WWTP - Schedule 5 - Influent Quantity and Quality Parameters (July 2022)
WWTP - Schedule 5 - Influent Quantity and Quality Parameters (July 2022)
RFP Documents
Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Table of Contents
Disclaimer ...........................................................................................................................1
Defined Terms.................................................................................................................... 2
1. Introduction ........................................................................................................... 3
2. Shared Facilities ..................................................................................................... 4
Screen Shaft......................................................................................................................................... 4
Pump Shaft .......................................................................................................................................... 4
Odour Influent Parameters ................................................................................................................ 5
TSE Pump Station ............................................................................................................................... 6
3. STW Facilities ......................................................................................................... 7
Influent Flow Quantity to STW Facilities .......................................................................................... 7
Influent Quality Parameters ............................................................................................................... 7
3.2.1 Combined Sewage Quality Parameters ................................................................................... 7
Polluted Influent ............................................................................................................................... 10
Odour Influent Parameters – STW Facilities ...................................................................................11
Page/Content/i Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Disclaimer
All information contained in this RFP, including inter alia financial, geographical, commercial, legal and
technical information, has been included for illustrative and indicative purposes only to assist companies
and consortia in making their own evaluation of the Project. Each Respondent shall be solely responsible
for satisfying itself as to the information required to submit the bid for the Project.
Respondents should make their own investigations, projections, conclusions and consult their own
advisors to independently verify the information contained in this RFP and to obtain any additional
information they might require prior to submitting the Bid.
Whilst the information contained in this RFP has been prepared in good faith, it does not purport to be
comprehensive and it does not purport to have been independently verified. Neither Ashghal nor their
respective employees, agents or advisors make any representation or warranty, express or implied, with
respect to the veracity, adequacy, accuracy, reasonableness or completeness of the information contained
in this RFP or with respect to the information on which it is based or in respect to any written or oral
information or representation given or made, or to be given or made, by Ashghal or any of its advisors to
any company or Consortium or to its or their professional advisors, whether given or made prior to or after
the issue of this RFP (collectively, the “Information”).
Ashghal, its employees, agents and its advisors hereby expressly disclaim any and all liability arising out of
or in relation to the Information (including in relation to omissions therefrom) and in respect of the use of
and/or reliance on such Information by companies or consortia and/or its or their advisors.
This RFP does not purport to commit or bind Ashghal in any manner whatsoever to proceed to the RFP
stage or to the awarding of a contract. Ashghal reserves its absolute, complete and unfettered right to, at
any time and for any reason whatsoever, disregard all Bids and to terminate at will the competitive selection
process and may, at its discretion, proceed with the Project in some other manner, with no liability to any
party whatsoever.
Each Respondent is solely responsible for all costs it incurs in the preparation of its Bid, including without
limitation all costs of providing information requested by Ashghal, attending meetings and conducting any
due diligence. Under no circumstances will Ashghal or any of its advisors be liable for any costs or expenses
borne by the Respondent or any of its advisors in this process, nor shall they be liable for any damages or
consequential damages whatsoever, which may arise out of the process.
Ashghal reserves the right, in its absolute discretion, with no liability whatsoever to:
a. amend the scope of the Project, modify, cancel or suspend the RFP process or any or all stages of the
procurement process, at any time for any reason;
b. waive a defect or irregularity in the form or content of any RFP;
c. re-advertise for new responses, call for tenders, or enter into negotiations for this Project or for work
of a similar nature;
d. make any changes to the terms of business opportunity described in this RFP; and
e. extend, from time to time, any date, time period or deadline provided in this RFP.
All Bids submitted to Ashghal shall become the property of Ashghal immediately upon such submission.
Page 1 Rev 0
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Defined Terms
Capitalized terms used in this Schedule have the respective meanings set forth in Agreement or as defined
in the Schedule 5 (Influent Quantity and Quality Parameters).
Page 2 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
1. Introduction
This Schedule 5 (Influent Quantity and Quality Requirements) stipulats the quantity and quality of various
inputs to the Project Assets.
Page 3 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
2. Shared Facilities
Screen Shaft
The following Table 1 provides general technical range for depicted sewage flows expected to be delivered
from MTS to Screen Shaft.
Hydraulic design of the Screen Shaft shall be based on different flow conditions (Minimum Daily Flow,
Average Daily Flow and Peak Daily Flow to Screen Shaft) in accordance with Screen Shaft design flows
tabulated in Table 1, Schedule 5 Influent Quantity and Quality Requirements.
The Project Company shall make the Screen Shaft available all the time to deal with the Screen Shaft design
flows specified in the Table 1, Schedule 5 Influent Quantity and Quality Requirements.
On any given Day if the Peak Daily Flows (as defined above) to the Screen Shaft from the MTS as measured
by the Metering and Monitoring System exceeds the Peak Daily Flow value specified for the Project flows,
Table 1, Schedule 5 (Influent Quantity and Quality Parameters), then it shall be treated as Peak Influent
Event – Screen Shaft as stipulated in the Agreement.
However, when the Expansion Phases have been executed and are operational, the Peak Influent Event –
Screen Shaft for the Screen Shaft shall be adjusted by the Project Company and Ashghal based on the
combined installed peak capacities of the Pump Shaft and the Future Pump Shafts.
Peak Daily Flow to Screen Shaft = Installed Peak Capacity of the Pump Shaft + Peak Daily Flow capacity of
installed Future Pump Shafts
Pump Shaft
The following Table 2 provides general technical range for depicted sewage flows expected to be delivered
from the Screen Shaft to the Pump Shaft.
Table 2: Expected Influent Sewage Flows from Screen Shaft to Pump Shaft
Page 4 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Hydraulic design of the Pump Shaft shall be based on Minimum Daily Flow, Average Daily Flow and Peak
Daily Flow from Screen Shaft to Pump Shaft in accordance with design flows tabulated in Table 2, Schedule
5 Influent Quantity and Quality Requirements.
On any given Day if the Peak Daily Flow (as defined above) to the Pump Shaft as measured by the Metering
and Monitoring System exceeds the value specified in Table 2, Schedule 5 ( Influent Quantity and Quality
Parameters), then it shall be treated as Peak Influent Event as stipulated in the Agreement.
The following Table 3 provides general indicative technical range for depicted odour Influent parameters
expected to be delivered from the MTS to the Screen Shaft.
The design of OCF at the TPS shall be based on the H2S concentrations, odour units indicated in table 3
above and verified by Project Company’s odour modelling in compliance with requirements specified in
clause 6.2, Part 2 Project Specific Requirements, Schedule 2: Design and Construction Requirements and
other requirements stipulated elsewhere in the Agreement. The Project Company has the flexibility to
develop the OCF at the TPS in phase wise manner at its own discretion.
On any given Day if the peak odour Influent parameters (as defined above) exceeds the specified values in
Table 3, Schedule 5 (Influent Quantity and Quality Parameters), then it shall be treated as Influent Excuse
Event - Odour as stipulated in the Agreement.
However, when the maximum odorous air flow rate to the Screen Shaft and the Peak Influent Event –
Screen Shaft for the Screen Shaft shall be adjusted by the Project Company and Ashghal based on the flows
to the Screen Shaft and the status of Expansion Phases being operational.
Page 5 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Table 4: Expected TSE Flows to TSE Pumping Station from Project and Expansion Phases
Year Unit Average Peak
On any given Day if the peak TSE flows (as defined above) from the Project and the Expansion Phases as
measured by Metering and Monitoring System exceeds the values specified in Table 4, Schedule 5 (Influent
Quantity and Quality Parameters), then it shall be treated as Peak Influent Event as stipulated in the
Agreement.
The quantity of TSE to be discharged to the TSE Delivery Points shall be as per the TSE Dispatch
Requirements specified in Schedule 4 (Service Requirements). The TSE quality discharged to the TSE
Delivery Points shall be monitored by the Metering and Monitoring System.
The Project Company shall monitor the TSE quality and quantity delivered from the Expansion Phases to
the TSE Pump Station at the delivery point against the requirements agreed with Ashghal.
If the Project Company is unable to dispatch the agreed quantities of TSE through the TSE Network due to
lack of demand or for reasons which are not in control of the Project Company, it shall be treated as TSE
Output Excuse Event.
Page 6 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
3. STW Facilities
On any given Day if the Peak Daily Flow (as defined above) to the STW Facilities from the Pump Shaft and
the Tanker Reception Facility as measured by the Metering and Monitoring System exceeds the value
specified in Table 5, Schedule 5 (Influent Quantity and Quality Parameters), then it shall be treated as Peak
Influent Event as stipulated in the Agreement.
During the case of Peak Influent Event the Project Company may reject the flows from tankers as stipulated
in section 3.1, Part 2 - Project Specific Requirements, Schedule 2 Design and Construction Requirements.
Page 7 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Page 8 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Sodium
Minimum Daily Concentration mg/l 118
Daily Average Concentration mg/l 151
90th Percentile Concentration mg/l 176
Maximum Concentration mg/l 194
Chlorides
Minimum Daily Concentration mg/l 184
Daily Average Concentration mg/l 296
90th Percentile Concentration mg/l 363
Maximum Concentration mg/l 461
Table 9: Combined Influent Quality Parameters – Minimum, Maximum and Off Specification Influent
Parameters
Parameter Unit Minimum Maximum Off Specification
Col 1 Col 2 Col 3 Col 4 Col 5
BOD5 mg/l 100 298 <100 or > 298
COD mg/l 319 818 <319 or > 818
TSS mg/l 100 450 <100 or > 400
VSS mg/l 82 368 No off spec
TKN mg/l 25 61 <25 or > 61
Ammonia (as N) mg/l 17 53 > 45
Total mg/l 3 9 > 20
Phosphorous
Alkalinity (as mg/l 175 500 No off spec
CaCO3)
Hardness (as mg/l 380 760 No off spec
CaCO3)
Hydrogen mg/l 0.4 11 No off spec
Sulphide (as
H2S)
Page 9 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
On any given Day if the Influent sewage quality as measured by the Metering and Monitoring System is not
within the range specified in Table 6, Table 7, Table 8 and as summarized in column 5, Table 9, Schedule 5
(Influent Quantity and Quality Parameters), then it shall be treated as Off Specification Influent Event as
stipulated in Agreement.
Polluted Influent
Polluted Influent occurs when extremely high levels of pollutants that are potentially detrimental to the
processes and/or equipment within the Project Assets are detected via an online monitoring system and can
be validated through test results from spot and/or composite sampling during any Day or pro rata period of
a Day, measured hourly.
The following Table 10 provide the maximum combined sewage quality parameters that defines a Polluted
Influent.
Table 10: Combined Influent Quality Parameters defining Polluted Influent Event
Parameter Unit Maximum
Col 1 Col 2 Col 3
Total suspended solids (TSS) mg/l > 1500 mg/l
pH mg/l < 3 pH units
BOD mg/l > 750 mg/l
Chemical Oxygen Demand mg/l > 1500 mg/l
Oil and Grease mg/l > 300 mg/l
Phenols mg/l > 50 mg/l
Herbicides & Pesticides mg/l > 100 mg/l
On any given Day if the Influent sewage quality is in excess of the parameters specified in, Table 10, Schedule
5 (Influent Quantity and Quality Parameters), then it shall be treated as Polluted Influent as stipulated in
the Agreement.
The Project Company shall take all reasonable steps to treat Polluted Influent to the best quality possible.
Should significant damage to the process occur, which could not have been reasonably prevented, the Project
Company shall submit a process recovery plan and associated costs to Ashghal for assessment. The Project
Company shall receive Supplemental Payments for such costs as stipulated in Schedule 11 (Payment
Mechanism).
Page 10 Rev 01
RFP Volume II - Al Wakra & Al Wukair Sewage Treatment Plant
Page 11 Rev 01