Final Project Proposal
Final Project Proposal
Hydropower
IETP
PROJECT PROPOSAL
Table of Contents
1. Introduction…………………………………………………………………………………………………………….1
2. Background Study……………………………………………………………………………………………………1
3. Objective…………………………………………………………………………………………………………………2
3.1. General objective…………………………………………………………………………………………2
3.2. Specific objective…………………………………………………………………………………………2
4. Work Plan and Modeling…………………………………………………………………………………………2
4.1. Physical Modeling…………………………………………………………………………………..……2
4.2. Mathematical Modeling…………………………………………………………………………..….3
4.2.1. Turbine Sizing……………………………………………………………………………………..….3
4.2.2. Turbine Modeling………………………………………………………………………………..…3
4.2.3. Power Calculation………………………………………………………………………………..…3
5. Important Assumptions………………………………………………………………………………………..…4
6. Whirlpool Hydropower Turbine System………………….………………………………………………4
6.1. Advantages and Disadvantages……………………………………………………………………4
7. Project Evaluation……………………………………………………………………………………………………5
7.1. Relevance ……………………………………………………….……………………………………………5
7.2. Effectiveness………………………………………………..………………………………………………5
8. Cost Breakdown………………………………………………………………………………………………………5
9. Design Approach………………………………………………………………………………………………………6
10. Geolocation……………………………………………………………..………………………………………………6
11. Stake holders……………………………………………………………………………………………………………7
12. Project Team……………………………………………………………………………………………………………8
13. Time Schedule…………………………………………………………….……………………………………………8
1. Introduction
Supply of electrical energy in rural area is always challenging due to high cost for installation of
transmission and distribution equipment, especially in mountainous areas. Some villages with
farm lands have rivers or water stream but usually cannot benefit from the sustainable
electricity for livelihood purposes. To overcome the high cost electricity production and to
promote eco-friendly environment, a small hydropower plant can contribute majorly.
The use of hydropower energy for energy generation is one of the oldest methods for
harnessing renewable energy. Use of renewable energy is an essential ingredient of
socioeconomic development and growth. Nowadays with increased concern for environment
led to the research for more environment friendly sources of energy and with this
considerations wind energy can be considered as a viable option.
2. Background Study
Agriculture accounts for 33 percent of Ethiopia’s GDP and 70 percent of its exports, with almost
eight of every ten workers in the country connected to the sector. It is increasingly difficult for
the agriculture sector to grow, especially as demand continuous to increase throughout the
country. It’s difficult to think of growing the agricultural industry without giving the vast rural
area of our country access to reliable & affordable electricity. Today, just 30 percent of
Ethiopia’s rural population has access to electricity, often through small solar lights or
intermittent grid supply.
Although Ethiopia is unique in that practically all of its electricity is produced from low-carbon
energy sources, we still didn't reach our limit when it comes to developing more of the
same energy that is essential to provide rural areas with electricity and guaranteeing a
sufficient supply of energy. The number of Ethiopians without access to the electrical grid is
now at 70 million, and there is a significant difference between access in rural and urban areas
(varying from five to 20 percent in rural areas to 80-90 percent or more in metropolitan areas.
To overcome this, we must find a way to come up with more sources of electric power
generation, and this is where our projects comes in. Among several options for rural
electrification, a small - hydropower plants have a special place for their ability to generate
energy continuously provided the rated flow. And this whirlpool hydropower plant is among
one of this hydropower generating plants that can easily be helpful to form mini-grids
throughout the country.
So to ease entry and exit in mini-grid development involvement both for the government and
the private sector participants. a good frame work needs to be established to create
transparent and trustful engagement in the development effort and also to ascertain
investment return and operational undertaking in orderly manner
1
3. Objectives
General objective
Our objective is the
2
Dynamic turbine is used to utilize the full flow of water inlet to rotate the turbine. Selection of turbine
blade is an important factor to enhance the efficiency of whole system because the turbine blades
should be able to catch the flow of whirlpool. Where:
5.2 Mathematical Modeling D = discharge in 𝑚3
A. Turbine Sizing /𝑆𝑒𝑐, (2)
C. Power Calculation
The theoretical power available from the flow of water falling to turbine can be expressed in as:
3
5. Important Assumptions
➢ Influence by weather conditions
Weather conditions of the project site are roughly sorted into the rainy season and the dry
season. In the rainy season, the constructions in the river are not possible due to high river
water levels, and also transportation of equipment and materials are restricted due to wet road
conditions. Therefore, the main part of construction works shall be carried out in the dry
season, while the partial works can be done even in the rainy season carefully.
➢ Influence by other projects/ imported items
As for equipment and materials, unless the items are made locally, imported items form
different countries could disrupt the project’s schedule.
4
7. Project Evaluation
• Relevance
The hydropower plant of this project is one of renewable energy power sources, and it has a
characteristic of relatively small environmental and social impacts. And also, the other
component of the project is to extend distribution lines to rural un-electrified villages, therefore
the project is consistent.
• Effectiveness
In addition to the contribution to the rural electrification and power import reduction the
following effects are also expected:
✓ Strengthening stable power supply to the surrounding areas
✓ Contribution to the local economic development and livelihood improvement
✓ Promotion of renewable energy development
8. Cost Breakdown
As of now, we expect to have the following expense in order to create our whirlpool turbine
project:
Cable
Type-B 3 225
Water tank 2 450 900
5
9. Design Approach
Installing Hydropower Plant Process:
➢ Surveying
The works concerning the construction of the Hydropower plant (diversion tunnel, concrete
framework, power house etc.) are concentrated in a small area of about 1.5m2.
The topography of Ethiopia, with mountainous areas coupled with numerous rivers and streams
makes Micro Hydropower Plants (MHP) development suitable. Out of this, about 15% of the
overall hydropower potential is from unregulated river run-off, usually in the category of micro
hydropower plants.
85% of Ethiopia’s population is living in rural areas while only 10 out of 100 households have
access to electricity. Extending the national grid to isolated rural communities seems technically
and economically not feasible in many cases. Due to its high potential, micro hydropower plants
could play an important role to electrify off-grid areas.
➢ Land Acquisition
Land acquisition is required to enable placement of the project which belongs to government as
riverside area, though this land could have been used for agriculture or garden by a local people
so, getting permission from its owner could be needed.
➢ Excavating, Installation and Framework
6
• Ganale Doria Riverside Area
The Ganale Doria river found in southeastern Ethiopia region, rising in the mountains east of
Aleta Wendo, it covers 171,050 sq. km in size with an annual runoff of 5.80 billioin cubic metres
and specific discharge of 1.2 litres per second per sq. km. The catchment area is estimated as
having the potential to irrigate 1,070 sq.km and to generate an enormous electric power.
NB: Ethiopia has approximately 11 large hydropower dams with an annual energy production
based on these rivers however, the rural side of these areas can’t even access electricity.
Therefore, this project aims to develop these river side areas by fulfilling their electrical power
demand.
11. Stakeholders
In order to achieve the goals, we need to have a good frame work from the regulatory side and
as the guidelines are under development in our country there isn’t much we can say about the
pricing and other related issues.
But generally the main stakeholders of the project that can help us to implement this service
are;
1. Public offices (the Government): agencies that are related to energy, water, electricity
and even agriculture. In our country these are MoWIE, EEU, Regional Energy Bureau’s,
Cooperatives
2. Private sector: here it can be organizations that can either help financially or in other
different sectors. These include Private sector enterprises, Banks, Micro finance
institutions, other financial intermediaries
3. The people: the people are the most important factors of this project because at the
end of the day the plan is to help people and we have communicated with them
constantly.
7
Sector Implementing Agency and Intermediaries
8
In the following chart we illustrate the general planned timeline of our
project.
proposal development
beginning of development
procurement process
design improvements