Region of Waterloo Stage 1 Light Rail Transit Project: Execution Version
Region of Waterloo Stage 1 Light Rail Transit Project: Execution Version
Execution Version
Table of Contents
13.1 General ..................................................................................................................................... 13-1
13.2 Requirements ............................................................................................................................ 13-1
13.3 Work for VTAC ..................................................................................................................... 13-10
13.4 Verification Tests ................................................................................................................... 13-11
13.5 Acceptance ............................................................................................................................. 13-19
13.6 Pre-Substantial Completion Demonstration ........................................................................... 13-24
13.7 Certification ............................................................................................................................ 13-28
13.8 Operations Term and Maintenance and Rehabilitation Term Expiry Transition Procedures . 13-29
13.9 System Operations and Maintenance Personnel ..................................................................... 13-29
13.10 Personnel Policy Manual ........................................................................................................ 13-29
13.11 Qualifications ......................................................................................................................... 13-29
13.12 Uniforms ................................................................................................................................. 13-29
Execution Version
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
13.1 General
(a) This Article describes the requirements for components, equipment, and systems verifications and
tests, leading to and including Integrated Systems Tests, a Demonstrated System Operations Test
and a Maintainability Demonstration Test, which together, if successful, shall lead to the issuance
of the Substantial Completion Certificate for the Region of Waterloo Stage 1 Light Rail Transit
System. Issuance of the aforementioned Certificate is a condition precedent to the entering
revenue service operations. Also, this Article addresses the development, during the performance
of the Phase 1 Work, of plans to monitor the dependability of the Project during the Phase 2 Work
and tests and Final Acceptance of the total System by the Region.
(b) The presentation of specific verification, testing, acceptance and commissioning requirements
within this Article must not be construed to limit or modify in any way Project Co’s responsibility
to provide a holistic, comprehensive, and fully functional approach to verification, testing,
acceptance and commissioning responsibilities. Project Co may add to these requirements,
revised lexicon, combine and rearrange these requirements, or otherwise make modifications as
needed to enable Project Co to meet its overall responsibility to provide a holistic,
comprehensive, and fully functional approach to verification, testing, acceptance and
commissioning needed to successfully deliver the Stage 1 LRT Project. However, as a minimum,
the Verification, Testing, Acceptance and Commissioning Plan shall address every aspect of the
requirements cited in this Article and the rationale for all deviations or variances from any
requirement cited this Article must be fully described in the Verification, Testing, Acceptance and
Commissioning Plan and presented in Project Co’s submission.
13.2 Requirements
(a) General
(i) Project Co shall subject the complete LRT System to a comprehensive test program to
verify the design and performance characteristics and to determine compliance with safety
and dependability characteristics. The comprehensive test program shall include the
following elements: design conformance, flow charts, production conformance, installation,
qualitative and quantitative verification, and routine acceptance tests on all items and
integrated systems. Requirements concerning test plans, procedures and reports are subject
to review and approval by the Region.
(b) Verification, Test, Acceptance and Commissioning Plan
(i) Project Co shall prepare an outline Verification, Test, Acceptance and Commissioning Plan
("VTAC Plan") for the review of the Region as part of the Phase 1 submission.
(ii) The VTAC Plan shall be fully developed as a VTAC program as the work progresses for
use in Project Co's performance of the work as well as for incorporation as necessary into
construction documents. The VTAC Plan shall outline the methods and procedures to be
utilized to verify System compliance with the technical requirements of the Project
Agreement prior to attaining Revenue Ready status. The VTAC Plan shall be structured to
ensure a systematic, thorough evaluation of all individual system components, as well as
their integrated performance. This evaluation shall be accomplished through data
submittals, inspection, testing and demonstrations, as described herein.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-1
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(iii) The VTAC Plan schedules shall reflect consideration of verification constraints which may
normally be expected during certain hours of the day, such as work at street crossings
during peak traffic periods. The schedules shall reflect any work shifts which are outside
the normal work day of 8:00 a.m. to 5:00 p.m., Monday through Friday, resulting from
these considerations, and the VTAC Plan shall explain the need for the special work shifts.
(iv) The VTAC Plan shall also provide procedures for implementing corrective actions after
failed inspections, tests, or demonstrations and following up to ensure incorporation of
corrections into System design.
(v) The VTAC Plan shall contain adequate information to reflect the VTAC program content
and shall specifically incorporate a Product Improvement Verification Program (PIVP), a
Software Verification Program (SVP), an Integrated Systems Demonstration Program
(ISDP), a Maintainability Demonstration Test Plan (MDTP) and a Dependability
Demonstration Test (DDT) Program.
(vi) Project Co shall also prepare a Systems Assurance Monitoring Plan (SAMP). This plan
shall set forth Project Co's proposed methodology for measuring system assurance
parameters during the Operations Term and Maintenance and Rehabilitation Term.
(vii) The pre-final VTAC Plan shall be submitted to the Region for approval within 120 calendar
days after the issuance of the Phase 1, and the final VTAC Plan shall be submitted 30 days
after receipt of the Region’s comments and be updated thereafter, as may be required, but
no less frequent than every six months.
(c) VTAC Program
(i) VTAC Program Outline
A. Project Co shall prepare the Verification Program in a building-block manner:
identifying all design and performance requirements, assigning the requirement to
the appropriate verification effort(s) (e.g., component or assembly development,
subsystem/subassembly qualification or acceptance, installation, combined
subsystem, system acceptance, or initial operation) and define the method(s) to be
used to accomplish verification (e.g., test, analysis, similarity to an equivalent
application, simulation, or in the case of dimensional or cosmetic requirements,
inspection). As part of the VTAC Plan, Project Co shall develop a list of
verification and acceptance tests which defines the planned verification and
acceptance tests. When an identifiable block of hardware is subcontracted, it shall
be noted.
(ii) VTAC Program Categories
A The VTAC Program shall address, at a minimum, the following categories of
verification:
1. Subsystem design and performance verification (in-plant and field).
2. Component, assembly, and subsystem factory acceptance testing and post
delivery acceptance testing (in-plant and field).
3. Subsystem acceptance tests - qualitative and quantitative (field).
4. Subsystem interface verification (in-plant and field).
5. Integrated Systems Tests.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-2
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-3
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(ii) Post Installation Check-out Tests are normally conducted by the equipment installer to
ensure that their installation work is done in accordance with the installation design,
instructions, procedures and manuals.
(iii) Site Acceptance Tests will be performed after Post Installation Check-out Tests on the
selected Subsystem equipment to ensure that all functional, operational and safety
requirements are met. Powering up equipment normally occurs during the site acceptance
tests. Site acceptance tests are normally performed by Subsystem/equipment supplier under
supervision of the Subsystem design engineer.
(f) VTAC Program Numbering Scheme
(i) Project Co shall include in the VTAC Program a numbering scheme to identify verification
efforts at the major assembly level or above for both in-plant and field activities, including
installation verification. The numbering scheme shall present a logical identification of
verification activities by discipline, level of test, sequence of test to allow constraint
identification, category of test, (safety-critical, operation-critical, or non-critical) and
location of activity. The numbering scheme shall be utilized in plans, procedures, reports
and schedules produced by Project Co and Subcontractors.
(g) Product Improvement Verification Program (PIVP)
(i) Product improvement verification refers to the sequence of analyses, data submittals, and
witnessed subsystem and system level testing required to substantiate the performance,
reliability and safety of an authorized product improvement and thereby qualify it for use in
the Project.
(ii) Project Co's Submission shall have listed specific product improvements which Project Co
proposes to incorporate in the Project. Project Co, within 90 days after the issuance of the
Phase 1, shall submit for the approval of the Region a Product Improvement Verification
Plan covering each proposed product improvement. This Plan shall present an orderly
procedure to verify the performance, reliability, and safety of the improvements. It shall
include:
A. Critical milestones related to development of the product improvement and the final
decision to incorporate the improvement into the Project.
B. Design review meetings to review conceptual design and implementation.
C. Qualification tests at the manufacturer's facility, witnessed by the Region
representatives, which qualify the product improvement as an individual entity.
(These tests shall include specific pass/fail criteria.)
D. Demonstrations witnessed by the Region representatives, which verify performance
of the improved subsystem within the Project. (These tests shall include specific
pass/fail criteria.)
E. Analyses, calculations and drawings prepared by the item manufacturer for review
and comment where testing and/or demonstration is impractical or specifically
waived by the Region.
(iii) The above items A, B, C, D, and E shall be successfully completed and approved by the
Region prior to beginning fabrication of production hardware or materials, unless otherwise
authorized.
(h) Software Verification Program (SVP)
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-4
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(i) All software shall be subject to design, verification and configuration control requirements
equivalent to those imposed on system hardware. Software shall comply with Project Co's
approved Software Documentation Plan which must include the standards that will be
applied to software development and testing.
(ii) Design reviews for software shall be conducted in accordance with the provisions of the
Project Agreement. The algorithms, design and interface requirements, functional and
programming hierarchies, organization and interconnection of modules, flowcharts, internal
safeguards and checks, and debugging and modification procedures shall be presented.
This data shall demonstrate the capacity of the software to withstand input data anomalies
and to provide the necessary real time control under emergency and other abnormal
conditions.
(iii) The software shall be tested and verified on a digital or hybrid simulator prior to interfacing
with system hardware. All subsequent software modifications shall be developed off-line
and verified on the simulator prior to incorporation into the System. The test and
verification of the software shall confirm its security against unauthorized access or
modification.
(iv) Following the Final Design Review, configuration control for software shall be established
by Project Co. Thereafter, all changes and reasons for changes shall be identified and
approved prior to implementation.
(v) Integration of the software into the System and subsequent testing shall be conducted in
accordance with the VTAC Plan. This plan shall include the integration and test strategy
for each software hierarchy level, individual tests and schedules, sources of prerequisite
data for each test, provisions for controlled input data variations (representing noise, etc.),
and the facilities and interlocking hardware to be used.
(i) Integrated System Demonstration Program (ISDP)
(i) Project Co shall develop and implement an Integrated System Demonstration Program that
encompasses all verification efforts of Project Co, its Subcontractors and others to verify
that the System meets all requirements on or before the commencement of revenue service.
(ii) Qualification testing successfully performed as part of the Product Improvement
Verification Program shall be acceptable under the ISDP Program, in lieu of further testing.
However, all product improvements shall be subject to the demonstration requirements set
forth in the ISDP Program.
(iii) The Integrated Systems Demonstration Tests shall include all in-plant (proof of design, pre-
delivery acceptance, and special), field (post-delivery acceptance, installation, integrated
systems, pre-revenue startup including training, demonstrated service operation and
maintainability), and other Project Co and Region verification activities which are
necessary to confirm compliance with the design and performance requirements.
(iv) Specific test requirements shall be included in Project Co’s Technical Specifications and
these test requirements shall be utilized to ensure that all tests are set forth in a manner
which clearly demonstrates that system/subsystem tests were conducted in compliance with
all requirements before incorporation into the higher level integrated tests, now being
defined. Test methodology shall be designed to assure that each succeeding test builds on
previous, lower level, tests.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-5
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(v) The Integrated System Demonstration Program shall incorporate system operations
demonstrations and test demonstrations for maintainability and dependability.
(j) Maintainability Demonstration Test Program (MDTP)
(i) A Maintainability Demonstration Test shall be conducted on systems and/or subsystems
jointly selected by the Region and Project Co to verify that they meet the Technical
Provisions on or before the commencement of revenue service. It is anticipated that 30% of
the approved Lowest Line Replacement Unit (LLRU) shall be demonstrated. The Region
reserves the right of final selection of systems or subsystems or components to be tested.
The Maintainability Demonstration Test shall be conducted concurrently with the
Demonstrated System Operation Test. The Demonstrated System Operation Test and the
Maintainability Demonstration Test are discussed in Section 13.6 of this Article.
(k) Dependability Demonstration Test (DDT) Program
(i) A Dependability Demonstration Test shall be performed during revenue service operations
on the Stage 1 LRT Project through the completion of one year of revenue service. Project
Co shall plan this Dependability Demonstration Test, which is described in section 13.6 of
this Article, by coordinating requirements with the Region.
(l) System Assurance Monitoring Plan (SAMP)
(i) Project Co shall prepare and submit for the review and approval of the Region a SAMP not
later than 240 calendar days prior to the commencement of revenue service. This Plan
shall set forth Project Co's proposed methodology for the recording/logging of all
operating incidents and for collecting and analyzing data to measure system assurance
parameters during the Operations Term and Maintenance and Rehabilitation Term, and
how such data will be compared with the System Dependability Requirements. The
System Assurance Monitoring Plan shall include all data requirements, data sources, data
gathering techniques, software, procedures and instruments, and computational methods to
be used in recording actual system performance, and comparing it with specified
requirements.
(ii) At a minimum, the following elements shall be included in the SAMP:
A. All required data shall be available from standard maintenance and operation
records;
B. The Plan shall specifically address the disposition of service interruptions and/or
delays attributable to passenger actions;
C. The Plan shall provide that System Assurance Monitoring shall start at the onset of
revenue service of the Stage 1 LRT Project and shall continue for a one-year
period, with data being collected at all times that these services are in operation;
D. The Plan shall explain Project Co's proposed methods for improving the system's
performance, should such be necessary in order to meet the specified requirements;
and
E. The Plan shall set forth the content and format of the monthly System Assurance
Monitoring Report.
(iii) All operating incidents shall be automatically recorded by the System's Central Computer.
The use of software to generate operating performance reports is required. A manually
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-6
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
written CCF Operator's log shall also be maintained and used to assist with determining
exclusions and otherwise interpreting computer-generated data.
(m) Test Management
(i) Project Co. testing shall constitute a major portion of the continuing process of design
verification. The following paragraphs describe the necessary features of Project Co test
program.
(ii) Test Organization
A. Project Co shall identify its VTAC organization, including assigned
responsibilities, and shall be responsible for assuring that qualified personnel are
available for all test planning, scheduling, performance, analyses, review of data
and reporting efforts. Project Co's description of organizational responsibilities
shall include preparation of verification plans, procedures, reports; recording of test
data; review of test data; reporting and resolving test failures and anomalies; and
coordination of each identified test effort. Project Co’s test organization shall
reflect continuity with verifying engineering requirements and, at a minimum, shall
respond to engineering in resolution of technical test issues such as test failures and
retest requirements.
B. In addition, Project Co shall supply trained personnel in support of the Pre-
Substantial Completion Demonstration and other tests required by the Region.
(iii) Commissioning Coordinator
A. Project Co shall identify a Commissioning Coordinator who shall be responsible
for directing the efforts of Project Co's test organization. This individual shall not
have project management or site management responsibilities. The Commissioning
Coordinator shall be responsible for all aspects of the Verification Test and
Acceptance effort, including coordinating access to test locations, arranging for
support personnel from other Project Co functional areas and areas not under
Project Co authority, coordinating test effort with other functional area construction
and test activity, and providing overall monitoring of Project Co's test performance.
As Project Co testing expands to the field, Project Co’s Commissioning
Coordinator shall ensure that test management is available on site to perform the
single point contact functions with full authority to make and implement test
decisions.
(iv) Test Notification
A. All testing shall be reflected on current schedules. In addition, Project Co shall
notify the Region a minimum of 20 days prior to the commencement of factory
tests and field tests. Project Co shall identify the tests to be performed in the
VTAC Plan and indicate the notification to be applied. The Region, as part of the
plan approval process, will indicate any tests which shall require notification by a
different number of days.
(v) Test Access
A. The Region reserves the right of access to test activity for purposes of monitoring
Project Co's performance and observing test progress.
(vi) Test Responsibility
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-7
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
A. Project Co shall be responsible for all tests performed under the Project Agreement.
Project Co shall furnish all test instruments and other equipment and materials
necessary for performing all tests. Proof of test equipment calibration shall be
submitted to the Region upon request.
(vii) Rejection and Retesting
A. Failure of equipment to meet factory or field test specifications or ratings shall be
sufficient grounds for rejection of equipment. Rejected equipment shall be retested
after suitable modifications are performed.
(n) Test Equipment/Instrumentation
(i) Suitability/Calibration
A. Project Co shall be responsible for assuring that all test equipment and
instrumentation are available and suitable for the intended purpose.
(ii) Region Equipment
A. Project Co shall identify any equipment which is not under Project Co's control and
which is required to perform a verification activity on Region-furnished property.
The Region will arrange for the availability of the requested equipment, if so
needed, within a minimum of 30 calendar days notice from Project Co or such
longer advance notice as the Region may deem reasonable for the particular
request.
(o) Test Criticality
(i) Identification of Requirements
A. Each verification requirement in the VTAC Plan shall be assessed for its criticality
to system performance and safety and classified as Safety-Critical, Performance-
Critical, or Non-Critical.
(ii) Safety-Critical Design and Performance Requirements
A. Safety requirements (e.g., components, circuits, performance) shall be verified only
by test unless specific directions to the contrary are provided by the Region.
Project Co shall consider the use of analyses and similarity as means of
accomplishing verification where the identical equipment has been successfully
used under essentially identical conditions to that required in the Stage 1 LRT
Project. Testing is the desired method of verification; however, when a method
other than testing is used, it shall be applied no less stringently. The final analysis
and evidence of similarity to an equivalent application, including the applicable test
data or report, shall be provided as part of the verification report.
B. Equipment of which the failure could present a safety hazard shall be demonstrated
to comply with design and performance requirements by testing. Project Co shall
ensure demonstration of design limits and shall include simulations, where
necessary, to confirm redundant safety features. Where design limit verification is
not practical, Project Co shall address each case in the Integrated System
Demonstration Plan for the approval of the Region, providing detail justification for
testing to other than design limits.
(iii) Performance Critical Design and Performance Requirements
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-8
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
A. Equipment, of which the failure will cause system operational delays but will result
in no safety hazard, shall normally be demonstrated to comply with design and
performance requirements by testing. Analysis may be used to demonstrate
equipment life, provided that a minimum of 10,000 hours of demonstrated
operation under essentially identical operating environments has been
accomplished on another project and the test report and operational records are
available to substantiate the analysis or similarity contention.
(iv) Non-Critical Design and Performance Requirements
A. Equipment of which the failure will neither cause system operational delays nor
provide a safety hazard shall be demonstrated to comply with design and
performance requirements in a method acceptable to the Region.
(p) VTAC Reports
(i) Project Co shall provide formal reports of results of all verification activities to confirm
compliance with design and performance requirements as defined herein.
(ii) Interim Reports
A. Project Co shall prepare Interim Reports for tests which form a part of a distinct
equipment group but which can be assessed incrementally or before completion of
total equipment group tests. The Interim Report shall identify all failures and
corrective actions encountered in the course of the verification activity.
(iii) Summary Reports
A. When Project Co has completed the tests in a particular classification or group level
for a distinct equipment group (to be identified by Project Co in Integrated System
Verification Plan) and the test results satisfy the prerequisites for beginning tests at
the next classification or group level, Project Co shall submit a summary report
containing such test results to the Region for approval.
(iv) Equipment Failure and Incident Report
A. The Equipment Failure and Incident Report is intended to provide an audit trail of
failure areas experienced during testing. Project Co shall provide Discrepancy
Reports, in tabular form, documenting all equipment failures to the lowest level
replaceable part. The Equipment Failure and Incident Report shall be a composite
of sequentially numbered Discrepancy Reports numbered to allow identification of
equipment sub-elements and shall include all pertinent data regarding the failures.
The report shall be updated quarterly until start of field tests and then be maintained
current through completion of field tests, including the Dependability
Demonstration Test.
(v) System Assurance Monitoring Report
A. During the Operations Term and Maintenance and Rehabilitation Term for the
Stage 1 LRT Project, Project Co shall undertake the program of operational data
collection and analysis as required in the approved System Assurance Monitoring
Plan. These operational data are to prove the actual performance of the System in
revenue service and to verify required dependability and other system assurance
requirements. Project Co shall submit monthly System Assurance Monitoring
Reports to the Region for review and evaluation. The System Assurance
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-9
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-10
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-11
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(iv) For each test/verification contained in the VTAC Program, Project Co shall include the
following general information, where applicable
A. Name of test/reference number
B. Procedure, objective and scope
C. Special environmental requirements, if any
D. Sample size
E. Equipment, facilities, and personnel required
F. Step-by-step procedures for tests
G. Glossary of technical terms used in procedures
H. Estimated time required
I. Description of set-up
J. Data to be recorded (data sheet)
K. Pass/Fail criteria
L. Documentation required.
(v) Written Qualification Test Procedures and written Qualification Test Reports shall be
submitted by Project Co to the Region. In addition, Project Co shall notify the Region at
least thirty (30) days in advance of the date that it is anticipated the test will be conducted;
the Region shall be notified at least fourteen (14) days in advance of the actual date the test
is conducted. The Region shall have the right to witness any and all qualification tests.
(vi) Within thirty (30) days after the completion of each qualification test, the qualification test
data and results of the test shall be transmitted to the Region for review. The Region will
notify Project Co in writing that the test results are acceptable, acceptable as noted, or not
acceptable and the reason therefore. Any equipment found not to be in compliance with the
Project Agreement during a qualification test may be rejected by the Region.
(b) Tests of Materials and Subassemblies Used in the Construction of Fixed Facilities
(i) The testing of materials used in the construction of fixed facilities shall be conducted by
Project Co, supplier, or special Subcontractor to verify that the installed materials meet or
exceed the design requirements and the Project Agreement requirements.
(ii) Project Co shall perform field tests, non-destructive testing, and destructive testing as part
of the Quality Assurance Program to assure that Project Co’s design, subsequent
construction, and quality of skilled workers meet the Region’s satisfaction.
(c) Factory Test of Operating System Equipment
(i) All assemblies and all subsystems of the Operating System shall be tested in the assembly
plant prior to shipment to the site to check and establish proper individual operation. As a
minimum the subsystems and subsystem equipment identified in shall undergo factory
testing prior to shipping to the site. Prior notification to the Region of factory tests is not
required unless:
A. As a result of design review or other information, the Region requests to be
notified; or
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-12
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-13
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
5.3.1. All tests listed shall be performed. Dry-type distribution and/or power
transformers shall be tested in accordance with ANSI C57.12.01, paragraph 3 and
Table 7. One transformer of each type shall be tested in the "design" and "other"
test classifications. All transformers shall be tested in the "routine" test
classification.
(vii) CCF Equipment
A. Project Co shall establish the proper integrated operation of CCF prior to shipment
of the associated equipment. Tests shall include the computers, associated
input/output devices, peripherals, master and remote data communication devices
(including transmission elements, CCF Console, the System Standard Display, and
the Power Station Display), and the communications equipment. For the purposes
of these tests, interfaces with other subsystems (i.e., Train Control, power
distribution, vehicle, and/or communications) may be simulated. During these
tests, the subsystems software shall be fully exercised.
(viii) Maintenance Equipment
A. Project Co shall functionally test the integrated operation of all Train Control and
departure test equipment associated with the Maintenance and Storage Facility.
Other maintenance equipment and special tools that are essential to operations,
maintenance, and safety shall also be tested.
(ix) Fare Collection Equipment Interfaces
A. Project Co shall test the interfaces between the fare collection equipment, the
SCADA system and the intrusion detection devices within the fare collection
equipment to confirm proper operation and reporting.
(d) Fixed Facilities Tests and Inspection
(i) It is Project Co’s responsibility to ensure that materials and workmanship are in accordance
with the design documents and that the Region can perform a complete review of Project
Co’s work.
(ii) Project Co shall develop a Guidelines for Construction Inspection Manual detailing the
inspection requirements and reporting methods. Once accepted by the Region, the
Guidelines Manual shall be issued to Project Co's Inspectors and shall require, among other
things, an Inspector’s Daily Report to be completed for every day on which work is
performed.
(iii) Project Co shall develop a Resident Engineer’s Manual detailing the construction
monitoring requirements of the Resident Engineer (or equivalent position). Once accepted
by the Region, this Manual shall require the maintenance of a daily log of all construction
site activities and a Weekly Progress Report to include the following:
A. Report number, period covered, and title
B. Scheduled status
C. Percentage complete
D. Weather
E. Manpower and equipment
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-14
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-15
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-16
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-17
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
B. Static operating checks of the power distribution system shall consist of checking
resistance to ground, energizing the system, opening and closing all breakers,
checking all interlocks, and recording no-load voltage and current readings for all
valid power feed configurations.
C. Uninterruptible power supplies shall be checked to assure proper operations in
primary supply mode and battery supply mode. The capability to switch
automatically, without disruption, from primary source to battery source upon loss
of primary source shall be determined. Tests shall also assure the ability to transfer
manually, without disruption from battery source to primary source upon
restoration of the primary supply.
D. Project Co shall record line voltages, line currents, power, motor current, and speed
on vehicles with all auxiliaries on under the following operating conditions:
1. Normal Service loading for the ultimate-length train over each trackway
(round trip), with LRT Stop and service by all System power sources.
2. Normal Service loading for the ultimate-length train over each trackway
(round trip), with LRT Stops and service by one primary feeder with the
second primary feeder out of service.
E. These checks shall be repeated with all trackway related power turned on.
F. The data taken shall be correlated by LRT Stop and analyzed to determine power
factor and to verify power distribution system voltage regulation requirements.
Analysis shall show that the power distribution system will impose no restrictions
on ultimate train length, train operations or the operation of vehicle auxiliaries due
to poor voltage regulation.
G. In addition to the above, checks shall be conducted to show coordination and
proper operation of fault detection devices.
(x) LRT Stop Equipment
A. Project Co shall inspect and check the installation and operation of all LRT Stop
equipment, including fare vending equipment and ticket validators provided by
others, against approved installation drawings and instructions. All equipment shall
be energized and the control and operation shall be operated from associated local
control panels and from CCF. Control of all LRT Stop equipment shall be checked
for all modes of train operation.
(xi) Operations Maintenance and Storage Facility (OMSF) Equipment
A. Inspection and installation checkout of all OMSF equipment shall be performed by
Project Co using procedures, techniques, and acceptance criteria which are fully
compatible with the installation and checkout of corresponding main line
equipment; i.e., trackway and trackway-mounted equipment, Train Control
equipment, control consoles UPS equipment, communications equipment, and
power distribution equipment. All maintenance building equipment, furnishings,
and special tools and equipment shall be checked as ready for functional use. The
inventory of all such items, spare parts, and consumables shall be affirmed.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-18
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
13.5 Acceptance
(a) General Requirements
(i) This Article describes the methods and procedures by which the Fixed Facilities and the
installed and delivered Operating System will be verified to the Region by Project Co as
complying with the requirements of the Project Agreement, and thereafter accepted by the
Region. This Article describes the Region's guidelines for an acceptable systems
acceptance process. Project Co shall develop and execute its plan, making use of
acceptance processes shown to be effective on past projects. Project Co's process shall
achieve the objectives defined in this Article.
(ii) Project Co shall thoroughly verify each aspect of the System and equipment prior to
commencement of the acceptance test activities discussed below; such prior verification
shall be accomplished during the design review, product qualification testing, factory
testing, on-site integration tests and fixed facilities inspection and test.
(iii) Project Co shall advise the Region when the Fixed Facilities and Operating System are
ready for acceptance activities, which shall not occur until Project Co has completed all of
the on-site integration tests and corrected any deficiencies and failures. Project Co shall
provide all resources necessary for, and carry out all of, the compliance verification and
acceptance activities defined herein. The Region will witness and review the results of these
activities. Compliance verification and system acceptance will be accomplished on the
basis of the Region’s review and acceptance of the compliance verification and system
acceptance activities and documentation of Project Co.
(b) Verification and Acceptance Procedures
(i) Project Co shall prepare, and submit for acceptance by the Region, a list of the Fixed
Facilities and Operating System requirements for which Project Co shall show compliance
for acceptance purposes. Previously conducted tests and data submittals that have been
accepted by the Region may also be used to satisfy appropriate requirements.
(ii) Three methods of compliance verification and acceptance are indicated and defined as
follows:
A. Analysis - Project Co shall submit analysis information and data in a manner so as
not to impede the verification and acceptance process. Analyses provided by
Project Co during the design review process may, at the sole discretion of the
Region, be used for verification and acceptance purposes. At the time of the design
reviews, the Region will examine the design review material and, in its sole
discretion, determine its applicability for any verification and acceptance purposes.
B. Inspection - In cases where inspections are to serve as the basis for compliance
verification, Project Co shall prepare detailed Inspection Procedures and submit
these to the Region for review not later than thirty (30) days prior to the schedule
date of the inspection. The inspection Procedures shall identify each element for
which that inspection is to demonstrate compliance. Project Co shall conduct each
inspection in accordance with the Inspection Procedures reviewed by the Region;
no inspection shall be performed prior to obtaining the Region’s review and
approval of such Inspection Procedures. The results shall be documented in a
suitable Inspection Report clearly showing if the inspection passed or failed based
on the Pass/Fail Criteria shown in the procedure. Inspection reports shall be
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-19
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
submitted in accordance with this Article. The Region may witness any inspection
conducted for compliance verification purposes. Inspections performed by
permitting agencies are a valid form of compliance verification.
C. Test - Project Co shall prepare detailed procedures for all tests, and submit them to
the Region for review and acceptance not later than forty-five (45) days prior to the
scheduled date of the test. The Test Procedures shall identify each line item to be
tested to demonstrate compliance. Such reference shall be by line item
identification number and Article of the Project Agreement. Project Co shall
attempt to combine the performance verification tests of more than one item into
the same test sequence, thereby minimizing the number of separate tests. Project
Co shall conduct each test in accordance with the Test Procedure reviewed and
accepted by the Region, and no test shall be performed prior to obtaining the
Region’s acceptance of such Test Procedures. Project Co shall document the results
in a suitable Test Report containing test data in an easily interpretable form and
clearly showing if the test passed or failed based on the Pass/Fail Criteria shown in
the Test Procedure. The Region may witness any test conducted for verification
and acceptance purposes.
(c) Fixed Facilities Acceptance
(i) At its discretion, and upon written request from Project Co, the Region may perform in-
progress fixed facilities inspections on selected portions of the fixed facilities. At that time,
a punch list of any items to be completed or corrected shall be prepared. This inspection
shall not be construed as a prefinal fixed facilities inspection. Once the System is nearing
operational readiness, in Project Co’s opinion, it may request a prefinal fixed facilities
inspection. If this inspection is satisfactory to the Region, a punch list of any items to be
completed or corrected shall be prepared. After completing the punch list, Project Co shall
request in writing a final inspection of fixed facilities. Such request shall represent that (1)
the punch list items have been corrected; and (2) the facility is complete and ready for final
acceptance. If this inspection yields findings satisfactory to the Region, the Region will
accept the fixed facilities portion of the work.
(d) Operating System Acceptance
(i) The Region will accept the Operating System when all aspects of the Operating System
have been verified to comply with the requirements of the Project Agreement. As
previously presented, verification will be accomplished by analysis, inspection and testing;
as a consequence, verification (and therefore System acceptance) is a step-by-step process
which takes place throughout the life of the Project Agreement. Because of this, it is
necessary to establish a systematic, carefully documented process to monitor and record the
progress of verification and System acceptance. Such a systematic process is the purpose of
the Operating System Acceptance Plan.
(ii) As a means of implementing the compliance verification and System acceptance
requirements of this Article, Project Co shall develop an Operating System Acceptance Plan
including a preliminary list of the Analyses, Inspections and Tests that will be conducted by
Project Co. Within 120 days after the commencement of Phase 1, Project Co shall submit
this Operating System Acceptance Plan. The Region will provide comments to the
Operating System Acceptance Plan and provide them to Project Co within 60 days after
receipt of Project Co’s Plan.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-20
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(iii) Once the final Operating System Acceptance Plan is approved, it shall be Project Co’s
responsibility to identify and finalize the list of Analyses, Inspections and Tests that will be
conducted to satisfy the Plan. Analyses shall be submitted pursuant to the Design Review
procedures. For each Inspection and/or Test which Project Co determines is required to
satisfy the System Acceptance Plan, Project Co shall prepare an appropriate Inspection
Procedure or Test Procedure, and submit this Procedure for the Region’s prior review. The
final activities for acceptance of the Operating System shall be the Demonstrated Systems
Operations and Maintainability Demonstration Tests.
(e) Operating System Acceptance Plan
(i) Purpose and Philosophy
A. The purpose of this Operating System Acceptance Plan is to provide a means for
Project Co to demonstrate to the Region by tests and inspections that the Operating
System satisfies the requirements of the Project Agreement. The proposed plan has
been developed to maximize the efficiency and minimize the time required of the
Region for witnessing (and that required of Project Co for conducting) these
activities. The plan sets forth the specific acceptance activities which the Region
believes are the minimum necessary for Project Co to demonstrate Contract
compliance in general; however, each specific requirement will be individually
verified by the acceptance activities.
B. There will be requirements that may be implied to be verified because they are
embodied within or in support of a higher level requirement. However, acceptance
of such higher level requirements shall not relieve Project Co of its responsibilities
to meet all requirements, including any not specifically verified. The plan also
establishes the general sequence of activities.
(ii) Plan Description
A. Each activity shall be conducted in accordance with written procedures prepared by
Project Co and accepted by the Region prior to the start of that specific activity.
Activities will be grouped into the categories and a test sequencing will be provided
by Project Co. Therefore, certain activities shall be completed successfully as a
prerequisite for conducting other activities. The acceptance activities will be
conducted by category, with no activity being performed unless all of the activities
in the prerequisite categories have been successfully completed and a test report
submitted.
B. Test/Inspection Acceptance Categories
1. The purpose of the categories is to logically group activities and establish the
general sequence in which testing is to take place. The intent of the
requirement that these categories of activities be conducted in a specific
order is to minimize the likelihood of invalidating a previously conducted
acceptance activity by making a change to a part of the System in order to
successfully conduct another activity.
2. The categories developed by Project Co shall be identified by a code letter in
the lower right-hand corner. The sequence in which activities within each of
the categories are conducted may be determined by Project Co. Activities
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-21
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Exhibit 13.5-1
Test/Inspection Acceptance Activities Report
1.0 TITLE: Title of acceptance activity, including its identification code.
REFERENCE CONTRACT SECTION: The section number and title of the
2.0
Project Agreement provision which is addressed by the acceptance activity.
PREREQUISITE ACCEPTANCE ACTIVITIES: The acceptance activity
3.0 categories which must be successfully completed prior to conducting this
activity.
OBJECTIVES: The specific intent of the acceptance activity regarding the
4.0
referenced Project Agreement Article.
SAMPLE SIZE: The number of units (e.g., vehicles) required to be used in the
5.0
acceptance activity or the specific area involved (e.g., maintenance building).
ENVIRONMENTAL REQUIREMENTS: Any specific environment's
6.0 conditions required in order for the acceptance activity to demonstrate
conformance with the referenced technical requirement.
EQUIPMENT/FACILITY REQUIREMENTS: Any test equipment or special
7.0
facility needs of the acceptance activity.
PERSONNEL/SKILL REQUIREMENTS: The number of Project Co personnel
8.0 required to perform the acceptance activity, as well as the skill levels of the
individuals.
ESTIMATED TIME REQUIREMENT: The period of time required to conduct
9.0 each acceptance activity. If the activity is conducted on each of several units
(e.g., LRT Stops), the time required for each unit shall be given.
DATA TO BE RECORDED: The specific data which are necessary to show
compliance with the referenced Project Agreement requirement shall be listed, as
10.0
well as the means by which these are to be obtained. The specific method of
documentation shall also be identified.
PASS/FAIL CRITERIA: The specific limits within which the data identified in
11.0
10.0 must fall in order for the activity to be acceptable.
PROCEDURES: The detailed, step-by-step, description of the acceptance
activity. This will provide specific directions to the person(s) conducting the
12.0
activity, including operating instructions for test equipment and when to record
data.
COMMENTS: Narrative description of any occurrences or events that may have
13.0
an impact on personnel safety, equipment integrity or the validity of the data.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-22
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Exhibit 13.5-1
Test/Inspection Acceptance Activities Report
CONCLUSIONS: The results of the activity, including a formal test report
statement by Project Co as to whether the data satisfied the Pass/Fail criteria, any
14.0
open items must be identified and the signatures of the participants must be
provided.
3. Project Co will develop the details of format elements 1.0 through 12.0.
Project Co may cite a test procedure document reference in lieu of the actual
procedure. The detailed description of each acceptance activity must be
submitted to the Region not less than six (6) months prior to its being
conducted by Project Co.
4. Format elements 13.0 and 14.0 will be completed during the actual
acceptance activity. Both Project Co’s personnel conducting the activity and
the Region’s observer will be permitted to enter comments in item 13.0. The
conclusions in item 14.0 will be those of Project Co.
(iii) Schedule
A. The Operating System acceptance activities shall be scheduled and conducted as
per Project Co's Plan. Project Co shall develop the specific Operating System
Acceptance Schedule and submit it to the Region for its review and approval.
B. Project Co may propose to conduct a category of acceptance activities prior to the
completion of the System if all of the system elements related to the acceptance
category are complete and fully operational.
(iv) Region Involvement
A. Procedure
1. The following procedures shall be followed to permit Region involvement in
approving the procedures, and in witnessing and tracking the status of all
acceptance activities.
I. Project Co shall develop the required Acceptance Inspection/Test
Procedures for each of the activities in accordance with the required
format and submit them to the Region for its review and acceptance.
Project Co shall submit the Operating System Acceptance Schedule
during this time.
II. The Region will review the Acceptance Inspection/Test Procedures
for each activity submitted by Project Co. Submittals will be
evaluated based on the extent to which each one addresses the letter
and intent of the Project Agreement requirements. Procedures which
can satisfy the requirements will be approved. Those procedures
which would be acceptable if minor changes were made by Project Co
will be approved, conditional on those specific changes being
incorporated in the procedure. Procedures which have more
significant deficiencies will be given the status “not accepted," and
procedures which are totally deficient will be “rejected.” The Region
will give Project Co written notification of the acceptance status
(accepted, conditionally accepted, not accepted, or rejected) for each
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-23
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-24
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
from any System Acceptance or System Integration test results to ensure their
"workability".
(iii) Demonstrated System Operation – Stage 1 LRT
A. After completion of the Operating System Acceptance Tests, and as a prerequisite
of Certification of Substantial Completion for the Stage 1 LRT System, Project Co
shall conduct a full demonstration of the LRT services.
B. This demonstration shall be called the "Demonstrated System Operation – Stage 1
LRT System" and shall involve day-to-day operation of the System in accordance
with the Region-approved System Operations Plan. During the DSO, the System
shall be operated continuously (without interruption), as though in passenger
service (without passengers), in strict accordance with all operations and
maintenance policies and procedures, until the System Service Availability
specified in the Schedule 15-3 Article 3 Section 3.6 has been achieved over a
consecutive 5-day operating period. Furthermore, the "Demonstrated System
Operation - Stage 1 LRT System" shall include the demonstration of all routine and
emergency procedures associated with operation of the Stage 1 LRT System.
C. During Demonstrated System Operation, performance data shall be collected,
analyzed and presented to satisfy the Region that the Stage 1 LRT System is ready
for deployment in revenue service. It is required that the "start of revenue service"
levels of dependability presented in the Technical Provisions be achieved during
the DSO.
D. During the Demonstrated System Operation, the number and skills of personnel
involved in operation and maintenance of the System shall not exceed the number
and skills identified in Project Co's COM Staffing Plan for the Stage 1 LRT
System. This is exclusive of Project Co personnel required for demonstration
administration and data collection.
E. Within ten days of the completion of the DSO, Project Co shall prepare and submit
to the Region a formal Demonstrated System Operation Report, documenting the
results of all activities. This report shall also identify any changes deemed
necessary in operating and/or maintenance procedures, manuals, etc., as a result of
the demonstration. The Region shall accept or reject such report within ten days of
receipt. The issuance of the Certificate of Substantial Completion for the Stage 1
LRT System shall not occur until approval of such report by the Region.
F. If the Demonstrated System Operation reveals a failure to satisfy the requirements
of the Project Agreement and/or the approved VTAC Plan, Project Co shall correct
those items and/or aspects deemed unsatisfactory, and another Demonstrated
System Operation shall be conducted. The scope and duration of all subsequent
demonstrations will be as approved by the Region.
(b) Maintainability Demonstration Tests
(i) Project Co shall provide a Maintainability Demonstration Test Plan for the conduct of a
Maintainability Demonstration Test concurrently with the DSO, demonstrating the
maintainability of the systems/subsystems. The Region's approval of the Plan shall be a
condition to issuance of the Certificate of Substantial Completion for the Stage 1 LRT
System.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-25
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(ii) The Plan shall address separate Maintainability Demonstration Tests for the Stage 1 LRT
System services with each test being conducted concurrently with the DSO. The Plan shall
include the following:
A. A list of selected maintenance tasks to be demonstrated. These tasks shall be
limited to component or assembly removal and replacement.
B. Safety procedures appropriate for tasks selected.
C. Maintenance procedures to be followed.
D. Skill levels required to perform each task.
E. Equipment or special tools required.
(iii) The Maintainability Demonstration Tests will be monitored by the Region for validity of
procedures and conformance to Contract requirements.
(iv) Unless otherwise approved, all maintenance performed during maintainability
demonstrations shall be by Project Co maintenance personnel. Project Co-shall furnish
maintenance manuals, tools and test equipment to be used as a part of the maintainability
and reliability demonstration testing.
(c) Dependability Demonstration Test (DDT)
(i) Starting within 30 calendar days following the issuance of Phase 3 for the Stage 1 LRT
System, the Dependability Demonstration Test will be conducted for a period of one year
on these lines.
(ii) The Dependability Demonstration Test shall be planned and conducted by Project Co. All
equipment incidents shall be documented on an incident report form approved by the
Region. Completed incident report forms shall be submitted on a weekly basis. All testing
on the program shall be considered dependability testing for the purposes of incident
monitoring.
(iii) The Database Management Information Systems (DMIS) shall be fully functional during
the entire Dependability Demonstration Test. Each applicable function of the DMIS shall
be used to track the results of the Dependability Demonstration Test. The DMIS shall not
be considered for final approval prior to completion of the Dependability demonstration.
The DMIS shall contain the expected life cycle for each component and its design reliability
parameters.
(iv) All of the equipment on the Stage 1 LRT System shall be included in the demonstration
test. Any equipment downtime for preventive or corrective maintenance, in excess of two
hours per week, shall be deleted from the test time database where such time is determined
by a Region-chaired Review Committee to be the fault of Project Co. This Committee will
consist of Region personnel and technical specialist contractors engaged by the Region. A
final Dependability Demonstration Test Report shall be prepared and submitted by Project
Co for the Region approval no later than 30 days after the completion of the test.
(v) Notification and Data Collection
A. The Region shall be notified of the commencement date for the Dependability
Demonstration Test, in writing, at least 20 days prior to the start of this test.
B. Data Collection
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-26
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-27
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
intended for use during the Phase 3 Period shall be replaced at no cost to the Region if used
for such purposes.
13.7 Certification
(a) Acceptance of the Phase 2 Work by the Region shall be accomplished in two stages: Certification
of Substantial Completion and Final Completion.
(b) Substantial Completion for the Stage 1 LRT System will signify the end of the first stage of LRT
construction planned by the Region, completion of the Integrated Systems Tests, Commissioning
and the readiness of the Stage 1 LRT System to enter revenue service under Project Co's control.
(c) Phase 2 Final Completion shall occur upon satisfaction of all requirements. Upon the issuance of
the Certificate of Phase 2 Final Completion, Project Co shall have no obligation to perform any
additional Phase 2 work under the Project Agreement.
(d) The criteria for and procedures associated with issuance of the Certificate of Substantial
Completion and the Certificate of Phase 2 Final Completion are presented in this Article.
(e) Certificates of Substantial Completion
(i) Certificate of Substantial Completion – Stage 1 LRT System
A. The Region will provide Project Co with a Certificate of Substantial Completion
for the Stage 1 LRT System when the following requirements are satisfactorily met:
1. Demonstration that the Project Agreement prerequisites for revenue
operation has been met during the Demonstrated System Operations Test and
the Maintainability Demonstration Test, and submittal and acceptance by the
Region of the reports related thereto;
2. Successful completion of the Integrated System Demonstration Program
(ISDP), demonstrating the System's conformance with the Project
Agreement;
3. The approval by the Region of the System Assurance Monitoring Plan for
documentation and incorporation of dependability/maintainability changes
and monitoring of system dependability growth during the Phase 3 Period;
4. Demonstration by Project Co that all of Project Co's responsibilities have
been substantially completed and/or successfully performed; and
5. The Region approval of:
I. Operations and Maintenance Plans and Manuals
II. Training Plans and Manuals.
B. Along with the Certificate of Substantial Completion for Stage 1 LRT System the
Region will provide Project Co with a punch list of items to be repaired or
corrected.
(f) Phase 2 Final Completion
(i) The Region will provide Project Co with a Certificate of Phase 2 Final Completion for the
Project when the following additional requirements are met:
A. Verification of meeting or exceeding the dependability System Service availability
requirements defined in the Project Agreement;
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-28
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
B. Correction/repair of all of the punch list items and all other construction, systems,
warranty items and deficiencies;
C. Submittal and acceptance of the "as-built" documentation; and
D. Submittal of revisions and approval of all of Project Co's Phase 3 Period Operations
and Maintenance Plans and Manuals.
13.8 System Operations and Maintenance Personnel
(a) During Phase 2, Project Co shall hire and provide training for all personnel who will operate and
maintain the System at the commencement of the 3 Period.
13.9 Personnel Policy Manual
(a) Project Co.’s Phase 2 Work shall include the preparation of the Phase 3 Staffing Plan, including an
organization chart and job descriptions. Project Co shall prepare and submit a Personnel Policy
Manual, for the hiring, promotion, discipline and dismissal of staff, that complies with applicable
Governmental rules, including all anti-discrimination provisions. Following the Region's approval
of this Personnel Policy Manual and absent any reason(s) to the contrary, applicants may be
interviewed and hired.
13.10 Qualifications
(a) The Personnel Policy Manual shall require pre-employment substance/drug screening of all
applicants for employment in safety-related positions. Such testing, as a minimum, shall satisfy the
requirements of the Region’s regulated drug testing protocol
(b) Project Co shall retain the records of all successful applications for employment, together with
verification of the references. The Region reserves the right to audit these records in accordance
with the Project Agreement.
(c) The education and experience of personnel employed shall be appropriate for the duties they shall
be required to fulfill, and such personnel shall be familiar with the general objectives and
requirements of their job assignments at the time they are hired. Project Co shall define skill levels
required for participation in each level of the training program.
13.11 Uniforms
(a) Project Co. shall furnish each employee who will interface with the public appropriate uniforms, the
colors and styling of which shall be approved by the Region. Later, during the Phase 3, these
uniforms shall be worn by said employees at all times while on duty.
13.12 Training of System Operations and Maintenance Personnel
(a) Project Co. shall provide training for all personnel who will operate and maintain the System during
Phase 3. The training shall start at such a time to ensure all operations and maintenance personnel
required for System Demonstration Tests are fully trained prior to the start of the System
Demonstration Tests.
(b) If so requested by the Region, Project Co shall include up to six (6) Region-designated personnel in
the training classes. As part of the System Safety and Security Program, Project Co shall provide
instruction for up to 10 Region and/or other agencies' fire, safety and security personnel. This
training shall provide an overview of System elements and operations, describe the features and
facilities available to emergency response personnel, and address applicable operation safety
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-29
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
procedures. It shall also address the proper use of equipment specific to the System that shall be
used in emergencies by emergency responders. In addition, training shall include the subjects listed
in the Rule Book.
(c) Project Co. shall provide all instructors, literature, and equipment necessary to train personnel.
Project Co shall provide sufficient classroom and on-the-job training for operations and
maintenance personnel to insure their competence in operating and maintaining the System.
Classrooms shall be provided by Project Co. Training on the actual System equipment and/or the
spare equipment will be permitted; however, such use shall not interfere with the pre-revenue tests
and demonstrations of the System.
(d) Project Co. shall have a testing program whereby personnel within a specific job classification are
tested for proficiency within that job classification. With concurrence by the Region, certain job
classifications may be exempted from such testing. Personnel shall pass the testing program
appropriate to their positions prior to assuming these positions on a full-time basis. Prior to
initiation of passenger service, Project Co shall provide the Region with the quantitative results of
all examinations administered to the trainees during and upon completion of the training program.
The results of these tests shall be sufficient for Project Co and the Region to evaluate the
competence of a trainee for his/her specific assignment in the operation and/or maintenance of the
System.
(e) Training Program Plan
(i) Project Co. shall develop a Training Program Plan responsive in all respects to the Project
Agreement. The plan shall provide for:
A. Materials: Student and instructor materials shall be developed, including course
outlines and objectives, lesson plans, training aids, and student manuals. All of
these materials shall become the property of the Region at the conclusion of the
training program.
B. Schedules: Training schedules shall include dates, location, and equipment
requirements of each course to be presented. Project Co shall have all training
completed before the start date of the pre-revenue service test program that is
required to complete the pre-revenue service tests. Project Co shall recognize that
some on-the-job training shall be necessary.
C. Training Presentation: Supervisory, operations, and maintenance personnel shall
receive training. Such training shall be sufficient to ensure the transfer of all
System-imposed knowledge and skills necessary to fulfill the duties required by the
function of said personnel.
D. Continuing Training: Project Co shall provide the Region an electronic copy of all
subject matter covered in the training program, to expedite the training for
employees hired after the Phase 3 has expired. Project Co shall furnish a complete
synopsis of subject matter for review, in accordance with Schedule 10 – Review
Procedures.. The Region may request that selected training sessions be recorded,
and Project Co shall accommodate such requests.
(f) Training Program Courses
(i) Types of Courses: Project Co shall develop courses of instruction in System
familiarization, operation, and maintenance.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-30
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-31
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
(i) Documentation
(i) Project Co shall prepare and deliver to the Region the following:
A. Training Program Plan
1. A Training Program Plan shall be prepared in narrative form and shall be
supported by such tables, charts, schedules, and graphs as are necessary to
fully convey and describe Project Co's plan for accomplishing the training
set forth herein. It shall be subject to the Region's approval. The Training
Program Plan shall include resumes and qualifications of key instructors and
Project Co's training staff, for the approval of the Region. The Training
Program Plan shall provide complete documentation to substantiate
employee certification.
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-32
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.
Schedule 15-2 Article 13
The Region of Waterloo Stage 1 Light Rail Project Execution Version
Confidential – Economic Interests of The Region of Waterloo and Ontario Infrastructure and Page 13-33
Lands Corporation
This document must not be copied or reproduced in any manner without the written permission of The Region of Waterloo and Ontario
Infrastructure and Lands Corporation. Queen’s Printer for Ontario © Copyright 2013.