Performance Task (Preliminary)
Performance Task (Preliminary)
Performance Task
1. S sold to B a specific SUV which S agreed to deliver no later than July 31, 2024. S did not
deliver the SUV on the said date.
a. Is S guilty of legal delay and, therefore, liable for damages? Why or Why not?
S is guilty of legal delay and liable for damages for failing to deliver the SUV to B by the
agreed upon date of July 31, 2024. When a seller agrees to deliver goods by a certain date
and fails to do so, this constitutes a breach of contract. The delivery date was a material term
of the sales agreement between S and B. By not delivering the SUV by July 31st, S did not
uphold their end of the contract and is now liable for any damages that B faced due to not
receiving the SUV on time. The law provides that B can recover damages from S for this
delay.
b. If demand is made upon S by B on August 5, 2024, and S fails to deliver the SUV,
when is S considered to be in default?
S would be considered in default beginning on August 6, 2024 if demand was made by B
for the SUV on August 5th and S still failed to deliver. When B made a demand on August
5th for S to deliver the SUV per their original agreement, this put S on notice that they
needed to promptly deliver to avoid defaulting. S would have a reasonable time period to
fulfill this new demand made by B. Assuming one day is a reasonable time period for S to
respond to the demand, then if S still did not deliver the SUV on August 6th, they would be
considered in default at that point. The original breach of contract occurred on July 31st
when S failed to meet the initial delivery date. But S would not be in full default until failing
to deliver within a reasonable time after B's subsequent demand.
c. If an action for specific performance is filed by B on August 10, 2024, when does the
payment of damages for the default commence?
If B files an action for specific performance against S on August 10, 2024, the payment
of damages would commence from the date that S originally defaulted by failing to deliver
the SUV. Even though the legal action was not filed until August 10th, the damages began
accruing on August 6th when S failed to deliver the SUV within a reasonable time after B's
demand. The damages start from the initial date of default, not the date the lawsuit is filed.
So in this case, B could claim damages starting from August 6, 2024 onwards until S delivers
the SUV. The filing of the lawsuit on August 10th does not impact or reset the timeline for
when damages commenced. The damages began on the default date and would continue
accumulating until S cures the default by delivering the SUV to B.