Presentation 06 (1slide-Pg)
Presentation 06 (1slide-Pg)
Motivations:
Replacement,
Expansion,
Cost reduction,
Safety and environmental aspects.
= × 100%
∑! " …
= × 100% input data: Net Profit
( )
∑ … −
input data: Cash Flow
= × 100%
PAYBACK PERIOD
Period CF Accumulated PV
1 15,000 15,000
2 17,500 32,500
3 17,500 50,000
4 16,000 66,000
DPB - CALCULATION
A project requires initial investment of € 50,000,
the net cash flows (cash inflows – cash outflows) during the following four
years are expected to be:
year Net cash flows
Interest rate: 10 % 1 15,000
@ 2 17,500
56789:;< =>8<9? =
(@ + A. @); 3 17,500
n = period 4 16,000
!"B = C Advantages:
1+ considers the time value of money
E
considers risk
For any project to be acceptable, considers all cash flows of the
the NPV must be positive. investment opportunity
objective decision criteria
Where there are competing projects
with positive NPVs, the one that Disadvantages:
gives the highest positive NPV requires specifying a cost of capital
should be accepted.
13
ECONOMICS FOR MANAGERS, 2023/24
ARR PB DPB NPV PI IRR MIRR
PROFITABILITY INDEX
PROFITABILITY INDEX
Initial investment: € 50,000
Expected cash flows for the first four years: year Net cash flows
1 15,000
Interest rate: 10 %
@ 2 17,500
56789:;< =>8<9? =
(@ + A. @); 3 17,500
n = period 4 16,000
52,175
" = = 1.04
ECONOMICS FOR MANAGERS, 2023/24
50,000 16
CAPITAL RATIONING
Capital rationing is a situation in which there is a limit on the capital
budget.
Capital rationing requires looking at all possible combinations of
projects to find the combination that maximizes owners’ wealth.
Capital rationing may result in rejecting profitable projects.
The finance manager at XYZ Co. has to determine which projects should the
company undertake when the capital budget is limited to €1,000,000
Project Initial Investment Present Value Profitability Index
A 400,000 500,000 1.125
B 1,100,000 1,430,000 1.300
C 450,000 486,000 1.080
D 600,000 564,000 0.940
ECONOMICS FOR MANAGERS, 2023/24 17
ARR PB DPB NPV PI IRR MIRR
C =0
(1 + )
E
Investment: € 50,000
Expected cash flows for the first four years: year Net cash flows
1 15,000
If p = 10 %, the NPV is positive. 2 17,500
3 17,500
Therefore, the IRR > 10 %.
4 16,000
= + ×( J − )
+ I
2175
= 10% + × (20% − 10%) = 11.97
2175 + −7504
p1=% by positive NPV (10 %)
p2=% by negative NPV (20 %)
A = positive NPV (by % p1)
B = negative NPV (by % p2)
ECONOMICS FOR MANAGERS, 2023/24 20
ARR PB DPB NPV PI IRR MIRR
Investment: € 50,000
Expected cash flows for the first four years: year Net cash flows
1 15,000
Interest rate: 11.97% 2 17,500
@ 3 17,500
56789:;< L>8<9? =
(@ + A. @@MN); 4 16,000
The Modified Internal Rate of Return (MIRR) is the effective yield on the
project if intermediate cash flows are reinvested at a specified rate (usually the
project's cost of capital).
MIRR reflects the cost and profitability of a project more accurately.
Solving requires two steps:
Step 1: Calculate the terminal (future value)
P B
Step 2: Solve for the rate: if FV = PV(1+MIRR)n, then: O = −1
"B
Advantages:
considers the time value of money
considers risk
considers all cash flows
objective decision criteria
Disadvantages:
difficult to interpret
requires specifying the reinvestment rate
ECONOMICS FOR MANAGERS, 2023/24
22
ARR PB DPB NPV PI IRR MIRR
Q 66,000
If FV = PV(1+MIRR)n, then: O = − 1 = 0.0719
50,000
Q 71,033
If FV = PV(1+i)n, then: O = − 1 = 0.0917
50,000
Q 78,592
If FV = PV(1+i)n, then: O = − 1 = 0.1197
50,000
Investment Profile
Discount Discounted NPV
20000
(%) inflows
15000
0 66,000 16,000
5 58,439 8,439 10000
15 46,931 -3,069 0
0% 5% 10% 15% 20%
20 42,496 -7,504 -5000
-10000
ECONOMICS FOR MANAGERS, 2023/24
26
DETERMINING THE CROSS-OVER RATE FOR
MUTUALLY EXCLUSIVE PROJECTS
Cross-over rate is discount rate at which the net present values of two
projects are equal; the internal rate of return of the differences in the
cash flows of two projects.
Step 1: Calculate the difference in the projects’ cash flows for each
period.
Step 2: Calculate the IRR of the differences. This is the cross-over rate.
Period CF A CF B
0 -1,500 -1,000
Determining the cross-
1 +450 +500
over rate for mutually
exclusive projects 2 +550 +400
(project A and B) 3 +650 +350
4 +650 +200
Cost of capital: 15%
NPV 106.2 81.7
ECONOMICS FOR MANAGERS, 2023/24
IRR 18.2 % 19.6 27
%
DETERMINING THE CROSS-OVER RATE FOR
MUTUALLY EXCLUSIVE PROJECTS
(PROJECTS A AND B)
Period CF A CF B Difference
0 -1,500 -1,000 -500
1 +450 +500 -50
2 +550 +400 +150
3 +650 +350 +300
4 +650 +200 +450
The IRR of the differences is 16.6 %
A project requires an initial investment of € 50,000, the cash flows during the
following four years are expected to be:
∑ "B S F TU 205,818
I = = = 0.9894
∑ "B F TF 50,000 + 156,348
ECONOMICS FOR MANAGERS, 2023/24 32