PEMERIKSAAN DAN PENGUJIAN K3 BERKALA
INSTALASI HYDRANT
(UU NO. 1 TAHUN 1970 TENTANG KESELAMATAN KERJA Jo.
PERATURAN MENTERI TENAGA KERJA RI Jo. INS.11/M/B/1997
Jo. SNI, PUIL)
PT. PLN (PERSERO) UP3 PALOPO
JL. Andi Kambo No. 70, Kota Palopo, Sulawesi Selatan
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
PEMERIKSAAN DAN PENGUJIAN BERKALA
K3 PROTEKSI KEBAKARAN JENIS INSTALASI HYDRANT
MEREK GRUNDFOS, TYPE CR5-18 A-FGJ-A-E-HQQE
PT PLN (PERSERO) UP3 PALOPO
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
DAFTAR ISI
1. SERTIFIKAT HASIL PEMERIKSAAN DAN PENGUJIAN (RIKSA UJI) ................
2. LAPORAN HASIL PEMERIKSAAN DAN PENGUJIAN K3 INSTALASI HYDRANT
DAN SPRINKLER ...........................................................................................
- DATA UMUM ............................................................................................
- DATA BANGUNAN ....................................................................................
3. PEMERIKSAAN DAN PENGUJIAN (CHECK LIST RIKSA UJI) ............................
4. REKOMENDASI (RIKSA UJI) ...........................................................................
5. BERITA ACARA HASIL PEMERIKSAAN (RIKSA UJI) .........................................
6. PHOTOGRAPH RIKSA UJI ..............................................................................
7. LAMPIRAN DOKUMEN & SERTIFIKAT ...........................................................
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
SERTIFIKAT HASIL
PEMERIKSAAN
DAN PENGUJIAN
RESULT OF INSPECTION
THIS IS TO RESULT OF INSPECTION THAT, based on the request of PT PLN (Persero) UP3
Palopo, PT. Bumi Teknik Selaras Makassar City Office has been inspected for 1 (one) unit Hydrant
Instalation, with result as follows:
Testing Certificate Number : RUBK-IH&S/013/IX/2023
Owner : PT PLN (Persero) UP3 Palopo
Equipment : Hydrant
Number of Floors : 1 (One)
Serial No. : A-96513388-10000373
Merk / Type : Grundfos / CR5-18 A-FGJ-A-E-HQQE
Type of Inspection : Periodical 12 Months
Date of Inspection : August 30th, 2023
Location of Inspection : Warehouse PT PLN (Persero) UP3 Palopo
Jl. Veteran, Tomarundung, Palopo City, South Sulawesi
Inspection Item : 1. Visual Inspection
2. Dimension Check
3. Hydrant testing pressure
Referens Test :
- Law No. 1 Of 1970 Concerning Work Safety
- Regulation of The Minister of Manpower No. PER 02/MEN/1983
- Instructions of the Minister of the Republic Of Indonesian No. INS. 11/M/B/1997
- SNI 03-3985-2000
The inspection result is stated below:
Suggestion : - Record of maintenance, modification and alteration should be attached
on this document.
- Periodical inspection of the Hydrant Instalation should be conducted in interval
12 (twelve) months.
Conclusion : Based on inspection result, the equipment above found in order and can be
operated accordingly.
Expired Date : August 30th, 2024
Place of issued : Palopo City, South Sulawesi
Date: September 4th, 2023
Director
Ali Hafid
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
LAPORAN PEMERIKSAAN DAN
PENGUJIAN K3 INSTALASI
HYDRANT
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
LAPORAN PEMERIKSAAN & PENGUJIAN
K3 INSTALASI HYDRANT
No. RUBK-IH&S/013/IX/2023
DATA UMUM
1. Nama Gedung/Bangunan : Gudang PT PLN (Persero) UP3 Palopo Dan
Gedung PT PLN (Persero) ULP Palopo Kota
2. Alamat : Jl. Veteran, Tomarundung, Kota Palopo
3. Penggunaan Bangunan : Gudang Dan Kantor
4. Pemilik : PT PLN (Persero) UP3 Palopo
5. Pengelola : Manajement PT PLN (Persero) UP3 Palopo
6. Nama Penaggung Jawab : Alimuddin (Manager UP3)
DATA BANGUNAN
1. Luas Lahan : 3.389 m²
2. Luas Bangunan : ± 1.188Meter
3. Konstruksi Bangunan
- Struktur Utama : Beton Bertulang
- Struktur Lantai : Keramik
- Dinding Luar : Bata Ringan
- Dinding Dalam (Penyekat) : Gypsum
- Rangka Plapond : Baja Ringan
- Penutup Plapond : Gypsum
- Rangka Atap : Beton
- Penutup Atap : Beton
4. Tinggi Bangunan : 9 Meter
5. Jumlah Lantai : 1 Lantai
6. Jumlah Luas Lantai : ± 1.188 m3
7. Dibangun Tahun :-
8. Perlengkapan Proteksi Kebakaran
8.1 ( √ ) AlatPemadamApiRingan
8.2 ( √ ) Instalasi Alarm Kebakaran Otomatik
8.3 ( √ ) Instalasi Hydrant
8.4 ( - ) Instalasi Sprinkler
8.5 ( - )Instalasi Khusus *)
8.6 ( √ )Sarana Evakuasi
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
PEMERIKSAAN
DAN PENGUJIAN (CHEKLIST)
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
LAPORAN HASIL
PEMERIKSAAN DAN PENGUJIAN
K3 INSTALASI HYDRANT
PT PLN (Persero) UP3 PALOPO
Laporan ini terdiri atas laporan pemeriksaan visual dan laporan pengujian dengan berdasar
pada:
Undang-Undangnomor 1 tahun 1970 Tentang Keselamatan Kerja
Keputusan Menteri Tenaga Kerja Republik Indonesia No. : KEP.186/MEN/1999
Instruksi Menteri RI. No. Ins II /M/BW/1997
SNI 03-1735-2000, SNI 03-1745-2000, SNI 03-6570-2001, SNI-03-3989-2000
Pemeriksaan Visual
a) Pemeriksaan Visual pada instalasi hydrant
b) Pemeriksaan dilakukan secara visual pada bagian-bagian dan tempat-tempat
yang dapat dilihat dan dijangkau
c) Pemeriksaan pada panel pompa
d) Pemeriksaan dilakukan secara visual pada pompa jockey, pompa elektrik, dan
Diesel
e) Pemeriksaan pada hydrant pilar, dan kelengkapan isi box hydrant
f) Pemeriksaan pada reservoir
Pengujian Instalasi Hydrant
1. Pengujian pada instalasi hydrant
a) Pengujian tekanan pada pompa jockey, elektrik, dan Diesel
b) Pengujian pada hydrant pilar terdekat, hydrant pilar bagian belakang dan
hydrant pilar terjauh
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
PEMERIKSAAN DAN PENGUJIAN K3 INSTALASI HYDRANT
A. PEMERIKSAAN DOKUMEN
PEMERIKSAAN DOKUMEN INSTALASI HYDRANT DAN SPRINKLER
NO. OBYEK HASIL NILAI RUJUKAN METODE
INS. KEMENAKER NO :
1. PENGESAHAN Ada/Tidak Ada VISUAL
INS.11/M/BW/1997
INS. KEMENAKER NO :
2. PEMASANGAN Ada/Tidak Ada VISUAL
INS.11/M/BW/1997
INS. KEMENAKER NO :
3. BUKU MANUAL Ada/Tidak Ada VISUAL
INS.11/M/BW/1997
BUKU PEMELIHARAAN INS. KEMENAKER NO :
4. Ada/Tidak Ada VISUAL
& OPERASI INS.11/M/BW/1997
INS. KEMENAKER NO :
5. TANDA PERINGATAN Ada/Tidak Ada VISUAL
INS.11/M/BW/1997
SERTIFIKAT PABRIK INS. KEMENAKER NO :
6. Ada/Tidak Ada VISUAL
PEMBUAT INS.11/M/BW/1997
INS. KEMENAKER NO :
7. RECORD DAILY Ada/Tidak Ada VISUAL
INS.11/M/BW/1997
DATA PENUNJANG INS. KEMENAKER NO :
8. Ada/Tidak Ada VISUAL
LAINYA INS.11/M/BW/1997
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
SPESIFIKASI PEMASANGAN INSTALASI HYDRANT
NO PERIHAL SPESIFIKASI STATUS KETERANGAN
1. Sumber air baku Air tanah & PDAM Baik
L meter x P meter x T Baik
2. Ground Reservoir meter
= 260 m³
3. Tangki Grafitasi - Baik
4. Siamese Connection Ada Baik
Q : 5.8 m3/h
Pompa Pacu /Jockey Pump H : 123 Meter
5. Baik
Merk Grundfos Start oto : 8 Kg/cm²
Stop oto : 10 Kg/cm²
Q : 500 US GPM
Pompa Utama H : 250 Meter
6. Baik
Merk Elektrim Start oto : 8 Kg/cm²
Stop oto : 10 Kg/cm²
Q : 500 US GPM
Pompa Diesel H : 250 Meter
7. Baik
Merk Isuzu Start oto : 7 Kg/cm²
Stop Manual: Kg/cm²
8. Priming tank Ada Baik
Kapasitas : 800 Liter
9. Bejana Angin P. Kerja : kg/cm²
Baik
P. Uji : kg/cm²
10. Pressure relief valve Hizec FW. 10 Bar Baik
11. Test Valve Kitz 4” Baik
12. Indikator Listrik terbuka Panel Indikator Baik
13. Pipa Hisap 4 inci Baik
14. Pipa Penyalur Utama 4 inci Baik
15. Pipa tegak 8 inci Baik
- Two Way
Hydrant Pilar / Hydrant
16. - With Main Valve
Baik
Halaman - With Ball Valve
- Size : 4’ x 2½’ x 2½
17. Hydrant Gedung - Baik
18. Hose Rell Starvvo 2,5 Baik
Catatan *)
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
Analisa Perhitungan Kecukupan Reservoir
Dari Pemeriksaan di Rumah Pompa Pompa di PT. PLN (Persero) UP3 Palopo, suplai
kebutuhan air untuk proteksi kebakaran sudah terpasang mulai dari tempat
penyimpanan air (Reservoir), Sistem distribusi, Sistem Pompa Hydrant. Melalui
perhitungan diketahui Reservoir Volumenya 260 m3, 500 Galon Per Minutes (GPM),
dan untuk durasi air mensuplai dari Pompa Hydrant sebagai berikut:
Kapsitas Resrvoir 260 m3
Debit Air Electric dan Diesel Pump 500 GPM – 113,562 m3/h
Debit Air Jockey Pump = 5,8 m3
Jadi Kemampuan Mensuplai Air ke Pompa adalah :
260 𝑚3
Electric dan Diesel = 𝑥 60 𝑀𝑒𝑛𝑖𝑡 =
113 𝑚3/ℎ
138 menit atau 2 Jam 18 menit
Jadi durasi waktu dalam mensuplai Air ke pompa Hydrant 2 jam 18 menit
kemampuan air tersedia, sehingga dalam pemadaman kebakaran waktu tersebut
masih memungkinkan bantuan Pemadam kebakaran dari pihak pemadam
kebakaran External terdekat setempat dengan jarak 4,1 km dari PT. PLN (Persero)
UP3 Palopo.
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
SPESIFIKASI PEMASANGAN PERLENGKAPAN INSTALASI HYDRANT
JumlahPerlengkapan Hydrant
Indoor Outdor
No Lokasi Status
Landing valve
2,5” 1,5” 1” HP HM SC
1. Area Depan √ √ Baik
2. Area Tengah 1 √ √ Baik
3. Area Tengah 2 √ √ Baik
4. Area Belakang √ √ Baik
HASIL PERCOBAAN UNIT POMPA
NO. POMPA START STOP KETERANGAN
1. Otomatik/Manual Otomatik/Manual
POMPA PACU
8 Kg/cm² 10 Kg/cm²
2. Otomatik/Manual Otomatik/Manual
POMPA UTAMA
8 Kg/cm² 10 Kg/cm²
3. Otomatik/Manual Otomatik/Manual
POMPA DIESEL
7 Kg/cm² 10 Kg/cm²
4 Otomatik/Manual Otomatik/Manual
POMPA CADANGAN
Kg/cm² Kg/cm²
HASIL PERCOBAAN OPERASIONAL HYDRANT
NO. PERCOBAAN TEKANAN STATUS KETERANGAN
1. Stand By 10 Kg/cm² Baik
2. 1 Titik hydrant 9,8 Kg/cm² Baik
3. 2 Titik hydrant 8,5 Kg/cm² Baik
4 3 Titik hydrant 7,0 Kg/cm² Baik
*Pengujian menggunakan alat Pitot Pressure Gauge Merk Wiebrock
Dibuat di Makassar pada tanggal 4 September 2023
Nama Jabatan TandaTangan
Ahli K3 Proteksi Kebakaran
Nirwan Saini
PT. Bumi Teknik Selaras
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
REKOMENDASI
(KESIMPULAN DAN SARAN)
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
REKOMENDASI (KESIMPULAN DAN SARAN)
Berdasarkan standarisasi hasil pemeriksaan dan pengujian bahwa K3 Instalasi Hydrant
berfungsi dengan baik, beberapa hal yang perlu ditindak lanjuti, sebagai berikut :
INSTALASI HYDRANT
1. Pengujian pada Jockey Pump dengan hasil baik dimana tekanan pada pompa
4,5 kg cm²
2. Pengujianan pada Elektrik Pump dengan hasil baik dimana tekanan pada pompa
9,8 kg cm²
3. Pengujian pada pilar hydrtant terdekat didaptkan hasil baik yang ditandai dengan air
menyembur keluar dari pilar hydrant dengan deras
4. Pengujian pada pilar hydrant terjauh didapatkan hasil baik yang ditandai dengan air
menyembur keluar dari pilar hydrant dengan deras
5. Rutin memeriksa volume air pada Ground Reservior, agar pasokan air selalu siap saat
ingin digunakan.
6. Mengupayakan agar Unit Pompa dan instalasi selalu Stand Bay.
7. Instalasi tersebut harus dilakukan pengujian ulang setiap tahun sejak dilakukan
pemeriksaan dan pengujian terakhir paling lambat
BULAN AGUSTUS 2024
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
KESIMPULAN.
Sepanjang yang dapat dililhat pada saat dilakukan pemeriksaan dan pengujian pada tanggal
tersebut diatas, dan sesuai dengan persyaratan yang berlaku, dengan ini disampaikan bahwa
k3 proteksi kebakaran (instalasi hydrant) tersebut adalah :
Tidak layak dioperasikan dengan alas an sebagaimana terurai pada table tersebut
diatas, dan
Perlu segera diperbaiki. Pemeriksaan ulang wajib dilakukan setelah dilakukan
perbaikan
Dapat dioperasikan serta diberikan Surat Keterangan Memenuhi Persyaratan K3 /
√ Laik sesuai dengan persyaratan yang berlaku, dengan memperhatikan catatan temuan
yang perlu diselesaikan/diperbaiki, sebagaimana terurai pada table tersebut diatas.
Yang melakukan Pemeriksaan dan Pengujian
PJK3 PT. Bumi Teknik Selaras
Tenaga Ahli K3 Penanggulangan Kebakaran
Nirwan Saini
Pengawas Ketenagakerjaan
Spesialis K3 Kebakaran
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
BERITA ACARA
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
BERITA ACARA
PEMERIKSAAN DAN PENGUJIAN PERALATAN K3
LOKASI BANGUNAN : PT. PLN (PERSERO) UP3 PALOPO
Pada hari ini Rabu tanggal Tiga Puluh Bulan Agustus Tahun Dua Ribu Dua Puluh Tiga, kami
yang bertandatangan di bawah ini:
Nama : Nirwan Saini
Jabatan : Tenaga Ahli K3 Proteksi Kebakaran PT. Bumi Teknik Selaras
Menyatakan bahwa telah melakukan pemeriksaan dan pengujian terhadap peralatan K3 :
1. Instalasi Proteksi Kebakaran Jenis Instalasi Fire Alarm
2. Instalasi Proteksi Kebakaran Jenis Hydrant
Dengan hasil MEMENUHI SYARAT yang telah di rekomendasikan berdasarkan pemeriksaan
dan pengujian serta dilaporkan setelah melakukan perbaikan maupun pergantian peralatan
dengan dasar hukum Undang – Undang No. 1 Tahun 1970 Tentang Keselamatan Kerja
Jo.Instruksi Menteri RI. No. Ins 11/M/B/1997 Jo. SNI.
Demikian Berita Acara ini dibuat untuk dipergunakan sebagaimana mestinya.
Disaksikan/Mengetahui: Yang Melakukan Pemeriksaan dan Pengujian
PT. PLN (Persero) UP3 Palopo Peralatan K3;
PJK3 PT. Bumi Teknik Selaras
Tenaga Ahli K3 Proteksi Kebakaran
......................
( ) Nirwan Saini
Ahli K3 Penanggulangan Kebakaran
.......................
( )
.......................
( )
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail : [email protected] / [email protected],
Website : https//bumiteknikselaras.co.id
PHOTOGRAPH RIKSA UJI
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
Pompa Jockey, Pompa Electric, dan Pompa Diesel
Name Plat Pompa Jockey, Pompa Electric, dan Pompa Diesel
Manometer Tekanan
Pengujian Pada Hydrant Pilar
1
PT. BUMI TEKNIK SELARAS
TECHNICAL TEST ANALYSIS AND INSPECTION (PJK3): ELECTRICAL,
ELECTRICAL CONDITION AND ELECTRONIC EQUIPMENT, LIFT, CONSTRUCTION, AND MECHANICAL
Jl. Minasa Upa Blok H8 No. 8 Kota Makassar, Sulawesi Selatan. Hp/WA. 085 222 678 910
E-mail :
[email protected] /
[email protected],
Website : https//bumiteknikselaras.co.id
Kondisi Pilar Hydrant Dan Box Hydrant
Box Hydrant Lengkap
Panel DC, Jockey, Electric Pump, Dan Diesel Pump
Bejana Angin