HDPE Fire Fighting Network in EOV
HDPE Fire Fighting Network in EOV
of The Arab Contractors and Elsewedy Electric Julius Nyerere Hydropower Project
EMPLOYER
JOINT VENTURE OF
PROJECT
Ver Date Version Detail Rev Date Revision Details Checked Approved Approved
Scale: 1/100 Type: A4/Black Phase: Construction Discipline: Mechanical Contract / PO No: 7000
Originator Title
This document defines specific guidelines that shall be considered while installing & testing HDPE firefighting Network at
operation village area
The method statement also communicates and defines the risks that may be involved during the activities, to ensure the highest
safety level required.
1‐ Description of Work:
This Method of statements describes the installation procedures for the Installation & testing of HDPE
Fire fighting Network at operation village area
2. Erection sequence
• Prior to the stage of fabrication and erection of any Activity, all Related Isometric (ISO)
drawings/layout to be issued as “For Construction”. ‐ Spools drawings, if applicable, to be
produced in accordance with ISO drawings/General Arrangements drawings/layout.
• Materials indicated in the drawings must be available with required size, quantity and quality
that confirm the requirements given in the related drawings.
• All materials to be used in the fabrication and erection shall be visually examined for no damage
and assure internally cleanness.
• Handling of pipes shall be by slings. Soft‐faced hooks, may also be used for lifting.
• After welding, “Visual Inspection” shall be done
3.0
Scope
• The scope of this method statement is to covers the Method Statement for Underground High Density
Polyethylene Pipes installation
• The purpose of this method statement is to detail the methods required to execute the Under Ground High
Density Polyethylene Pipe piping systems with the appropriate quality according to international standards.
• Butt Fusion Welding of HDPE Pipes Work Procedure
• The principle of butt fusion is to heat the pipe ends to a designated temperature (200-230 C deg.) under
pressure for a specified amount of time, then the pipe ends are fused together under pressure for a period of
time
WORKING PROCEDURE
1. •
• Preparation of welding: before you start the operation, it is
important to prepare the work area.
• Select the operation area that is suitable for the work.
• Install the protection tent or other equipment to protect the
welding zone against rain, sunshine or bad weather (if required)
• Set up the welding machine with all the accessories according to
the welding pipe size. Check if the machine is functioning.
• All of the problems or missing parts must be fixed prior to the
start of the welding operation.
• Welding machine must be calibrated before using
• Pipes to be cut with Over length for shaving and heat fusion
• Using suitable equipment for loading and downloading pipes ,
shaving tool & Heating plate such as ( forklift , boom truck & Mobile Crane )
2.
• Insert two pipes ends on both side of the machine clamps, protrude approx. 3-5 cm. from each shell side,
clamping and adjust the pipe or piping part, the surfaces to be welded should be parallel to each other.
• Adjust the alignment of pipe line by tightening or losing bronze nuts on the top aluminium clamps.
• Secure longitudinal movement of the parts to be welded by taking appropriate measures.
• Clean outside and inside pipe surface.
3.
• Insert the shaving tool or trimmer between the two pipe ends into
the lock position on the welding machine.
4.
•
Start the shaving tool or trimmer by turning on the
control switch.
•
Slowly approach the pipe ends towards the shaving tool
or trimmer by controlling the directional valve on
hydraulic control unit while keeping control pressure a
little higher.
The cutter will cut the surface of both pipe ends making
them clean, plane and parallel.
5.
•
When the pipe ends had been trimmed squarely and with an even thickness, slowly decrease the
pressure before switching off.
•
Remove the shaving tool or trimmer from welding machine to the support frame and clear the facing
scraps from pipe ends.
•
Inspect the ends, they must be clean and plane; otherwise repeat the step 3 – 5 again.
•
During the clearing and inspection, avoid any contact with the surface of pipe ends.
6.
•
Recheck the alignment of the pipeline by bringing the pipe ends closely together and measure the actual
tolerance.
7.
•
Bring the pipe ends apart, to clean both pipe ends using coat with suitable cleaning agent and avoided any
contact to the surface after cleaning.
•
Repeat the cleaning process, if necessary.
8.
•
To start with the welding process, begin with the alignment stage by inserting the heating plate between the
two pipe ends, moving both pipe ends close together until contact with the heating plate.
•
Start the build up pressure, maintain the pressure until there are welding seam appear.
9. Open both pipe ends, carefully remove the heating plate without touching the melted area and see to it that
• the removing time should not be longer than permissible time, insert heating plate to the support.
10.
Immediately increase pressure up to the joining pressure level within the joining pressure built-up time
• Uniform beads must be created throughout the whole circumference of the pipe joints.
• Maintain or Keep the joining pressure constant throughout the cooling time or until the welding joint cools
down. Avoid forced cooling down by applying water.
11.
• Possible differences in the formation of the beads may be justified by different behavior of the joined
materials.
Trench Length
The length of open trench required for fused pipe sections should be such that bending and lowering the pipe
into the ditch does not exceed the manufacturer ’s minimum recommended bend radius and result in
kinking.
Trench Width
The trench width should allow sufficient room for joining the pipe, if required, snaking small diameter from
side to side along the bottom of
Trench Construction
Principal considerations in trench construction are trench width, length, and depth; soil stability; and
groundwater accumulation in the trench. Unstable soils or wet conditions should be controlled by sloping or
bracing the trench walls, de-watering the trench bottom, and/or other measures.
Placing Pipe in Trench
Place HDPE pipe up to 1600 mm diameter in the trench Using equipment to lift, move, and lower larger
diameter pipe into the trench. Pipe must not be dumped, dropped, pushed, or rolled into the trench.
Backfilling
Backfill the pipes with recommended soil and compaction to be done with suitable equipment
Why wo do H.T
T o uncover any faults in the pipeline joints - for example, electrofusion, butt fusion or mechanical joints.
T o reveal any faults in the assembly of fittings, including valves, hydrants, bends, tees, branch saddles,
and flanges. T o check that the pipeline will handle pressure greater than its design pressure without
leaks.
A fully fused pipe string for installation by a trenchless method such as Horizontal Directional Drilling, may have a pre-
commissioning test, above ground.
Generally check that the complete pipeline has no leaks and is ‘good to go” into service.
But... A test may not uncover damage to pipes, that’s your job…you must check for damage during construction.
Pre-commissioning testing is not intended to supplement or replace the test requirements of the pipeline product Standards.
What you need to know
You’ll need to choose an appropriate Test Method, with consideration for:
(a) Pipe diameter, PN class and length to be tested. (b) Length of time for the pressure test itself.
(c) Magnitude of the test pressure and rate of pressurization.
(d) Removing all air from the pipeline during filling with water
(e) Prevent movement of thrust restraints, and have in place all permanent or temporary anchor block supports.
(f) Be sure your test gauges are accurate.
YOUR
(g) BeTEST EQUIPMENT
aware of ambient temperature changes during testing.
(h) Prevent
Test Manifoldleaks
& theinPump
all test equipment and the pipeline.
.
.
PRE‐TEST PROCEDURES
When the pipe is pressurized, visually inspect all the exposed joints to be sure they have no leaks. Avoid testing against any closed isolation valves as these
can leak slightly and upset the test.
• Leave all bolted or flanged joints exposed, to allow for re-tensioning during or after testing.
• Leave all fusion joints, service connections and valves exposed, wherever possible to check for leaks.
• Always, slowly fill the pipeline with water from the lowest point – this will allow for air to migrate to the high point and allow it to
bleed off through an air valve, hydrant or service connection located at a high point.
• Be sure to remove all air out of the line during filling, and before you apply the test pressure. Air trapped in the line, can make the test
appear like you have a leak, (when there actually is no physical leak) and give a false result.
• T he availability of water for testing is important….
you’ll need a clean acceptable supply and don’t forget you’ll need an approved location to discharge it after the test.
• As the pipe slowly fills with water, allow a stabilization time-period for the air to escape and water temperature in the pipe to stabilize.
T he length of the stabilization time period will depend on the pipe diameter, and ground gradients or profile - overnight is preferred but
should be at least 3 hours. Any trapped air must be bled off before you start your pressure test.
Assessment Assessment
Task/Activity / No Control With Control
Ser. Hazard Hazard Effect Control Measures
Operation
P S R P S R
RISK ASSESSMENT FORM
Assessment Control Measures Assessment
No Control With Control
Task/Activity / Hazard
Ser. Operation Hazard Effect
P S R P S R
D Avoid manual handling by using special beams.
D Heavy loads D Team lifting (e.g. several workers to handle large loads)
D Poor ergonomics D D Using manually operated load handling aids) e.g. trolley,
Slippery objects D Medical chain – block, forklift, wheelbarrow)
D Slippery surfaces Treatment
D All assist lifting equipment shall be maintained and
D Jammed objects D Chronic/Acute
Manual inspected.
D Unknown load weight disorder
Handling, D High frequency of D Dividing the load into smaller packages to reduce the
04 Pushing, D Equipment and 4 3 A weight. 1 2 --
lifting/action property damage
Pulling/ Bio-
D Pre-existing injury D Reduce duration & frequency of manual handling
Mechanics D Fatigue D Provide adequate breaks and recovery time
D Disease D Stress
D Shifting weight D Ensure provision of dry and anti-slip surfaces and access.
D Any leaks and spillage shall be corrected in accordance
D Bio mechanical
inefficiency with site instructions.
D Equipment failures D Ensure provision of adequate free space for
D equipment and worker’s movement without any
Task/Activity / Hazard
Ser. Operation Hazard Effect
P S R P S R
Summary of Requirements:
1 Specific Training : Manual handling, Hot work, Electric hazard, Welding and cutting
Task/Activity / Hazard
Ser. Operation Hazard Effect
P S R P S R
3 PTW required : Hot work and high risk activates permit and STARRT Cards.
8 Certificates, SDS or Data Sheets : This document shall be reviewed periodical in accordance with site conditions, change in work method and
used materials or failure in controls measures / Major accident or change.
Assessed by: