2M Look Ahead - Summary

The document provides an overview of the Rua Al Madinah Main Infrastructure Package project including activity names, durations, budgets, milestones, and progress. It includes details on site offices, vehicles, accommodations, general items, subcontractors, traffic management, five tunnel constructions, MEP rooms, utilities, and corridors with completion dates ranging from December 2023 to May 2025.

Uploaded by

Erickson Malicsi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
28 views1 page

2M Look Ahead - Summary

The document provides an overview of the Rua Al Madinah Main Infrastructure Package project including activity names, durations, budgets, milestones, and progress. It includes details on site offices, vehicles, accommodations, general items, subcontractors, traffic management, five tunnel constructions, MEP rooms, utilities, and corridors with completion dates ranging from December 2023 to May 2025.

Uploaded by

Erickson Malicsi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

RUA AL MADINAH MAIN INFRASTRUCTURE PACKAGE

Two Months Look Ahead


Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Budgeted Total Planned Value Earned Value Schedule % Performance % Qtr 4, 2023 Qtr 1, 2024
Duration Cost Cost Cost Complete Complete
Nov Dec Jan Feb
RUA AL MADINAH MAIN INFRASTRUCTURE PACKAGE REV03- UPDATE AS OF 02-11-2023 1232 01-Jun-22 15-Jun-26 31-May-22 A 07-Dec-25 564,060,969.57 500,598,658.38 207,047,880.87 88.75% 36.71%

MILESTONES 0 07-Dec-23 07-Dec-23 07-Dec-23 07-Dec-23 0.00 0.00 0.00 0% 0% 07-Dec-23, MILESTONES
INTERMEDIATE MILESTONE 0 07-Dec-23 07-Dec-23 07-Dec-23 07-Dec-23 0.00 0.00 0.00 0% 0% 07-Dec-23,
Complete Approved
INTERMEDIATE
Subcontractor
MILESTONE
and Vendor
MOBILIZATION & GENERAL ARRANGEMENT 1232 01-Jun-22 15-Jun-26 31-May-22 A 07-Dec-25 95,341,544.10 49,875,201.51 55,031,259.39 52.31% 57.72%
SITE OFFICES FOR CLIENT/CONSULTANT/CONTRACTOR 1125 08-Oct-22 15-Jun-26 01-Dec-22 A 09-Oct-25 3,264,800.00 1,123,039.78 966,707.28 34.4% 29.61%
CLIENT/CONSULTANT VEHICLES 1060 01-Jun-22 18-Nov-25 31-May-22 A 09-Oct-25 2,136,000.00 878,581.13 1,860,456.00 41.13% 87.1%
JV ACCOMMODATION & BUILDING 945 08-Oct-22 09-Nov-25 01-Aug-22 A 19-May-25 17,062,500.00 5,940,277.78 12,534,112.50 34.81% 73.46%
OTHER GENERAL ITEMS 981 23-Jul-22 05-Oct-25 01-Aug-22 A 07-Dec-25 47,526,963.90 26,319,022.62 24,396,261.43 55.38% 51.33%
CONTRACTOR'S DELIVERABLES 35 31-Aug-22 10-Oct-22 26-Jun-22 A 08-Nov-23 720,000.00 720,000.00 648,000.00 100% 90% 08-Nov-23, CONTRACTOR'S DELIVERABLES
TRAFFIC MANAGMENT 900 08-Oct-22 16-Sep-25 01-Dec-22 A 06-Oct-25 14,980,000.00 5,243,000.00 5,939,570.00 35% 39.65%
TRAFFIC DIVERSION PLAN 57 14-Mar-23 22-May-23 19-Jan-23 A 06-Nov-23 9,651,280.20 9,651,280.20 8,686,152.18 100% 90% 06-Nov-23, TRAFFIC DIVERSION PLAN
GENERAL ENGINEERING 125 31-Aug-23 25-Jan-24 31-Jul-23 A 25-Jan-24 0.00 0.00 0.00 0% 0% 25-Jan-24, GENERAL EN
PROCUREMENT OF SUBCONTRACTORS/VENDERS 30 31-Aug-23 05-Oct-23 31-Jul-23 A 07-Dec-23 0.00 0.00 0.00 0% 0% 07-Dec-23, PROCUREMENT OF SUBCONT
MATERIAL SUBMITTAL 63 04-Nov-23 15-Jan-24 04-Nov-23 15-Jan-24 0.00 0.00 0.00 0% 0% 15-Jan-24, MATERIAL SUBM
QUALITY ENGINEERING 20 02-Jan-24 25-Jan-24 02-Jan-24 25-Jan-24 0.00 0.00 0.00 0% 0% 25-Jan-24, QUALITY EN
TUNNEL CONSTRUCTION 863 05-Jul-22 01-May-25 02-Aug-22 A 19-May-25 422,750,637.85 404,754,669.25 150,908,605.05 95.74% 35.7%
JADAT AL HARAM TUNNEL 767 13-Aug-22 09-Feb-25 02-Aug-22 A 11-Dec-24 264,927,514.24 254,586,598.12 100,043,007.44 96.1% 37.76%
AIRPORT ROAD TUNNEL 611 02-May-23 01-May-25 26-Oct-22 A 19-May-25 6,419,282.19 678,099.70 1,593,576.18 10.56% 24.82%
KAAR TUNNEL (KING ABDULAZIZ ROAD TUNNEL EAST) 832 05-Jul-22 22-Mar-25 03-Oct-22 A 22-Mar-25 56,055,769.21 55,606,419.60 14,413,543.33 99.2% 25.71%
KAAR TUNNEL (KING ABDULAZIZ ROAD TUNNEL WEST) 533 24-Nov-22 24-Aug-24 03-Oct-22 A 24-Aug-24 40,826,509.84 40,826,509.84 15,190,000.89 100% 37.21%
TUNNEL 2 568 09-Aug-22 12-Jun-24 17-Oct-22 A 06-Jun-24 29,323,345.64 29,323,345.64 6,158,499.19 100% 21%
TUNNEL 3 382 18-Apr-23 22-Jul-24 06-Oct-22 A 11-Jun-24 25,198,216.72 23,733,696.34 13,509,978.03 94.19% 53.61%
MEP ROOMS 81 04-Nov-23 06-Feb-24 04-Nov-23 06-Feb-24 32,406,130.62 32,406,130.62 0.00 100% 0% 06-Feb-24, MEP RO
ENGINEERING 53 04-Nov-23 04-Jan-24 04-Nov-23 04-Jan-24 0.00 0.00 0.00 0% 0% 04-Jan-24, ENGINEERING
PROCUREMENT 60 28-Nov-23 06-Feb-24 28-Nov-23 06-Feb-24 31,950,996.63 31,950,996.63 0.00 100% 0% 06-Feb-24, PROCUR
CONSTRUCTION 20 13-Dec-23 04-Jan-24 13-Dec-23 04-Jan-24 455,133.98 455,133.98 0.00 100% 0% 04-Jan-24, CONSTRUCTION
EXTERNAL SURROUNDING UTILITIES 370 25-Feb-23 12-May-24 26-Nov-22 A 13-Feb-25 13,562,657.01 13,562,657.01 1,108,016.43 100% 8.17%
CROWD CORRIDOR NO.01 BESIDE ZONE 10 27 13-Dec-23 13-Jan-24 13-Dec-23 13-Jan-24 740,327.99 740,327.99 0.00 100% 0% 13-Jan-24, CROWD CORRID
CROWD CORRIDOR NO.04 IN SUPERBLOCK 2 82 15-Nov-23 18-Feb-24 26-Nov-22 A 13-Feb-25 0.00 0.00 0.00 0% 0%
SUPERBLOCK - S1 51 05-Nov-23 03-Jan-24 05-Nov-23 03-Jan-24 602,326.96 602,326.96 0.00 100% 0% 03-Jan-24, SUPERBLOCK - S1
SUPERBLOCK - S2 51 05-Nov-23 02-Jan-24 05-Nov-23 02-Jan-24 183,936.21 183,936.21 0.00 100% 0% 02-Jan-24, SUPERBLOCK - S2
SUPERBLOCK - S3 40 09-Dec-23 24-Jan-24 09-Dec-23 24-Jan-24 54,921.48 54,921.48 0.00 100% 0% 24-Jan-24, SUPERBLOC
SUPERBLOCK - S4 20 01-Jan-24 24-Jan-24 01-Jan-24 24-Jan-24 0.00 0.00 0.00 0% 0% 24-Jan-24, SUPERBLOC
SUPERBLOCK - S5 30 03-Apr-24 12-May-24 03-Aug-23 A 26-May-24 439,748.46 439,748.46 219,874.23 100% 50%
SUPERBLOCK - S8 52 15-Nov-23 15-Jan-24 15-Nov-23 15-Jan-24 146,457.29 146,457.29 0.00 100% 0% 15-Jan-24, SUPERBLOCK -
DISTRICT - D9 369 25-Feb-23 11-May-24 13-Dec-22 A 08-May-24 7,199,957.32 7,199,957.32 888,142.20 100% 12.34% Completion Engineering work for Extern
DISTRICT - D10 279 20-Mar-23 15-Feb-24 13-Dec-22 A 15-Feb-24 4,194,981.29 4,194,981.29 0.00 100% 0% Completion Engineering15-Feb-24,
work for Extern
DIST
LOCAL ROADS AND PAVINGS 42 04-May-24 25-Jun-24 01-Jan-23 A 30-Oct-24 0.00 0.00 0.00 0% 0%
ENGINEERING 42 04-May-24 25-Jun-24 01-Jan-23 A 30-Oct-24 0.00 0.00 0.00 0% 0%

WBS Summary Summary Date Revision Checked Approved

Actual Work
Page 1 of 1
Remaining Work
Critical Remaining Work
SUMMARY