Chapter 3-Building Site Works
Chapter 3-Building Site Works
Abdissa G. [Lecturer]
Building Construction
2023/2024 G.C.
11/19/2023
Building Construction
2
Lecture 3
11/19/2023
Sub-Contents
3.1. Site Selection
3.2. Planning
3.3. Design
3.4. Construction:-
3.4.1. Site preparation
3.4.2. Setting out
3.4.3. Earth work
3
3.1. Site Selection
• The site of a building greatly affects its planning, design and
construction.
• The main factors that should be considered while making the selection
of site for a building are:
• Climatic conditions: The intensity of rainfall and sub–soil water
level should be low so as to avoid dampness in the building.
• This factor is to be considered in case the choice is not limited to
any part of the country.
• Sub-soil conditions: A hard stratum should be available at a
reasonable depth so as to construct the foundation of the building
safely and economically.
4
Site Selection Cont’d
• Availability of modern services: The site must be within
municipal limits so that modern amenities like water supply,
electricity, drainage lines, roads, etc. can be made available in
near future if there is no provision at present.
5
Site Selection Cont’d
• Availability of other facilities: The site should provide as easy access
from the nearest road and offer sufficient light and air; there should
be also good and cheap transport facilities available near the site.
• It is always better if pubic services like the fire team, police station,
etc. are also not very far off from the site.
• Level of the site: The level of the site must be higher than that of its
surroundings so as to provide good drainage.
6
3.2. Planning
• The basic objectives of planning of buildings are to arrange all
the units of a building on all floors and levels according to their
functional requirements, making best use of the space available
for a building.
7
3.3 Design
In building construction works, there are basically five major
types of design:
• Architectural design: is in a sense/intelligence the humanization
of space.
• Structural design centres about the conception, designing and
construction of structural systems.
• Electrical design focus on the provision of adequate electric
power and assembly of associated electrical equipment.
• Sanitary design involves mainly on the supply and distribution of
clean water and waste sewerage disposal system design.
• Mechanical design this design involves the designing of
mechanical equipment like Boiler, Air conditioner, Dust sucker,
elevators and escalators and etc.
11
3.4. Construction
I. Site preparation
• The site will consists of permanent objects existing within the site or
adjoining sites which are used for referencing or identification of the
site called physical site features, e.g. Existing buildings, trees, roads,
fences, etc.
• Before starting the work, permanent bench marks must be established
at a suitable point in the construction site. (like boundary lines)
• Fix position of the storage and stacking of the materials, the site office,
the guard and the labour shed, the access and existing roads for
transport.
• Fix position of health and safety signs/symbols and screw them onto
the fence. Signs outside the fence should read "Danger Construction
Work in Progress" Signs inside the fence should include the site safety
regulations, "No Hats, No Boots, and No Job”. 12
II. Setting out of the building
Terminology
• Setting out: - is the process of locating of the works to be constructed,
ensuring that they are dimensionally within permissible tolerances and
correctly constructed.
– It is the opposite of levelling that is data transferred from plans
to the ground.
• Pegs: - are short pointed wooden rods driving in to the ground to
mark an excavation, construction, etc .line or a level. A nail driven in
top of the peg usually shows the position of the point.
• Batten boards (profile board):- A horizontal board 150mm by 25mm
cut to varying length.
13
NOTE
in them.
14
Methods of Setting Out
In setting out simple (rectangular) building we can use one of the three method
1. The 3, 4, 5 method
2. The builder’s square method
3. Instruments method (Theodolite).
The followings are equipment /tools used in building setting out
Theodolite
Builder’s square
Measuring Tape
Pegs
Strings
Hammer
Nail (different size)
Batten (4x5cm)
15
A. The 3, 4, 5 Method
1. Mark out the building line from the road by measuring the required
distance from the centre of the road, or by stretching a line along an
existing building to the proposed site.
2. Mark out the overall length of the building by driving pegs at A and B
along the ranging line.
3. Obtain two steel tape measures; mark out four equal distances on the
ranging line starting from the corner peg at B. These distances may be
in any unit of measurement. That is mm, cm, m etc.
4. Pull a tape measure from point B to C and ask an assistant to hold it,
ready with hammer and peg.
5. Pull the second tape from fourth mark at D on the ranging line to point
E on the first tape.
16
3, 4, 5 Method Cont’d
23
24
III. Earth work
Site clearing
Foundation excavation
o Bulk excavation
o Trench excavation
o Pit excavation
27
I. Site Clearing
All vegetation such as bushes and scrub; should be removed; the roots of
trees and bushes must be dug out and cleared away.
If the new building is to be built on an area of already existing, the old
building has to be demolished, the debris cleared away and existing
services disconnected and removed.
Site clearing will be carried out using manual labours(with pickaxes and
spades) or Machineries.
The building site should be inspected for termites as part of the process
of clearing the site.
The ground a termite nest is usually treated with toxic chemicals and
powders should be mixed in the open air.
28
II. Foundation Excavation
A. The Top soil Excavation
Note: Do not use the soil to backfill holes that are created by excavating
roots in the topsoil.
The soil may settle to a different level in the over site concrete.
You should pack hard core tightly in the holes or use a weak
concrete mixture or filler. 29
B. Bulk Excavation
After the removal of the topsoil, there should be a firm sub soil that is
strong enough to support the over site concrete and building loads.
II. Dig down part the topsoil to the recommended level in the
sub soil.
III. Inspect the ground to check that the sub soil is firm and
continue digging if the ground is not firm.
30
Bulk Excavation Cont’d
The working can be done manually with:
Spades;
Shovels;
Pick axes;
Wheel barrows.
31
C. Trench Excavations
When to dig deeper into the sub soil to excavate trenches for
foundation, the depth of excavation for the trenches will be
indicated on the working drawings.
If you want to achieve more speed than you can use a back actor.
It is very important if the trenches are quit deeper.
32
33
D. Pit excavation
• It is a deep hole in the ground that gives access for
foundation placement.
34