This document provides details on the bar schedule for the reinforcement in the foundation, columns, and tie beams of a G+3 building project. It includes the bar sizes, dimensions, spacing, lengths, weights, and total weights of reinforcement needed for isolated footings (F1-F4), rectangular columns (C1-C2), and tie beams (TB). The total weight of reinforcement required is estimated to be 7461.73kg for foundations, 44145.5kg for columns, and 4419.61kg for tie beams.

Uploaded by

saubhagya majhi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views

BBS

This document provides details on the bar schedule for the reinforcement in the foundation, columns, and tie beams of a G+3 building project. It includes the bar sizes, dimensions, spacing, lengths, weights, and total weights of reinforcement needed for isolated footings (F1-F4), rectangular columns (C1-C2), and tie beams (TB). The total weight of reinforcement required is estimated to be 7461.73kg for foundations, 44145.5kg for columns, and 4419.61kg for tie beams.

Uploaded by

saubhagya majhi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Bar Schedule of G+3 Building

Name of Project:-
Name of Client:-
Name of Consultant:-

Dia.
Lap Total
of bent Weight Total weight
Spac Clear Length (m) length No. length Remarks
Desg. No Shape of bar bar length (kg/m) (kg)
ing cover (m) (m)
(mm
) a b c d e
Isolated Footing
F1

160 160
Main bar 16 150 75 2450 160 160 64 18 2.71 1.58 76.9707
2450 150mmc/c spacing
main and distr. Bar
160 160
Dist. Bar 16 150 75 2450 160 160 64 18 2.71 1.58 76.9707
2450
Total no. of foundation 16 Sub. Total 2463.06 kg
F2

160 160
Main bar 16 150 75 2000 160 160 64 15 2.26 1.58 53.4756
2000
150mmc/c spacing
main and distr. Bar
160 160
Dist. Bar 16 150 75 2000 160 160 64 15 2.26 1.58 53.4756
2000

Total no. of foundation 8 Sub. Total 855.61 kg


F3

160 160
Main bar 16 150 75 2850 160 160 64 20 3.11 1.58 98.1649
2850 150mmc/c spacing
main and distr. Bar
160 160
Dist. Bar 16 150 75 2850 160 160 64 20 3.11 1.58 98.1649
2850
Total no. of foundation 16 Sub. Total 3141.28 kg
F4

120 120
Main bar 12 150 75 2350 120 120 96 27 2.49 0.89 119.7120
150mmc/c spacing
2350
main and distr. Bar
main and distr. Bar
in 2 layers
120 120
Dist. Bar 12 150 75 3850 120 120 96 17 3.99 0.89 120.7076
3850

400
352 352 chair at 1m x 1m in
Chair 10 150 75 400 352 352 300 300 80 10 1.62 0.62 10.0247
300 300 spacing

Total no. of foundation 4 Sub. Total 1001.78 kg


Total 7461.73 kg

C1 Rectangular Column for all from foundation base to top

Corner
25 40 2363 1396 160 9140 100 4188 4 17.15 3.86 264.6142
bar 11503
160
1396

other
than 11503 20 40 2363 1117 160 9140 80 3351 8 16.05 2.47 317.0568
edge 160
1117

Stirrups 10 100 30 1910 1310 1310 240 141 4.29 0.62 373.3889

Total no. of column 32 Sub. Total 30561.92 kg


C2 Rectangular Column for all from foundation base to top
50% reif should be
spliced at every floor
Corner of mid ht.
11503 20 40 2363 1117 160 9140 80 3351 4 16.05 2.47 158.5284
bar
160
1117
50% reif should be
spliced at every floor
other 11503 of mid ht.
than 20 40 2363 1117 160 9140 80 3351 8 16.05 2.47 317.0568
edge 160
1117
Stirrups 10 100 30 1910 1310 1310 240 141 4.29 0.62 373.3889

Total no. of column 16 Sub. Total 13583.59 kg


Total reinf. in column 44145.50 kg

TB Tie Beam
At least 10 splicing
required in entire
16 30 59271 200 200 64 8930 6 68.54 1.58 649.832 length
59271

Grid A-
A, B-B, 16 40 29636 2 29.64 1.58 93.663
C-C, D- 29635.5
D

340 10 125 240 340 240 340 150 80 476 1.23 0.62 361.407

240
Total no. of same length 4 Sub. Total 4419.61 kg
At least 3 splicing
required in entire
12480 16 30 12480 200 200 64 2679 6 15.50 1.58 146.916 length

Grid 1- 16 40 6240 2 6.24 1.58 19.721


1, ..,12- 6240
12

340
10 125 240 340 240 340 150 80 101 1.23 0.62 76.685

240

Total no. of same length 12 Sub. Total 2919.87 kg


PB Plinth Beam
At least 10 splicing
required in entire
59271 16 30 59271 200 200 64 8930 6 68.54 1.58 649.832 length

Grid A-
A, B-B, 16 40 29636 2 29.64 1.58 93.663
C-C, D- 29635.5
D

340
10 125 240 340 240 340 150 80 476 1.23 0.62 361.407

240
Total no. of same length 4 Sub. Total 4419.61 kg
At least 3 splicing
required in entire
12480 16 30 12480 200 200 64 2679 6 15.50 1.58 146.916 length

Grid 1-
16 40 6240 2 6.24 1.58 19.721
1, ..,12- 6240
12

340 10 240 340 240 340 150 80 101 1.23 0.62 76.685
125

240
Total no. of same length 12 Sub. Total 2919.87 kg
MB Main Beam at First and Second Floor
At least 10 splicing
required in entire
59271 16 30 59271 225 225 64 8930 7 68.59 1.58 758.691 length
Grid A-
A, B-B, 16 40 29636 3 29.64 1.58 140.494
29635.5
C-C, D-
D

100/
390 10 240 390 240 390 150 80 556 1.33 0.62 456.469
125

240
Total no. beam of same length in no of floor 2 floor 4 Sub. Total 10845.23 kg
At least 3 splicing
required in span
16 30 12480 225 225 64 2679 7 15.55 1.58 171.955
12480 length

Grid 1- 16 40 6240 3 6.24 1.58 29.582


1, ..,12- 6240
12

100/
390 10 240 390 240 390 150 80 119 1.33 0.62 97.698
125

240
Total no. beam of same length in no of floor 2 floor 12 Sub. Total 7181.62 kg
SB Secondary Beam at First and Second Floor
At least 4 splicing
required in total
12480 16 30 12480 175 175 64 3572 4 16.34 1.58 103.272 length

290
All in a 100/
8 170 290 170 290 150 64 113 1.01 0.40 44.910
floor 150

170

10 250 380 250 380 250 80 12 1.43 0.62 10.593

Total no. beam of same length in no of floor 3 floor 11 Sub. Total 5239.57 kg
MB Main beam at third floor
possible 10 splicing
required in total
59271 16 30 59271 225 225 64 8930 6 68.59 1.58 650.306
length

Grid A- 16 40 29636 1 29.64 1.58 46.831


29635.5
A, B-B,
C-C, D-
D
390
150/
8 240 390 240 390 150 64 529 1.35 0.40 281.297
100
240

Total no. of same length 4 Sub. Total 3913.74 kg


At least 3 splicing
required in span
16 30 12480 175 175 64 2679 6 15.45 1.58 146.441 length
12480

Grid 1- 6240 16 40 6240 1 6.24 1.58 9.861


1, ..,12-
12

100/
390 10 170 290 170 290 150 80 119 0.99 0.62 72.722
125

240
Total no. of same length 12 Sub. Total 2748.29 kg
Total steel in beam = 41859.12 kg
SL Slab reinforcement ofeach floor

8 150 25 59211 75 75 0 0 16 4470 84 63.82 0.40 2117.713


59361
Cutpiece over main
IN X beam
dirn. 8 150 25 2100 75 75 0 0 16 0 996 2.23 0.40 879.038
2100
cutpiece over
8 150 25 2200 75 75 0 0 16 913 2.33 0.40 841.854 secondary beam
2200

8 150 25 12420 75 75 0 0 16 1341 396 13.93 0.40 2178.802


12570

IN Y Cutpiece over main


dirn. 8 150 25 2150 75 75 0 0 16 0 1580 2.28 0.40 1425.667 beam
2150

cutpiece over
8 150 25 2200 75 75 0 0 16 1185 2.33 0.40 1092.658 secondary beam
2200

Sub. Total 8535.73 kg


Total area of slab = 741.00 m2
reinf in 1m2 area = 11.519 kg
`` Deduct area in roof of not having slab = 36.200 m2
Final reinf. required = 8118.7354 kg

Total reinf for all 3 slab = 24356.206 kg


SL Slab reinforcement of 9450mm ht

10 150 25 51125 75 75 0 0 20 5590 84 56.85 0.62 2947.519


51275
IN X Cutpiece over main
dirn. 10 150 25 2150 75 75 0 0 20 0 747 2.28 0.62 1051.333 beam
2150
cutpiece over
10 150 25 2200 75 75 0 0 20 664 2.33 0.62 955.012 secondary beam
2200

10 150 25 21000 75 75 0 0 20 3913 396 25.08 0.62 6131.400


21150

IN Y Cutpiece over main


dirn. 10 150 25 2150 75 75 0 0 20 0 1580 2.28 0.62 2223.704 beam
2150
cutpiece over
10 150 25 2200 75 75 0 0 20 1185 2.33 0.62 1704.352 secondary beam
2200

Sub. Total 15013.32 kg


Total area of slab = 1076.00 m2
reinf in 1m2 area = 13.953 kg
Deduct area in roof of not having slab = 622.500 m2
Final reinf. required = 6327.6399 kg

Total reinf for all 1 slab = 6327.640 kg

Total reinforcement in slab = 30683.85 kg


SR Staircase Reinforcement for 1 flight

4371 16 125 25 1760 2056 555 64 15 4.31 1.58 102.092

16 125 25 1840 928 75 0 0 48 15 2.80 1.58 66.252


2843

1334 10 200 25 704 555 75 0 0 20 9 1.31 0.62 7.300

10 200 25 704 555 75 0 0 40 9 1.29 0.62 7.189


704

750 10 200 25 250 250 125 125 20 9 0.73 0.62 24.333

10 150 25 1720 0 0 0 0 40 57 1.68 0.62 118.222


1720

Total number of Flight = 3 Sub. Total 325.39 kg


Total reinf. For 3 staircase = 2928.49 kg