PPDN Process Audit Sheet
PPDN Process Audit Sheet
Verified By:
EPS-F/PACE-P12.5KVA-TRC/00
In-process Testing:
22 Should follows as per spec
23 HV Test Agronic BDV Meter
24 No load current With variac dimmer and power meter
25 No load watt loss With variac dimmer and power meter
26 Sec. no load voltages Measure with accuracy multimeter
Varnishing stage:
27 Painting on core Use only rust proof paint
28 Varnish dipping Isonel 31J pure varnish
29 Varnish curing 110°C for four hours
Termination stage:
GE board with engraving -
30 Fixing of terminal board 30x12x309mm
FG testing:
31 HV Test Agronic BDV Meter
32 No load current With variac dimmer and VAW meter
33 No load watt loss With variac dimmer and VAW meter
34 Sec. no load voltages Measure with accuracy multimeter
Final stage:
35 QC inspection As per the sampling plan
36 Transformer Fixing on the Palletts As per the work instruction
37 Covering on transformer Cover with wrapper
9 Mosfets Q1,Q2 fixing with electrical torque AS Per WI & BOM - SE/PPDN/WI/02
11 Thermal switch fixing with electrical torque AS Per WI & BOM - SE/PPDN/WI/03
12 Top plate fixing with electrical torque AS Per WI & BOM - SE/PPDN/WI/05
14 Components pre foming stage as per bom AS Per WI & BOM - SE/PPDN/WI/00
Varnishing Stage:
26 Painting on Core Use only Rust proof paint
27 Varnishing Isonel 31J Pure Varnish
27 Viscocity of the Varnish Viscosity in Sec(50-75)
28 Paint Black
28 Varnish Curing 110°C 5 Hours
Termination Stage:
29 Terminal Board 430x30x12mm
30 Ring lugs 50 SQ mm with M8 hole
31 bolts MS M8x40 mm,5.3Grade, Black
M8 MS plain washers, OD:16MM,
32 Plain Washers
Thickness 1mm,black
33 Nuts M8x40 mm,5.3Grade, Black
34 spring washers M8 MS spring washers
35 Bolts M6X15mm 5.3Grade black
36 Bolts m6X5.3 Grade
Final Stage:
47 QC inspection As per the sampling plan
Observation
SE/QA/F-00
SMT SECTION :
9 Mosfets Q1,Q2 fixing with electrical torque AS Per WI & BOM - SE/PPDN/WI/02
11 Thermal switch fixing with electrical torque AS Per WI & BOM - SE/PPDN/WI/03
12 Top plate fixing with electrical torque AS Per WI & BOM - SE/PPDN/WI/05
14 Components pre foming stage as per bom AS Per WI & BOM - SE/PPDN/WI/00
Stuffing Stage :
15 Components stuffing stage 1 as per bom AS Per WI & BOM - SE/PPDN/WI/07
34 Torriod & Main transformer cable tiening AS Per WI & BOM - SE/PPDN/WI/23