Capital Investment-Lecture
Capital Investment-Lecture
Hemlata Karne
Factors Affecting Investment &
Production cost
Sources of Equipment
Price Fluctuation
Company Policies
Operating Time & Rate of Production
Government Policies
Factors Affecting Investment &
Production cost
Sources of Equipments
Purchase of new equipments
Purchase of second hand equipments
Price Fluctuation
Raw material & resource cost
Equipments cost
Salaries & wages
Factors Affecting Investment &
Production cost
Company Policies
Safety policies
Labor policies
Labor unions demands
Chemical Reaction
Stoichiometry and Thermodynamics
- material flow
-Overall conversion and heat requirements
Unconverted feed
- separated recycled or reused
Process Economics
Additional Unit operations
Utilities including electricity,
steam, cooling water, refrigeration
Generation on site importing from
third parties
Process Economics….
Feed Stock
- Cost of feed stock- quantity and quality
-Quantity from yield/desired product
-Quality defined by purity
Catalyst
- selection based on yield and selectivity
-optimization reduces investment and operating cost
Capital costs
ISBL
Cos t of procuring and installing
all process equipment
Contingency Charges (10% of ISBL+OSBL)
Minor changes in project or
extra charges
Engineering costs (10% of ISBL+OSBL)
Home office/design
Offsite costs (40% ISBL)
If you want more infrastructure/
expand
Working capital
Money tied up in maintaining
feed stock, spare parts, products
etc..
Direct and Indirect Cost Estimates
For a Class 4 estimate, from Table 5.2, the expected accuracy range is between 3 and 12
times that of a Class 1 estimate. A Class 1 estimate can be expected to vary from +6% to -
4%. We can evaluate the narrowest and broadest expected capital cost ranges as:
Lowest Expected Cost Range
High value for actual plant cost ($2.0 x 106)[1 + (0.06)(3)] = $2.36 X 106
Low value for actual plant cost ($2.0 x 106)[1 - (0.04)(3)] = $1.76 x 106
The actual expected range would depend on the level of project definition and effort. If
the effort and definition are at the high end, then the expected cost range would be
between $1.76 and $2.36 million. If the effort and definition are at the low end, then the
expected cost range would be between $1.04 and $3.44 million.
Example 5.2
Compare the costs for performing an order-of-magnitude estimate and a detailed
estimate for a plant that cost $5.0 x 106 to build.
Solution :
For the order-of-magnitude estimate, the cost of the estimate is in the range of
0.015% to 0.3% of the final cost of the plant: