Method Statement For Concrete Work
Method Statement For Concrete Work
DISCIPLINE: CIVIL
Contents
1. Purpose
2.Scope
3. References
4.Definitions
5. Responsibilities
6.Resources
7. Safety
8.Procedure
9. Attachments
The purpose of this Method Statement is to describe the quality control procedure to be
Followed during the Concrete works at the mentioned project.
2- SCOPE:
The scope of this Method Statement is to define all the procedures and inspections to be
Followed during site Concrete work activities at Construction & Phase 1 Operation of Green
Riyadh Nursery Project, in compliance with the project specifications and standards
procedures.
3- REFERENCES:
4- DEFINITIONS:
MAG and ADVACON :Al Majal Al Arabi Group and advanced Concept of contracting
ITP : Inspection & Test Plan
PPE : Personal Protective equipment
QA/QC : Quality Assurance/Quality Control
ASTM : American Society for testing and materials
HSE : Health, Safety and Environment
RCRC : Royal commissioning for Riyadh city.
5- RESPONSIBILITIES
Ensures that the content of this method statement is understood and implemented
at all times.
Coordinate with the site engineer to ensure that the necessary resources to
Implement the approved Method Statement have been allocated to the task.
Determine all the requirements needed in order to comply with safety standards and
Regulations as require.
The progressing works are carried out according to the planned program and all the
equipment’s required to execute the works are available as per the project planning
and are in good condition
Co-ordinate with the Consultant, Project Manager, Site Engineer, Safety Engineer, and
sub-contractor for the safe and proper execution of the work.
5.2 QA/QC Engineer.
Will ensure that the site preparation activities are conducted according to the
approved Method Statement and project contract documents.
Shall be responsible of the implementation of this procedure.
Will ensure that the materials being delivered and used are in accordance with the
project specifications and approved material submittal.
Shall be responsible for the inspection, preparation of all documents and compiling
them for the inclusion in the final documentation packaged.
The HSE manager is responsible for reviewing this procedure to ensure that systems of
work is in place/considered in each phase of activities.
He also has the overall responsibility of ensuring, through the safety
supervisors/officers that the works in the field are are performed safely and in
compliance with all applicable quality standards stipulations and procedures of Royal
Commissioning of Riyadh City.
The HSE manager reports and coordinates all HSE matters with Royal Commissioning of
Riyadh city HSE team along with the functional responsibility to the project manager.
Ensure proper welfare arrangements for all manpower and staff
Will ensure that all the activities related to the specified task are being followed
Safely and all workers are wearing PPE.
Identify and take measure control the risks associated with the hazard.
Ensure that the site is maintained clean and tidy.
Inspect all the site activities and train the persons to prevent accidents and its proper
reporting to the project manager and the client.
Ensure all required documents (PTW, approved MSRA, checklists, 3rd party certificates,
etc.) are available and up to date.
Ensure all staff and workforce involve in the job are aware about the emergency plan
Shall coordinate directly with the project/site engineer in regards to advisement of
safety issues and problems.
Report any violations to HSE manager in order to take corrective action.
Ensure that the site is maintained clean and tidy
It will be ensured at all time that concrete activities shall be carried out under the
Control of competent works supervisor. Assigned supervisor shall have extensive
experience concrete works undertaken
Shall explain the Method Statement for his subordinates and responsible for
Executing the works in accordance with the method statement.
To ascertain that the work is being carried out as per the instructions of site
engineer and in conformance with the approved drawings & specs.
Also to instruct workers to eliminate hazards and encourage safety actions or
Initiatives.
Ensure all materials/ equipment’s to be used is available prior to start of work
Co-ordinate with the QC engineer for the tests to be carried out and initiate for the
inspection for the finished works.
Ensure that the site is maintained clean safe and tidy
Carrying out the work and the proper distribution of all the available resources in
coordination with the site engineer on a daily basis.
Daily reports of the works achieved and coordinate for the future planning with the Site
engineer.
Incorporate all the QC and HSE requirements as requested by the concerned Engineer.
Met with any type of unforeseen incidents or requirements and reporting to the site
engineer immediately.
Reports directly to site engineer.
Social Distancing:
Social distancing means consciously increasing the physical space between yourself and
Others.
These are measures you take to limit the spread of COVID - 19.
1. Keep at least 1 to 2 meters
2. Stay away from a sick person
3. Call MOH online services
4. Stay at home when u sick
6- RESOURCES:
6.1 Materials and their approval
Form work:
Factory fabricated, adjustable length, removable or snap-off metal form ties.
For water holding structures use special types recommended by manufacturer.
Formwork Release Agents: Oil emulsion or any other type approved by the
Engineer.
Reinforcement:
The grade of the reinforcement steel shall consist of FY 415 Mpa Conform to SSA
2, ASTM A 615 or ASTM A 706
Steel Wire: Conform to ASTM A 82 plain, cold-drawn, steel (fy = 465 MPa)
Vapor Barrier
High density polyethylene sheet, conforming to ASTM E 154, 200 microns thick
Water proofing
As approved by RCRC
6.4 Equipment
The following equipment will be used for Concreting
1) Compressor
2) Concrete boom placer
3) Survey Instrument (Total station, auto level, measuring tape and other accessories).
4) Safety Accessories for barricading the working area.
5) Concrete Vibrator
6) Concrete pump
7) Meter tape, pegs, nylon cord, and warning tape.
8) Hand tools.
6.5 Human Resource
1) Project Engineer
2) Site Engineer
3) Foreman.
4) Charge hands
5) Land Surveyors
6) Mechanic
7) Electrician
8) Skilled labors
9) Unskilled labors
10) Vehicles & Machine Operators
7- SAFETY PRECAUTIONS:
1) Task specific safety briefing / tool box talk has been conducted by HSE dept. prior
to start of work activity.
2) Safety officer and direct supervisor will ensure that PPE are worn by site personnel
at all times during this activity.
3) Safety officer shall ensure that all workers and workplaces are safe by continuous
monitoring and providing safety instructions.
4) All personnel must adhere to the safety rules and regulations at the site.
5) Hazard identification and control measures has been implemented.
6) Only approved scaffolds should be used
7) Proper housekeeping is done on a daily basis.
8) Safety warning signs, lights and notices shall be displayed as needed on site
locations.
9) Excavations / Permits shall comply as per HSE plan.
10) All survey pegs on site shall be capped to provide appropriate safety.
11) It will be ensured that the equipment used at site shall be maintained and relevant
certification (including operator training certification and / or licenses) shall be
Submitted.
12) All survey pegs on site shall be capped to provide appropriate safety.
13) Housekeeping shall be given prime importance and carried out on a regular basis.
Prevention of entry by personnel into restricted areas, and a high regard for the
environment and natural resources shall be adhered to at all times
8.1 General
1) Approved civil and structural shop drawings for Concrete works shall be available
at site and shall be used.
2) All required HSE and environmental requirements are in place.
8.3Execution
8.3.1 Blinding
8.3.2 Formwork
1) Design, construct, support and maintain formwork system to safely support and
carry the vertical and the lateral loads applied and until such loads can be
supported by concrete structure.
2) Construct forms to sizes, shapes, lines and dimensions shown on drawings to
obtain accurate alignment, location, grades, level and plumbness. Set and built
into work anchorage devices and other embedded items as required.
3) Coat form contact surfaces with form-coating compound before reinforcement
is placed as per the manufacturer's instructions.
4) Layout shall be check by surveyor to determine the exact location of RCC members.
5) Materials used shall have no surface defects and shall be resistant to the action of
cement and water. Forms shall be rigidly constructed and it should be water tight.
6) Forms shall be properly braced or tied together so as to maintain position and shape
during and after placing of concrete.
7) All exposed edges of concrete shall be formed with 25mm chamfer unless special
finishes are specified.
8) Before concreting is commenced, the forms shall be thoroughly cleaned and freed
from all sawdust, tie wire, shavings, dust, dirt and other debris.
9) Removal of Forms: Remove non-supporting formwork as that on the side parts,
24 hours after casting concrete. Formwork supporting weight of concrete shall
not be removed until concrete has attained its designed 28-day compressive
strength which shall be determined by testing of field-cured specimens, but not
before 14 days starting from date of casting. Comply with the requirements of
ACI Codes regarding removal of formwork.
1) Review the cutting list and bar bending schedule before cutting and bending of
rebar.
2) Main bars, ties and spirals shall have a minimum specified yield strength according
to design requirements conforming to the approved drawings and specification.
3) Steel will be cut and bent using suitable cutting & bending machine respectively
according to design requirements conforming to the approved drawings and
specification.
4) Fix the steel according to requirement at site considering the overlap length at
construction joints as indicated on the drawings. The lap joints shall be staggered.
5) Steel reinforcement shall be placed with concrete spacers on the bottom and sides
of the formwork to maintain the required concrete covering as specified in the IFC
drawings.
6) Spacing and sizes of ties, plumbs, lines and levels, rust and oil contamination shall
be checked prior to placement of concrete.
7) All the fabrication shall be as per the approved drawing and specification.
8) Reinforcing steel bars are securely tied together at intersections by ties in formwork
and held in position by spacers, chairs or other supports to prevent displacement
when placing of wet concrete.
9) The spacers are having the same grade of concrete poured.
10) Supports for reinforcing steel bars are sufficient in number and should have enough
strength to the reinforcement they support.
11) Walking on reinforcement by workers shall be avoided to prevent contamination
and displacement of the bars before placement of the concrete.
12) Any reinforcement steel bars left protruding from the concrete shall be protected
from dust and condensation by enclosing in polyethylene or by other suitable means
13) Any rusting which occurs on exposed bars before concreting shall be removed.
14) Complete rebar bending schedules and materials lists shall be shown on the
engineering drawings.
15) Reinforcement shall be supported on concrete blocks of a size to give the correct
cover to the reinforcement. Position, support and secure reinforcement against
displacement by formwork construction, or concrete placement operations. Locate
and support reinforcing by chairs, runners, bolsters, spacers and hangers, as
required.
16) Place reinforcement to obtain the minimum coverage for concrete protection.
17) Arrange, space and securely tie bars with 1.6 mm annealed wire to hold
reinforcement accurately in position during concrete placement operations.
18) Check reinforcement after fixing and before submitting to the Engineer for
approval. Allow time for the Engineer's inspection.
8.3.4 Mixing of Concrete
1) Concrete shall be ready-mixed, supplied by one single producer approved by the
Engineer. Supplier shall submit a written assurance that concrete complies with
specifications including control of temperature. For mixing of concrete follow the
requirements of ACI standard 305 (Recommended Practice for Hot Weather
Concreting) as well as ASTM C 94. Do not allow additional water to be added, unless
approved by the Engineer; reduce mixing and delivery time to 60 minutes.
Maintain the concrete temperature during mixing and placing at 30°C or below.
1) Prior to any work of this section, inspect thoroughly the installation of other trades
as formwork, reinforcements, embedded items, conduits and pipes to verify that
concrete may be placed to lines and elevations indicated on the Drawings as well
as spacing and clearance from reinforcing bars. Make sure that areas are cleaned
and ready for casting concrete. Notify Engineer at least 48 hours before placing.
Do not proceed with concrete casting until written approval for pouring had been
issued by Engineer.
Concrete Surface Repairs: Repair and patch defective areas with cementitious or
resin based repair systems recommended by repair material manufacturer. Strictly
follow manufacturer's instructions for proper application of materials.
1) All below ground membranes and coatings shall be protected from damage due to
construction activities and backfilling by install of 12mm thick protection board
including necessary appurtenances to complete the work. Protection board shall at
least equivalent or as per approved protection board. After the bitumen coating is
checked and approved, cut protection board to size and prepare covering, apply
adhesive as specified.
2) All membrane/coatings shall be applied after curing is completed.
Double layer Bituminous damp proofing paint, includes all preparation works,
protection layer completes all in accordance with the drawings and specifications.
9 ATTACHMENTS:
HERA
ITP
WIR with CHECK LIST
CONRETE FORMS
Contractor Signature:
Discipline Engineer: QA/ QC HSE MEP Project Manager:
MAG
The Engineer:
A- Approved B- Approved with Comments C- Revise and Resubmit
D- Rejected
Comments:
Distribution:
Client Engineer Contractor