
04
Confirm that the engine control / protection, relays are correctly configured and the settings are in
05 accordance with the latest design drawings.

Confirm that the equipment rotates freely.


06
Check and record the insulation resistance of the anti-condensation heater.
07
Measure the winding resistance and record it
08
Confirm point-to-point test of motor feeder.
09
If necessary, continuity test of the winding thermistors.
10
Select test position and check operation of starter control circuits.
11
Ensure that all trip circuits are functioning satisfactorily.
12
Confirm that all remote/local control devices are functioning satisfactorily.
13
Confirm that the anti-condensation heater is functioning satisfactorily.
14
Red Line Markup completed.
15

Start motor and check direction of rotation (record on page 2).


16
Confirm and record ramp-up time and starting current (record on page 2).
17
Stop the motor using the local control station and record the run-down time (record on page 2).
18
Time (mins) 0 5 10 20 30 60 90 120 150 180 210 240 270
Current Amps
Voltage Volts
Ambient Temp Deg C
Bearing Temp (NDE) Deg C
Bearing Temp (DE) Deg C
Motor Frame Temp Deg C
Winding Temp (U) L1 Deg C
Winding Temp (V) L2 Deg C
Winding Temp (W) L3 Deg C
Motor D.E. (X) in./sec
Motor D.E. (Y) in./sec
Motor D.E. (Z) in./sec
Motor N.D.E. (X) in./sec
Motor N.D.E. (Y) in./sec
Motor N.D.E. (Z) in./sec
Run-up time Run-down time

Starting current Rotation viewed from NDE CCW CW

Comment: -

Contractor Commissioning team

Name: Name:

Signature: Signature: