Production Order in SAP
Production Order in SAP
time and how much quantity is required. It also defines which components and sequence of
operations are to be used and how the order costs are to be settled.
Planned orders are results of running MRP. Shortages of materials that are set to internal
procurement will create planned orders, which can be converted into production orders.
Production orders are "hard copies"; they cannot be adjusted by an MRP run anymore.
BOM and routing data of the materials are copied into the production order which
determines the list of components and operational data in the order.
Planned Costs also gets updated in the production order via component price and routing
activity price.
You can run an availability check on production orders which determines any missing
components in the order so that you can bring that missing component for the order
execution at shop floor.
You can print the production order for shop floor which indicates the list of components to
be consumed and what kind of operations to be performed in sequence at the work center.
After you have physically produced the material, you can declare the production through
order confirmation which updates the activities cost such as machine running price, labor
price on the order.
You can also post goods receipt of the material automatically during order confirmation.
Goods receipt would increase the inventory of the material, and it is carried out with
movement type 101 in SAP.
After Order Confirmation, all the cost such as the cost of components and activity cost will
be debited on the order, and once you post goods receipt, costs will be credited on the order.
Once, production order is fully confirmed and delivered, or business has decided not to
execute that order, then it needs to be technically closed which means order will no longer
be considered in MRP run and will be deleted from stock/requirement list. Order reservation
on components will also be deleted.