Practice Question MRP - Solution
Practice Question MRP - Solution
B(3) C(2)
Master Week 1 2 3 4 5 6 7
Schedule for:
Quantity 95
E
E LT=2 Beg.
1 2 3 4 5 6 7
Lot size: Lot-for-Lot Inv.
Gross requirements 95
Scheduled receipts
Projected on hand 5 5 5 5 5 5 5 0
Net requirements 90
Planned-order receipts 90
Planned-order releases 90