Hollowcore Guide v7 Book
Hollowcore Guide v7 Book
Precast Concrete
Building Concepts
Written by Barry Crisp
2
DESIGN CONSIDERATIONS AND PROCESS 7
2.1 Design considerations 7
2.2 Design considerations in moderate seismic areas 12
2.3 Design process 16
3
PRECAST BUILDING CONCEPTS 19
3.1 General 19
3.2 Structural systems 20
3.3 Applications of precast structural systems 25
4
PRECAST STRUCTURAL ELEMENTS 31
4.1 General 31
4.2 Walls 32
4.3 Columns 38
4.4 Beams 41
4.5 Floor slabs 46
4.6 Balconies 52
4.7 Stairs 54
5
STRUCTURAL STABILITY 55
5.1 General 55
5.2 Un-braced Precast Structures 56
5.3 Braced precast structures 58
5.4 Floor plate action 61
5.5 Connections 64
5.6 Tie systems 69
5.7 Design for accidental actions 73
6
BRACED WALL STRUCTURES 81
6.1 General 81
6.2 Design Concepts 82
6.3 Connection details 85
7
SKELETAL STRUCTURES 91
7.1 General 91
7.2 Design concepts 92
7.3 Connection details 95
8
LOADBEARING WALL STRUCTURES 107
8.1 General 107
8.2 Design concepts 108
8.3 Connection Details 111
8.4 Design of welded plate connections 118
9
MIXED STRUCTURES 121
9.1 General 121
9.2 Design concepts 122
10
FIRE RESISTANCE 127
10.1 General 127
10.2 Basic requirements 129
10.3 Fire actions 130
10.4 Global structural analysis 134
10.5 Member analysis 135
10.6 Fire resistance of structural connections 139
10.7 Establishing FRP by testing 142
10.8 Conclusion 142
11
DEMOLITION AND DISMANTLING 143
11.1 General 143
11.2 Structural assessment for demolition 144
11.3 Safe design for demolition 145
11.4 Demolition or dismantling process 146
12
REFERENCES & LITERATURE 147
12.1 References 147
12.2 Literature 149
1 CHARACTERISTICS OF
PRECAST CONCRETE
The main characteristic of precast concrete buildings is Continuity of reinforcement through the joints results in
they comprise a series of discrete elements assembled bending and torsional moments, along with shear and
and connected on site to form a complete structure. axial forces being distributed throughout the structure
Connection between elements is critical and continuity by frame action.
between elements can be difficult to achieve. Realisation
of a three-dimensional framework is seldom applied A common misconception is that precast concrete has
unless specifically required. Stability can be provided by little or no flexibility in design. Modern precast concrete
in-plane stiffness of shear walls, braced frames, restraint buildings can be designed safely and economically,
of columns in foundations, diagonal bracing, floor and with a variety of plans (figure 1.1) and with considerable
roof diaphragms, or combinations of the above systems. variation in the treatment of the elevations (figure 1.2).
Technically there is no limit to the building height that
Conversely cast in-situ concrete structures are monolithic can be constructed in precast concrete; the limitation is
and behave as three-dimensional frameworks. generally one of logistics and material handling on site.
Figure 1.1 Irregular Layouts. complex plans with simple framing Figure 1.2 Complex elevations in precast concrete
• Factory made products SCC needs no or minimal vibration and thus minimises
The only way to industrialize the construction process labour requirements and creates advantages such as
is to shift the work from the site to permanent low noise level during casting, less mould pressure,
factories. Factory production means rational and rapid casting, easy casting when using dense
efficient manufacturing processes under controlled reinforcement or with thin or complicated cross-
conditions, skilled workers, repetition of actions, sections, less air pores at the surface and easy pumping.
quality surveillance, etc. Automation of production
is an area offering significant advantages. Examples High strength concrete with cylinder strength greater
already exist in Europe where preparation of the than 65MPa is common in prefabrication and most
reinforcement, assembly of moulds, concrete casting, factories are using it daily. The major benefit for
surface finishing and de-moulding is fully automated. building structures concerns the improved structural
efficiency enabling more slender elements and
• Optimum use of materials optimum use of materials.
Prefabrication has much greater potential for economy,
structural performance and durability than cast in- • Prestressing
situ construction because of the higher potential to Pre-tensioning of steel tendons, either small diameter
optimise materials in individual elements. Additives wires or compound helical strands, are often applied
and admixtures are used in the mix design to obtain in precasting due to the ability to use long-line
the specific mechanical performances needed for prestressing beds and tendons anchored by bond.
each product. Casting and compaction of the concrete This technique gives not only all the construction
is performed under controlled working conditions advantages of prestressed concrete, but also improves
with optimum equipment. The water content can be economy at manufacture because of the low labour
reduced to a minimum, and compaction and curing are input and the absence of expensive anchorage devices
done in controlled environments. and duct grouting required in post-tensioning.
Safe design means that early in the design process of Generally in all cases the objective of the design team
a building, control measures need to be implemented is to develop a structural system characterized by
to identify workplace hazards during the construction structural simplicity and geometric clarity, providing
and life of the building and to eliminate or minimise, short and direct paths for the transmission of the vertical
so far as is reasonably practicable, the risks associated and horizontal actions, thus minimizing uncertainties
with those hazards. Managing this risk is a systematic concerning the modelling, analysis, dimensioning and
process that is usually easier and cheaper to achieve detailing for the construction. This can be obtained by;
at the design stage than trying to make changes later • Optimising the spans for each element.
when the hazards become real risks in the workplace. • Minimising the number of building elements.
• Using simple lateral restraining systems.
Precast concrete construction can be a high risk • Providing for structural integrity.
process that requires serious consideration of these
issues by all relevant people involved in the work, Structural simplicity in turn, is best characterized
including the principal contractor, designers, engineers, by uniformity and regularity in the geometrical
prefabricators, and erectors. configuration of the structural system in plan and
elevation. Load transfer should be avoided or otherwise
Safe design starts at the concept design stage when limited and if required specially treated at one level.
consideration needs to be given to materials, methods
of construction, maintenance and eventual demolition
or dismantling. This topic is discussed in detail in the
2.1.3 Modulation
Code of Practice, Safe Design of Structures [38] and in Although modulation, designing the building on a
AS3850. [35] rigid module, can be an economic factor in designing
and constructing buildings, it should not be the over-
riding factor. The precasting industry in Australia has
developed in response to architectural requirements
and few buildings are constructed to a rigid module.
Grid layouts and dimensions are usually based on site
limitations or car park dimensions.
Figure 2.4 Building examples of soft storey ground floors and soft storey upper floors to be avoided
Figure 2.5 Shear wall configurations to be avoided due to the fact that they are not symmetrical in plan with respect to two orthogonal axes.
Figure 2.6 Building example with column failure due to spandrel infills
9m to 16m
In practice most buildings comprise a combination of Detailed information on braced wall structures is given
the above basic structural types and are completed by in Chapter 6.
using a range of precast elements for the construction
of walls, floors, roofs and façades. Similar concepts can be used on residential buildings
as shown in figure 3.3 where loadbearing wall panels
The selection of a structure for a given project is support a metal framed roof structure which in turn is
based on a number of parameters related to the type, braced to provide lateral stability. The slab-on-ground
occupancy, the needed spans and grids, the applied is often poured and tied into the walls after erection of
solution for the façades, the required fire resistance, the structure.
available lifting capacity during erection, etc. Each of
the above parameters will have an optimum structural
solution and each need to be weighed against the others
in making the final choice.
Figure 3.4 Cantilevered precast skeletal frame Figure 3.5 Braced precast skeletal frame
Precast bearing wall systems are mostly used in residential Maintaining stability of the structure during erection
construction, both for low and high-rise apartments. of the precast is important and erection design usually
Indeed, the ideal solution on apartments is to build free requires all walls to be braced during construction.
open spaces between the load-bearing perimeter walls
of each apartment and to use light partition walls for the Detailed information on loadbearing wall structures is
internal layout. (Fig 3.6) This offers the possibility to later given in Chapter 8
change the interior layout without major costs.
Figure 3.6 Low-rise apartment building with load-bearing Figure 3.7 High-rise apartment building with loadbearing walls
cross-walls and corridor walls and precast floors
Figure 3.10 Hybrid construction, steel frame roof, timber floors and precast walls
For the longer floor spans, hollow core slabs are the most
suited floor type because of the large span capacity,
slender floor thickness and ease of construction. There
are a range of slab thicknesses available for different
spans but it is common to have hollow core units of up
to 400 mm thickness with a design capacity of 5kPa or
more on spans up to about 16 metres.
Figure 3.13 Hotel building with open lower levels and Figure 3.14 Hospital building
loadbearing upper levels
Precast wall elements can be either single or multi- Where high thermal performance is required insulated
storey height. The thickness is a function of requirements sandwich panels are becoming common. These have
related to structural capacity, stability, acoustic generally comprised an inner structural layer tied to an
insulation, fire resistance of the wall, the equipment outer non-structural veneer with insulation between but
Figure 4.3 Design cases and load model for braced wall design
es
efl
4.2.4 Manufacture
Most precast walls are manufactured on horizontal steel
tables or casting beds. Some manufacturers use tilting
tables to allow early de-moulding but with modern
concrete mix designs, early strengths are usually
sufficient to allow lifting on a one day casting cycle
without needing to tilt the beds. Battery moulds are
rare in Australia and are only used where considerable
repetition in panel size and shape occur.
Figure 4.7 Load-bearing spandrel beams
For reasons of stability at de-moulding and handling,
minimum dimensions of lintels and mullions between
Non load-bearing façades fulfil only an enclosing windows and at panel edges are required. Figure
function. The elements are either individually fixed to 4.8 gives an example of recommended dimensions
the structure of the building or they can be supported for typical 150mm thick panels. On irregular shaped
from the ground or a load transfer element. In the first panels or where minimum dimensions are structurally
case the structure of the building supports the self- insufficient temporary strong-backs can be used to
weight of the cladding elements at each level. In the stiffen the panel to allow lifting, transport and erection.
second case the elements are stacked vertically and are
only anchored horizontally to the structure. In principle, Service ducts and electrical conduits can be incorporated
the shape of the elements can be designed without into the panel prior to casting. The dimensions for door
any restriction. Non load-bearing façade elements are openings and windows are generally unlimited and door
described in detail in the Precast Concrete Handbook [2]. and window frames are often cast-in.
200 200
200 200
300
200 200 200
300
4.2.5 Erection
This document is not intended to cover the transport and
erection of elements. These aspects are covered in detail
by State and Commonwealth authorities. Many aspects
of erection are also covered by statutory requirements
under OH&S regulations [3] [35]. Reference should be
made to these documents to ensure compliance.
Precast columns are mainly used in frame structures in Figure 4.10 Multi-level columns with corbels
conjunction with precast beams but can also be used
with insitu concrete floors in hybrid structures or with
wall cladding panels in braced wall structures. 4.3.2 Design concepts
The design of a precast column is the same as that for an
The column size is function of requirements related
insitu column. They are typically designed in accordance
to structural capacity, stability, and fire resistance but
with Section 10 of AS3600 for applied axial loads and
generally a minimum dimension of 400mm is adopted
bending moments that are derived from analysis.
to accommodate column to beam connections. This
minimum dimension can be obtained by providing
Where precast columns are used as part of a skeletal
corbels on smaller or rectangular columns.
frame with pinned connections, the structure is subject
to staged loading and partial continuity. It is therefore
Columns may be of constant dimension for the full height
difficult to establish the continuity and eccentrically
of the building or stepped back at intermediate levels
induced bending moments without carrying out a
to satisfy structural and architectural requirements. As
complex non-linear analysis. A non-linear analysis
b) End column Because of their robustness and the use of high strength
concrete, columns can be easily manufactured on a daily
To establish the upper bound eccentricity it is generally casting cycle.
assumed that the beam reaction is applied at a distance
of one third of the support length from the inner face of
the column.
4.4.3 Manufacture
Most beams are designed as pre-tensioned and therefore
manufactured on a long line casting bed. Bed lengths of
40-60 metres are common and usually allow for two or
three standard beam profiles and widths, and a range of
depths and ledge heights.
typically loaded slabs. Where it is critical, the shear units should be connected together to form a single
capacity can be increased by filling the cores at the ends entity by a tying system.
of the slab with concrete from the topping screed.
Most precast floor systems used in Australia are provided
In most uses hollowcore slabs are designed as composite with structural toppings and these can be reinforced and
with a reinforced concrete topping. The topping is kept used to tie the individual elements together. In the rare
to about 60mm thick, the minimum required to contain cases where no structural topping is used the individual
the topping reinforcement. Thicker toppings do not elements need to be tied together by other methods
necessarily increase the capacity of the composite such as welded connection plates or strategically placed
section and on longer spans may actually reduce reinforcement in the joints and across the ends of the
capacity. Surface roughness and surface preparation elements to prevent lateral displacement and loss of
is important in ensuring full composite action occurs. integrity. This is discussed in greater detail in Chapter 5,
Roughness is specified in AS3600 [7] and at the time Structural Stability
of pouring the screed the surface should be ‘surface
saturated dry’, damp but with no water pooling. 4.5.4.2 Diaphragm action
Hollowcore slabs
Applied load + topping screed
For hollowcore slabs the treatment depends on the An alternative to the above is to cantilever the precast
direction of span of the floor relative to the cantilever. floor over the loadbearing wall to form the balcony. The
Figure 4.29 shows a typical solution where the floor disadvantages with this solution are in accommodating
spans at right angles to the cantilever span. This the set-down in the floor and the usual need to erect
frequently occurs on apartment buildings comprising formwork on the perimeter of the building to provide an
loadbearing cross walls between apartments and non- appropriate finish on the face of the balcony.
bearing façade walls. A precast floor element that
incorporates the cantilevered balcony spans between
the loadbearing cross walls. The cantilevered portion is
generally pre-finished and the element is tied into the
floor by reinforcement in the screed.
Floor
Precast floor & screed
& screed
Non-bearing
wall line
Cantilevered
balcony unit
Cantilevered
Loadbearing wall balcony
Section
Plan
Figure 4.29 Floor element incorporating cantilevered balcony
Precast floor
& screed
Cantilevered balcony
Erect onto falsework
Load bearing wall
Section
Figure 4.31 Combined landing, flight and half-landing elements Figure 4.32 Spiral and self-supporting stair units
In addition two design stages need to be considered with 5.4.2 Shear transfer between elements 62
precast concrete. Firstly, the temporary stability during 5.4.3 Chord forces 62
construction and secondly the permanent stability, which 5.4.4 Movement joints 63
includes connecting the individual elements together 5.5 Connections 64
and generating horizontal diaphragm action to transfer
5.5.1 General 64
horizontal loading from the horizontal elements to
the vertical bracing element or roof and thus into the 5.5.2 Strength 64
foundations. 5.5.3 Volume change 65
5.5.4 Deformation 65
Provision of structural stability can be achieved by using 5.5.5 Ductility 65
the following concepts:
5.5.6 Durability 65
• Un-braced (or sway) structures, where stability is
provided by the cantilever action of the columns or 5.5.7 Dimensional tolerances 65
walls in the structure or by two dimensional frame 5.5.8 Fire resistance 66
action. 5.5.9 Basic force transfer mechanisms 66
• Braced structures, where resistance against horizontal 5.6 Tie systems 69
actions is provided by shear walls, lift shafts and
5.6.1 Types of ties 70
central cores that provide horizontal support to the
remaining parts of the structure. 5.6.2 Ties in structural toppings 72
5.7 Design for accidental actions 73
In conjunction with the above concepts it is important to: 5.7.1 Introduction 73
• Ensure that horizontal actions are distributed evenly 5.7.2 Indirect design method 74
across the structure by designing the floor or roof
5.7.3 Alternative load path method 76
plates to act as diaphragms.
• Provide connections or ties between the individual 5.7.4 Specific load resistance method 79
precast elements to ensure that the assembled 5.7.5 Risk elimination 79
precast elements act as a coherent structure.
• Ensure that the structure can retain its integrity under
accidental actions.
Shear force
Chord force
Shear wall
5.4.2 Shear transfer between floor units but Section 8 provides some guidelines. It
is recommended that a conservative value be adopted.
elements Where used without a topping screed the hollow core
Floor diaphragms with a topping screed are generally elements must be restrained from moving apart.
designed on the basis that the precast concrete floor
elements act compositely with the in-situ reinforced Appropriate detailing and care in connection design
concrete topping to prevent buckling while the shear is necessary to ensure that diaphragm forces can be
across joints is assumed to be carried entirely by the transferred to the stabilising elements. Connections that
topping. transfer shear from the diaphragm to the shear walls or
other lateral force resisting elements should be analysed
Floor diaphragms without topping screeds are not in the same manner as the connections between adjacent
common in Australia and when used are generally on one precast elements. Care must be exercised, particularly
or two storied residential buildings with relatively short where there are openings adjacent to shear walls, or to
floor spans. In these cases the shear transfer between other elements which provide stability
elements is accomplished by shear friction, aggregate
interlock or dowel action between adjacent elements. The weak link in diaphragm action is always the
To resist these forces it is necessary that the units be connection between diaphragm and shear resisting
tied together so that shear forces can be transferred elements.
across the joints even when they are cracked.
5.4.3 Chord forces
Because of their edge profile and the grouting of the
longitudinal joints, floors made of hollow core units can Chord forces in the diaphragm are calculated from
be used to act as a diaphragm with or without a topping analysis as a deep beam or by a strut and tie model.
screed. The shear stress in the joints should be calculated Peripheral tie reinforcement is calculated and placed
using a section depth 30mm less than the overall precast as appropriate round the perimeter of the diaphragm
depth to allow for the fact that the bottom of the joint to resist these forces. As with any beam, this tie
does not fill with grout and to account for differential reinforcement needs to be lapped and anchored so that
camber of the elements. AS3600 does not specifically the forces are transferred to the shear walls or other
cover interface shear capacity in joints between precast lateral force resisting elements.
In practice many solutions allow some relative Ductility can be provided by confinement reinforcement
displacement to occur. For example, elastic deformations in concrete connections or by anchor bars in steel
of structural members or connection fixings will relieve connections. Methods of detailing the confinement
restraint forces. reinforcement required to develop plastic hinges for
ductility in concrete connections is discussed in detail in
In some connections it is not only the force transfer texts on seismic design. [37]
capacity of the connections that is important but also
the stiffness as measured by the load-displacement In connections using steel fixings the anchor bars are the
relationship and the deformability. This is particularly ductile components. To ensure ductile behaviour the other
important in connections that are required to form a components, mainly the welded fixings, should be designed
coherent structure from a series of individual elements. to have higher ultimate capacity than the anchorage bars.
In this case, deformability can lead to a loss of stiffness, The bar should project into the uncracked zone where it is
particularly under seismic loading. properly anchored. Transverse confinement reinforcement
should also be provided particularly close to edges and in
5.5.4 Deformation thin sections.
In the case of walls and floors that have an important 5.5.9.3 Dowel action of bars
separating function with regard to thermal insulation
and fire penetration the connections at wall joints and Transfer of horizontal actions from one element to
floors should be designed to prevent the passage of another can be provided in precast structures by
flames and hot gases. means of dowel action. Depending on the strength and
dimension of the steel bar and the position of the bar
More information on the design of fire resistant relative to the element boundaries, several failure modes
structures is given in Chapter 10. are possible. A weak bar in a strong concrete element
might fail in shear of the bar itself. A strong steel bar in
a weak concrete element or placed with small concrete
5.5.9 Basic force transfer cover might result in concrete bearing failure or splitting
mechanisms of the concrete. However, when the bar is placed in
well confined concrete with adequate concrete cover
Structural connections are usually composed of a
or when the splitting effects are controlled by properly
number of components and fixings that assure the
designed confinement reinforcement, the dowel pin will
transfer of forces through the whole connection. The
normally fail in bending by formation of a plastic hinge
transfer of forces from one component to another one,
in the steel bar at some distance above the joint face.
or within a connection as a whole, is based on a number
of principles as outlined below.
Connections can be formed by welding directly to Post-tensioning can be used in segmental construction
protruding steel fixings, for example reinforcement bars and in shear walls of tall buildings. Ducts are installed
that overlap into an insitu infill. The disadvantage of this into the units, and after erection, the pre-stressing cables
is lack of tolerance, particularly if the lapping bars have or bars are placed in the ducts and post-tensioned. The
a short projection length. An alternative is to use an joints between the units are able to resist tension and
intermediate steel section, which is used as a link and shear forces.
welded between the protruding fixings.
lW
lW
To satisfy the deemed to comply requirements of BS These ties are used in skeletal structures and loadbearing
8110 [34] ties should be provided as shown in Figure wall structures to tie the edge beams or perimeter walls
5.17. These requirements are based on fib Bulletin 74, into the floor system. They should be anchored into the
Planning and design handbook on precast building structural topping or the precast floor elements and not
structures. [18] into the joints between the elements.
5.6.1.1 Internal ties (types 1 & 2) The edge ties and wall ties should be capable of resisting
the ultimate tensile force equal to;
These ties are also known as longitudinal and transverse Ftie = 20kN/m along length of edge or wall.
ties. They are placed across the ends as well as
perpendicular to the span of the floor elements. Internal In skeletal structures these ties can be the torsion ties
ties may, in whole or in part, be spread evenly in the that are provided to resist torsion on the edge beam.
floor or may be grouped at or in the joints, tie-beams,
along floor beams, walls or other appropriate positions. 5.6.1.3 Peripheral ties (type 5)
Where a structural topping screed is provided the screed These ties are required around the total precast floor,
reinforcement can act as the internal tie. within a distance of 1.2 m from the edge. Peripheral
ties are made continuous around external corners or
The internal ties should be capable of resisting an by lapping the tie reinforcement with the longitudinal
ultimate tensile force equal to; reinforcement in the precast component. In the latter
Ftie = 20kN/m x s case the precast component can act as the peripheral
Where s = spacing of the ties. tie. At inner corners of the perimeter of structures, the
tie reinforcement should be anchored straight inward on
If type 2 ties cannot be placed within the floor zone both sides.
the ties may be concentrated and added to perimeter
beams as ties type 5 and along the lines of the internal Peripheral ties can also act as the tensile chord of the
beams as ties type 5a. floor diaphragm. Peripheral ties should be capable of
resisting an ultimate tensile force equal to;
Ftie = ℓ x 10kN/m but not less than 70kN.
Where ℓ = length of the longest floor span.
Internal ties are required along the internal beam lines Vertical wall ties should be provided between
and are provided either by passing the ties through a superimposed walls to ensure there is a minimum
column to column connection, by passing ties through a tensile capacity vertically through a building. Normally,
sleeve in the column or placing ties symmetrically either continuous vertical ties should be provided from the
side of the column. Internal ties also act as the internal lowest to the highest level.
tensile chord of the floor diaphragm.
The vertical ties should be capable of resisting an
Internal ties along beam lines should be capable of ultimate tensile force per metre length of wall equal to:
resisting an ultimate tensile force equal to; Ftie = the maximum design ultimate vertical permanent
Ftie = (ℓ1 + ℓ2) /2 x 20kN but not less than 70kN. and imposed load per metre length applied to the wall
Where ℓ1 & ℓ2 are the span lengths in metres either side from any one storey.
of the beam.
Ties can be spaced equally along the length of the wall
5.6.1.5 Corner column ties (type 6) or grouped at not greater than 2.5 metre centres along
the wall.
These ties provide horizontal restraint to the corner
column by tying the floor system into the supporting 5.6.1.8 Vertical column ties (type 9)
structure. The corner column ties should be capable of
resisting an ultimate tensile force equal to; Vertical column ties should be provided between
Ftie = 150kN in two perpendicular directions or superimposed columns to ensure there is a minimum
equivalent placed diagonally. tensile capacity vertically through a building. Normally,
continuous vertical ties should be provided from the
Reinforcement provided for peripheral ties that is within lowest to the highest level.
1.2 metres of the column can be used as part of this
requirement The vertical ties should be capable of resisting an
ultimate tensile force equal to:
5.6.1.6 Edge column ties (type 7) Ftie = the maximum design ultimate vertical permanent
and imposed load applied to the column from any one
These ties provide horizontal restraint to the edge storey.
columns by tying the floor system into the supporting
structure. The edge column ties should be capable of
resisting an ultimate tensile force equal to;
Ftie = 150kN perpendicular to the edge.
Cantilever action.
In case of failure of a corner column the surrounding
structure can be supported by cantilever action. For
example the horizontal tie reinforcement on top of the
floor beam can function as cantilever reinforcement. To this
effect the tie-reinforcement should be inside the projecting
stirrups at the top of the beams.
Figure 5.21 Alternative mechanisms for alternate load path in skeletal structures
Figure 5.22 Mechanisms for alternative load path in wall frame structures
GENERAL ARRANGEMENT
Figure 6.1 Loadbearing wall structure
Portal raft
er
Free standing steel frame
Portal raft constructed first
er
Steel columns
V This edge to be
checked for stability
Bearing Length
60°
60°
T
Footing
C
Wall panels
Wall to raker
Wall to eaves tie
Eav
es ti
e
Ra ker Wall to rafter
er
Raft
er
Raft
Wall to wall
Wall to footing
Restraint required
Cladding panels
This chapter will focus on skeletal structures used for 7.3.2 Column to column connection 98
low to medium rise buildings. Technically there are no 7.3.3 Column to beam connection 99
constraints to the height that can be constructed but 7.3.4 Beam-to-beam connection 101
currently in Australia material handling issues dictate a
maximum practical height limit. 7.3.5 Beam to wall connection 103
7.3.6 Floor slab to beam connection 104
The most efficient skeletal frame solution irrespective 7.3.7 Floor slab to wall connection 106
of the number of storeys is in braced structures where
the horizontal stiffness is provided by stair or lift shafts
or shear walls. In this way, connection details between
beams on columns can be designed as pinned, greatly For buildings up to 2 to 3 storeys the structural system
simplifying the design and construction. can be based on the cantilever action of the columns or
walls, which are clamped into the foundations.
Figure 7.2 Indicative load verses span data for composite prestressed concrete inverted-tee beams
skeletal structure is the obvious solution and this can Given the above constraints the solution for the grid
be dimensioned to suit the architectural requirements. layout and framing is as follows.
If a concrete façade is nominated consideration should • The column locations dictate longer grid dimensions
be given to using loadbearing precast concrete wall in the east/west direction and determine the floor
panels. Where this is not possible, façade or spandrel should span east/west and the beams north/south.
panels that are supported on a skeletal structure at • The central core can provide lateral stability and
each level can be used. A common solution is to have allow the structure to be a braced skeletal frame.
an upper loadbearing façade supported on a transition • The blank west wall lends itself to a loadbearing
level above the ground floor. This can be an economical precast concrete wall.
solution provided the spans of the transition beams are • Internal beams can be inverted Tee beams and
limited. splayed from the grid to be supported on the
central core.
7.2.2 Establishing the grid layout • The east perimeter beams can be L beams with
spans to suit the façade module.
By way of example this section outlines the typical • The glass curtain wall can be supported off the floor
process that can be carried out by the project consultant slabs eliminating the need for perimeter beams on
to establish the grid layout for a building. the north façade.
• Beams on the south side of the central core can
The building shown in plan in figure 7.3 has the following either span from the south wall to the core or be
planning and architectural requirements. supported on an internal column as shown. In the
• Building footprint set by site limitations. latter case the short beam can be very shallow to
• Internal column and core locations are set by allow large service ducts to exit from the core.
basement carparking. • The south wall can be spandrel beams that span
• North and East walls are glass curtain wall. from grid to grid.
• South wall has horizontal glazing with up-stand • On these spans hollowcore slabs with a topping
spandrels. screed is probably the most economical floor
• West wall is a blank wall on the boundary. system.
Figure 7.4 shows a typical skeletal frame and identifies Where large numbers of protruding starters are required
the main connection types as follows. the projecting lengths should be staggered to facilitate
• Column to footing. positioning into the column ducts.
• Column to column
• Column to beam. Additional tie reinforcement should be provided at the
• Beam to beam bottom of the column to resist splitting forces induced
• Beam to wall. by the reinforcement discontinuity.
• Floor slab to beam.
• Floor slab to wall
d
pocket depth
min 1.5 d
The upper column loads are transferred down through A variation of this connection is where the beam runs
the beam ends to the lower column. Although apparently across the top of the lower column. This is a common
a monolithic connection the failure mode depends detail where beams cantilever over a column or where
on the relative strengths of the concrete and grout. beam continuity is used to reduce beam depths.
Typically at ultimate limit state the grout ‘extrudes’
from the joint and induces high splitting forces in the Connection Type B is the preferred option where column
ends of the elements. The flow of forces shows that the loads are high. With this type of connection the beams
column ends are subject to a splitting force that must are supported by corbels on the column. Running the
be resisted by horizontal tie reinforcement at the ends column past the beams avoids the issue of transferring
of the columns. The mechanism resisting the forces high column loads through the beams and allows the
through the ends of the beams can be likened to a column splice to be at any location. Corbels can be
‘bottle strut’ and horizontal reinforcement is required projecting or recessed and either concrete or steel.
to resist the induced stresses. Added to these are the
stresses induced by partial fixity of the beams and the
discontinuity formed by the grouted dowels.
Figure 7.12 Inverted-tee beams designed with a dapped joint Figure 7.13 Connection type B
to create a negative bending moment at the column that will
reduce the depth of the beam
100 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
Concrete corbels are designed in accordance with strut 7.3.4 Beam-to-beam connection
and tie theory. The ‘Precast Concrete Handbook’ [2] has
a detailed example of the design of a typical concrete Beam to beam connections should be avoided if possible
corbel. but where it is necessary, connections can be made as
shown in Figure 7.16. There are two types of beam to
As with the Type A connections dowel bars from the beam connections. The first is where a joint is required
concrete corbel project up through ducts in the beams. along the length of a beam and the second is where two
These bars are usually threaded to allow nuts and beams intersect at right angles.
washers to clamp the beam to the top of the corbel.
This clamping force can also be designed to resist any Both types of connections can be formed either by
torsional effects due to out of balance loading on the concrete or steel corbels or frequently by a combination
beam, particularly during construction of both, with a concrete corbel on the supporting beam
and a steel corbel on the supported beam.
Proprietary steel corbels as shown in figure 7.15 are not
readily available in Australia but specifically designed Concrete corbels, or dapped ends, are difficult to detail
steel insert corbels have been used on a number of on shallow beams as typically used on a skeletal frame
projects. A variation of these is the hanger bracket structure. There are a number of dimensional limitations
described in Chapter 7.3.4, beam to beam connections. in design codes for the geometry of the dapped end.
Figure 7.14 Connection type B. Concrete corbel Figure 7.16 Beam to beam connections
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 101
For example the PCI Design Handbook [4] requires the The assembled hanger bracket system comprises;
depth of the extending end to be not less than one half • Steel cantilever bracket(s) with anchor bars cast into
the depth of the beam. Strut and tie methods should the supported beam.
be used to design dapped ends. The ‘Precast Concrete • Bearing bracket cast into the supporting beam
Handbook’ [2] has a detailed example of the design of a ledge.
typical dapped beam. • Torsional brackets (if required) between beams.
Where beams intersect at right angles the connection Pairs of brackets are used with the load to each bracket
design requires special attention, particularly in the being apportioned in accordance with direct and torsional
supporting beam, where the combined effects of loading on the beam. Brackets lengths should be least 1.5
bending, shear, torsion and bearing stresses may cause times the beam depth. The design process is as follows;
problems within the shallow depth. Figure 7.17 shows 1. Design the cantilever of the bracket to resist the
the forces induced in the projecting corbel on the applied combined bending moments and shear
supporting beam. forces. The lever arm is taken from the centreline of
the support to the centre of the anchor bars. Bracket
Steel hanger brackets are the preferred option for beam sections are usually channel or rectangular sections.
to beam connections particularly with shallow beams. 2. Calculate the area of steel required for the anchor
Although they have higher material cost, steel hanger bars. The point of rotation is assumed to be the
brackets are preassembled and cause less disruption end of the bracket. The preferable reinforcement
during manufacture and beams with hanger brackets configuration is to provide a single bar each side of
are easy to install on site. Loads of several hundred kN each bracket.
can be supported by this type of connection. 3. Check and design the supporting beam ledge.
Bearing brackets are usually required and the ledge
and the brackets and the associated hanger ligatures
should be designed in accordance with strut and tie
theory. The ‘Precast Concrete Handbook’ [2] has a
detailed example of the design of a typical beam
ledge.
4. Torsional effects induced in the supporting beam
can be resisted by designing the beam for torsion or
by providing torsion brackets in the bottom of each
beam.
5. After erection the hanger bracket is usually welded
to the bearing bracket and if present, torsion
brackets are connected by a welded plate, usually
before the beams are loaded.
Figure 7.17 Typical intersecting beam connection
102 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
beam to column connection as described in Chapter
7.3.2 and the same concepts apply. To ensure adequate
bearing and tolerance the nib projection should be
at least 200mm. If the precast wall is multi-level the
discontinuity in projecting nib above the beam needs to
be such that the beam can be inserted and lowered over
short dowels projecting from the lower nib. In this case
the projecting nib should be the full width of the beam
to prevent torsional overturning of the beam.
7.3.5 Beam to wall connection If the precast wall is multi-level the pocket clearance
The type of beam to wall connection is dependent on above the beam needs to be such that the beam can be
the supporting wall. If the wall is precast concrete the inserted and lowered over short dowels projecting from
options are to support the beam on a projecting nib on the lower wall.
the wall or on a pocket in the wall. If the wall is cast
insitu pockets or nibs may be difficult to provide and an An insitu connection is frequently required where
alternative solution is to connect the beam to the wall supporting walls are cast insitu and poured prior to
by an insitu infill. erection of the precast. For example, where a precast
skeletal structure is supported on an insitu concrete
Concrete or steel corbels on the wall can also be used to central core structure.
support the beam but these become substantial and not
economical because of the induced bending in the wall
from the large beam reactions.
The nib on wall connection is effectively similar to a
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 103
Figure 7.21 Beam connection to insitu wall
The top section of the beam is recessed for about 1 7.3.6 Floor slab to beam connection
metre at the end with the bottom ‘flange’ containing the
tensile reinforcement and ligatures continuing through Precast concrete floor slabs are typically one-way
to the supporting wall line as shown in figure 7.22. The spanning, and are therefore supported only at the two
beam is erected onto falsework, tie bar reinforcement is ends. Two support conditions occur, an internal beam
provided from the wall and into the pocket in the beam and an edge beam. To provide even bearing, slabs are
and the recess filled with insitu concrete. The design usually supported on neoprene bearing strips on the
method is based on the concept of shear-friction and is beam ledges.
covered in detail in the ‘Precast Concrete Handbook’. [2]
This connection effectively becomes the same as that Internal beams are typically inverted Tee or rectangular
used for connecting insitu concrete beams to previously profiles with the precast floor units supported on ledges
poured insitu concrete walls. or on the top surface. Where structural screeds are
provided the individual elements are tied together by
104 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
reinforcement in the screed. If there is no screed, which
can be the case with hollowcore slabs, tie bars are
provided either through or screwed into the beam and
into the cores of the slabs that are subsequently filled
with concrete.
For the service condition high torsion may occur with Figure 7.23 Forces inducing torsion in edge beams
a long and short span either side of the beam. This is
particularly the case with hollowcore slabs and torsion For the erection case, the precast portion of the beam
ties from the side of the beam and into concrete filled should be designed to resist the torsion induced by the
cores in slabs can be provided to resist the torsion. floor slabs without any need for propping.
Edge beams, or more precisely beams with floors With hollowcore slabs it is relatively easy to resist the
supported on only one side, can be either L or rectangular torsion due to the additional loads by providing tie bars
and may project above floor level to form spandrels. into the bottom of cores that are filled with topping
The depth of edge beams is normally not restricted by concrete. The applied loads used to calculate the torsion
headroom, in fact it is sometimes preferable to make the ties are those applied after the topping has been poured
edge beams deeper in order to provide an envelope on and cured.
to which cladding panels or the façade are attached. As
such, edge beams depths of around 1200mm are quite Edge beams can be either the same width as the column,
common. with the beam ledge projecting beyond the column face,
or a smaller width with the ledge inside the column
Torsion due to out of balance actions needs to be taken width. See Figure 7.24. In the first case the floor slab will
into account in the design of edge beams, particularly pass in front of the columns. In the second case it may
with long span floor slabs. Figure 7.23 shows the forces be necessary to cut notches in the slabs at the column
induced in an edge beam due to the applied loads from and possibly provide support for erection and service
the floor slab. loads with some form of corbel on the column.
Figure 7.24 Floor slab detail at columns. (a) wider beam allows floor slab to be uninterrupted. (b) floor slab is notched at the column
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 105
7.3.7 Floor slab to wall connection insitu part of the floor slab. Where the wall has sufficient
thickness the floor can be supported on a recess in the
This section covers only the typical details that occur on a wall.
skeletal frame structure where walls are supported on or
run parallel to shear wall core structures. In most cases It is possible to support the floor slab without the provision
the floor slab occurs only on one side of the wall. For a of corbels by providing tie bars across the interface to
more detailed coverage of connections between floors transfer the forces in accordance with shear-friction
and walls refer to Chapter 8, Loadbearing Wall Structures. theory. This detail is not recommended for hollowcore
slabs unless the loads to be transferred are very small.
Broadly there are two types of floor to wall connections. As temporary support is required during erection and
The first where the floor is supported on the wall and pouring the topping it is usually more economical to use
the second is where the floor spans parallel to the wall. one of the two previously described details.
Because these cases usually involve tying the floor
diaphragm to the shear wall structure, care is required in Figure 7.26 shows the typical detail where floor slabs
detailing to ensure that the ties can transfer the design span parallel to the wall. Slabs are tied to the wall with
forces into the precast floor. Ductility is an important bent-out bars or screwed-in starters into pockets notched
requirement for this type of connection. Where very in the side of the slabs. Because there is no transverse
high diaphragm forces need to be transferred it may be reinforcement in the hollowcore the lateral load capacity
necessary to locally thicken the insitu portion of the floor of this connection is limited unless there is a topping
to accommodate the heavier reinforcement adjacent to screed with lapping bars provided to tie the wall back to
the shear walls. the screed. The number and length of these starters is
limited by the amount that can be notched in the side of
Figure 7.25 shows typical details where the floor slabs are the hollowcore. Hooked bars are usually provided to lap
supported on the wall. A common detail is to stop the wall with the starters and the topping reinforcement.
at the underside of the floor and provide direct support
for the slabs on the wall. Projecting dowel bars run up
through the floor and into the upper wall. Hairpin bars
are required to lap round the dowels and into the floor
slab. Where the wall has sufficient thickness it is possible
to support the floor on a rebate with a thin section of the
wall running past the floor. This gives a tidier detail and
avoids the need for formwork.
Where the wall is multi-level and runs past the floor slab,
it is common to provide a concrete or steel corbel on the
wall to support the floor. The wall may be precast or insitu
concrete. Tie bars are required from the wall and into the
Figure 7.26 Floors spanning parallel to walls
106 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
8 LOADBEARING WALL
STRUCTURES
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 107
8.2 Design concepts
Any building that by its nature requires many internal For envelope wall systems the loadbearing wall
or external walls is well suited to be constructed as configuration depends on the building layout. For a
a loadbearing wall structure. The most economical typical rectangular building the cross walls between
structure is the result of optimising the cost of the two apartments and possibly the corridor walls can be
main components, the walls and the floors. This usually precast with a precast floor system spanning along
results in minimising the number of vertical components the building and across the width of the apartment as
and maximising the spans of the floor system. This will shown in figure 8.1. and figure ??? The façade walls can
also depend on the type and occupancy of the building be either precast or lightweight.
being considered, for example an apartment building
with many walls or a commercial building requiring a This configuration is appropriate for floor spans of up to
minimum of walls. about 16 metres between apartment walls. Where this
span is exceeded and the total width of the building does
8.2.1 Apartment buildings not exceed about 16 metres the precast floors can span
across the width of the building from façade to façade
Walls on apartment buildings can be floor-to-floor or as shown in figure 8.2. Other alternatives are to span the
multi-level, with the decision often dictated by the floor floor across the width of the building from the corridor
system. With precast floors the internal walls usually wall to an external loadbearing façade or to provide an
run floor-to-floor with the floor supported on top of the internal loadbearing wall within the apartment.
wall. External walls can be floor-to-floor or multi-level
and usually run past the edge of the floor. Buildings with There are also numerous variations with precast floors
insitu concrete floors frequently have multi-level walls. to accommodate cantilevered balconies and floor set-
downs. These are described in Chapter 4.
Apartment buildings can roughly be divided into two
categories: Integral wall systems and envelope wall With relatively large numbers of walls compared with
systems the floor area the lateral stability of apartment buildings
is usually not critical. In most cases the wall panels
• Integral wall systems are where all internal and can be erected one above the other with only nominal
external walls are in precast concrete. Some walls tension and shear capacity across the horizontal joints
are load bearing, others perform only a separating and with no shear connections in the vertical joints.
function. The façades are also loadbearing and Where lateral stability is critical, individual wall panels
the floors can be precast or insitu concrete. This can be connected to form larger shear walls as described
was a common form of construction in the early in Chapter 5.
years of precast concrete as it mimicked traditional
construction of loadbearing masonry.
108 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
Corridor Dividing walls
between apartments
Apartment
Figure 8.1 Outline of a building with load bearing cross-walls
Lightweight internal
walls & dividing walls
Load bearing facade between apartments
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 109
8.2.2 Commercial buildings Floor-to-floor heights of commercial buildings are often
greater than the maximum dimension for transporting
The use of loadbearing walls in commercial buildings panels so there is a tendency to favour the use of
can roughly be divided into two categories: Lift and stair narrower multi-level panels. It is also common to locate
shafts or external walls. the horizontal joint above floor level so that the wall acts
as a safety barrier during construction.
• Lift and stair shafts are an ideal use for precast
concrete, particularly for low to medium rise
buildings where overturning is not a major factor.
Typically panels are connected after erection to
form composite T, L, U or box-shaped sections.
Tension and shear forces across horizontal joints
are resisted by grouted dowel connections
and vertical shear between panels by welded
connections. Panels can be floor-to-floor or multi-
level depending on the floor system be used.
110 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
8.3 Connection Details
Examples of typical connections in loadbearing wall Types 2, 3 and 4 are further sub-divided by use with
structures are given in this section. The intention is not to either a precast or an insitu floor. Type four is further
show a complete overview of all solutions, but to make sub-divided into vertical and horizontal joints.
the designer familiar with common types of connections.
The principles applied in the majority of solutions are
valid for all types of loadbearing wall structures and
both for low-rise and multi-storey buildings.
Floor to footing
Wall to wall
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 111
8.3.1 Wall to footing connection 8.3.2 Floor to internal wall
The most common wall to footing detail is a grouted connection
dowel as described in Chapter 6.3.1. The number and There are a number of variations of this detail that
size of dowels will be dependent on the axial forces and depend on the type of floor and the forces to be
the presence or not of tensile or shear forces across the transferred from the upper to the lower wall.
joint. Where compressive forces are high, confinement
reinforcement may be required in the base of the wall Figure 8.7 shows connection details that are typically
panel. used between precast walls and precast floors.
112 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
Figure 8.7 a) shows the classic connection detail of a The National Precast Concrete Association Australia
precast floor supported on the lower wall. Grouted have produced a grouting guide for loadbearing joints
dowels run from wall to wall through the floor and that covers this topic in some detail.
tie bars within the floor or structural topping tie the
elements together. Consideration needs to be given to Where loads from the upper walls are very high it
the clamping force due to axial forces from the upper may be necessary to eliminate the sandwich effect of
wall and the resulting negative bending moment and the floor and provided direct bearing wall to wall as
reduced shear capacity that can be induced in the shown in Figure 8.7 c). The supporting corbels can be
end of the precast floor elements. Where a structural either steel or concrete as described below in Chapter
screed is provided the reinforcement in the screed is 8.3.3. Concrete corbels each side of a wall panel is not
usually sufficient to resist this bending moment. For a practical solution and should be avoided wherever
un-screeded floor systems the ends of the precast floor possible. Where steel corbels are used, the FRL of the
elements can be tapered as shown in Figure 8.7 b) to connection for moderate loading conditions can be
ensure a true pinned support condition. achieved by providing dowels that project from the
wall and into the precast floor system. Such dowels are
Bearing length of the floor elements and the effects designed in accordance with shear friction theory to
of tolerances also need to be taken into account and carry the reduced fire load eliminating the need to fire
this may dictate a minimum wall thickness. In multi- protect the steel angle.
storey loadbearing wall structures, the ends of the slabs
together with the jointing concrete or mortar transfer Information on the detailed design of wall connections
the forces from the upper wall element to the lower one. and extensive literature is available on the subject.[4]
[27]
Calculation of the load capacity through horizontal joints
is very complex. Quality of the grouting is important and
bearing is often non-uniform or eccentric and can result
in high splitting forces in the panels even when the
average stress is small. Even where bearing is uniform a
reduction factor of 0.5 is often applied to the calculated
vertical load capacity through the joint.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 113
8.3.3 Floor to external wall design for eccentricity of load from the floor. As noted
for internal wall connections the FRL can be achieved
connection without the need to fire protect the steel angle by using
As with the internal wall connections there are a large shear friction design methods.
number of variations of this detail that depend on the
type of floor, the loads to be transferred from the upper In both cases tie bars from the wall into the precast
to the lower wall and the presence or not of a horizontal elements or floor topping tie the elements together. If a
wall panel joint. In all cases the eccentricity of load from horizontal wall panel joint occurs at this location it should
the floor into the wall needs to be taken into account in be positioned at or above floor level. With a stepped joint
the design. Deflection and rotation of the floor can also for waterproofing, care should be taken to ensure that
increase the bending moment in the wall. This is described the wall panel has sufficient thickness to accommodate
in detail in Chapter 4. and provide adequate cover for all the fixings and edge
reinforcement.
Figure 8.8a) shows the connection detail of a precast floor
supported by a concrete Where structural requirements dictate a thick wall, the top
corbel. The corbel is designed in accordance with strut section of the wall can be rebated as shown in figure 8.8 c)
and tie theory and eccentricity of load needs to be taken to provide support for the floor elements. With minimum
into account in the design of the wall. With this detail it is dimensions for the up-stand and floor bearing this detail
easy to produce a ductile connection. This corbel detail requires a minimum wall thickness of about 200mm.
is probably the simplest and most economical of these
support details but it is not favoured by many precast wall Bars projecting from the lower panel are bent down into
manufacturers because of the two stage pouring process the precast floor elements or screed and grouted dowels
and complexity of storing and transporting the element running from the lower panel past the floor and into the
with a projecting corbel. upper panel tie all elements together. The bent down
bars can be eliminated if sufficient dowels are provided
Figure 8.8 b) shows a similar connection detail of a and each is confined by a hairpin bar anchored into the
precast floor supported by a steel corbel. The steel corbel precast floor or screed.
can be either cast into the panel during manufacture or
bolted or welded to the panel before or after erection. As shown in Chapter 7.3.6 it is possible to support the floor
Casting in during manufacture is the most economical slab without the provision of corbels by providing tie bars
option as post fixing, particularly on site after the panel across the interface to transfer the forces in accordance
is erected is a time consuming and expensive process. with shear-friction theory. This detail is not recommended
Because of their lack of ductility, fixing with drilled-in for hollowcore slabs unless the loads to be transferred
expansion anchors is not recommended for such major are very small. As temporary support is required during
and key structural connections. The steel corbel should erection and pouring the topping it is usually more
be designed in accordance with the Steel Structures economical to use one of the previously described details.
Code, AS 4100. [28] Due allowance should be made in the
114 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
8.3.4 Floor connection parallel to 8.3.5 Wall to wall connections
wall There are two basic wall to wall connections. They
Where the floor system spans parallel to the wall the two occur at vertical joints and horizontal joints. The forces
elements should be connected together to eliminate any to be transferred by the connections will depend on
differential movement. Although the wall may not be the structural application of the wall but can include
intended to be loadbearing the fact that it is connected in-plane shear, out-of-plane shear, tension and
to the floor means that some load will be transferred. compression. Ductile behaviour is a requirement of all
The magnitude will depend on the stiffness of the floor connections and with relatively thin wall sections this is
and the extent of axial shortening and shrinkage. For often difficult to obtain. Careful detailing of anchor bars
one-way prestressed floor elements it is usual to assume and confinement reinforcement is required to prevent
that the load from a one metre band of floor each side pull-out of the connection fixings. Where significant
is carried by the wall. An alternative and more accurate forces are to be transferred by the connection an insitu
load distribution assumes that only actions applied after infill joint to emulate monolithic construction may be
the two elements are connected are distributed to the necessary.
wall by two way action. Floors such as hollowcore slabs
with high torsional stiffness will distribute higher loads The National Precast Concrete Association Australia
than slabs that tend to have relatively low torsional have produced a grouting guide for loadbearing joints
stiffness. that covers this topic in some detail. This document,
‘Understanding Grouted Precast Joints, a guide for
Figure 8.9 a) shows a hollowcore slab connected to Engineers and Contractors’, [43] highlights the need
the side of an external precast wall. Threaded bars are for careful design and detailing of the load transfer
screwed into ferrules cast into the wall and project into mechanism through grouted horizontal joints. The
slots cut in the side of the hollowcore slab. Because importance of establishing a work process that ensures
there is no transverse reinforcement in the hollowcore the joints are grouted in accordance with the design
the lateral load capacity of this connection is limited requirements cannot be overemphasised. Structural
unless there is a structural screed and lapping bars can failures have occurred due to inadequate grouting
be provided to tie the wall back to the screed. and this process should not be left to inexperienced or
unskilled tradespeople.
Figure 8.9 b) shows the detail where there is hollowcore The use of stepped joints where high vertical loads occur
on each side of an internal wall. The lower wall projects should be given careful consideration as partial grouting
above the soffit of the floor. Dowels or starter bars the width of a joint introduces significant splitting forces
project from the lower to the upper wall and the that can limit the load bearing capacity of the joint.
elements are tied together by and insitu infill. With thin wall sections it is often impossible to provide
reinforcement to resist these splitting forces.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 115
With a stepped joint for waterproofing, care should be Connections at the vertical joints between wall units
taken to ensure that the wall panel has sufficient thickness are normally designed to transmit in-plane shear forces.
to accommodate and provide adequate cover for all the Figure 8.11 shows the three typical variations that can
fixings and edge reinforcement. Where out-of-plane forces occur. In all cases the connection is formed by cast-in
occur confinement reinforcement should be provided to fixings and stitch plates. The fixings may or may not be
prevent side breakout of the dowels. recessed for protection or fire rating.
Tension forces can also be transferred by a bolted The basic types of fixings used are;
connection recessed in the base of the upper panel as • Steel plates complete with anchor bars cast into the
shown in Figure 8.10 c) although this connection can be edge of each panel as shown in Figure 8.11. After
difficult to use where a waterproof joint is required. erection a stitching plate is welded across the joint to
form the connection.
Vertical post-tensioning with strand or bar is another • Threaded inserts with appropriate anchor bars are
option that can used to resist high tension forces that cast into each panel and a loose plate is bolted
occur in lift or stair shafts. Vertical ducts are provided across the joint. Bolt holes need to be oversized to
in the wall panels from base to top and strand or bar is accommodate tolerance and this may require the
threaded down and anchored into the footings. The strand plate to be welded to complete the connection.
or bar is tensioned after erection and grouting of the • A variation of the above fixings is to bolt the stitching
complete wall. plate to the cast-in plates as a temporary fixing for
erection and then weld the plate at a later date to
The horizontal joint between lower and upper panels complete the connection.
needs to be filled to ensure axial forces can be transferred.
This is usually accomplished by sealing each side of the Because of the cost of the plates and the need to site weld
joint and filling it with a flowable grout or by dry packing at height these are expensive connections and should
with mortar. The strength of the grout or mortar should be only used where needed for structural reasons. Each
be sufficient to carry the load. Where a waterproof joint additional plate in a wall panel can add several dollars per
is required the backing rod and sealer will reduce the square metre to the cost of the panel.
load bearing area. Filling only part of the joint width can
result in transverse splitting stresses being induced into The use of post installed expansion or chemical anchors
the walls. is not recommended for this type of structural connection
due to the difficulty in providing ductility.
As noted in Clause 8.3.2 horizontal joints with high
loads and complex geometry may require a detailed There are a number of proprietary panel connection
finite element analysis be carried out and if necessary systems available that allow the installation of precast
longitudinal and transverse reinforcement be provided in concrete panels on site without the need for welding or
the walls to resist cracking. bolting.
116 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
Figure 8.11 Vertical wall to wall connections
Figure 8.12 shows a detail for a ship-lap joint that is suited Figure 8.13 shows variations of an insitu concrete infill
to connecting individual walls to form lift or stair shafts. connection that is intended to emulate monolithic
The advantages are high load capacity, ease of providing construction.
ductility and ability to work on the connection from floor
level outside the shaft. The vertical joint faces are usually indented or intentionally
roughened to increase the shear capacity of the joints.
The size or width of the infill needs to be sufficient to allow
it to be filled with a flowable grout or concrete. Projecting
hairpin ties over the height of the panels are held together
by a continuous vertical bar. The shear capacity of the
connection can be calculated using shear-friction theory.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 117
8.4 Design of welded plate
connections
8.4.1 Introduction 8.4.2 Design concepts
Welded connections between walls are common within All connections should be robust so that they have
the precast industry and every consulting engineer and the ability to withstand accidental events such as fire,
precast manufacturer seems to have their own favourite. explosions, impact and consequences of human error
In many cases details have been used for many years without causing damage to an extent disproportionate
and repeated from project to project without being to the original cause.
subject to a rational design method to verify capacity.
Robustness infers that the connection is stable, has
This section will set out a design philosophy that gives reserve strength and stiffness, exhibits ductility and
a rational design method for welded connections. Given has redundant capacity. These requirements are often
the critical nature of these connections the approach is difficult to provide in connections in relatively thin
based on a conservative lower-bound design case. concrete sections. Concrete failure is usually the critical
and limiting factor in establishing the capacity of the
An alternative is to carry out a finite element analysis, connection. With a concentration of forces in such a small
but given that the material cost is only a small part of area it is difficult to provide sufficient reinforcement that
the cost of weld plate connections this is rarely justified. can anchor and prevent localised splitting or spalling of
the concrete around the fixings. For example additional
reinforcement other than a long anchor bar has little
influence on the concrete cone failure of a cast-in ferrule.
118 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
8.4.3 Design method The stitch plate and associated welding should be
designed to resist the same forces as those calculated
Figure 8.14 shows a diagram of a typical welded plate above.As required by the Building Code of Australia
connection between two panels that are subject to [10] these connections also need to be detailed to
vertical shear. The fixing plates are provided with anchor accommodate thermal movement and possible collapse
bars and a headed stud on the rear. The anchor bars of the roof structure during a fire.
need to be of sufficient length to develop full capacity
and can be either perpendicular to the joint or splayed Cladding panels can act as shear walls by positively
as shown. The fixing plates are recessed to ensure the connecting each panel to the steel frame or by providing
anchor bars occur within the middle third of the panel grouted dowel connections in the horizontal panel joints
thickness. A welded stitch plate forms the connection so that a series of individual panels act as a single panel.
between the two fixing plates.
The remaining types of cladding panel connections,
Vertical shear between panels produces direct shear vertical panel to eaves tie, panel to panel and corner
as well as a rotational moment in the connection that panel connection are all similar to those used for
is resisted by the anchor bars acting in tension and loadbearing walls as described in Chapter 8.
compression. The vertical shear is assumed to act at the
face of the wall joint and the design forces in the anchor
bars are calculated on the assumption that each plate
can rotate about a point where the anchor bars are fixed
to the plate.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 119
120 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
9 MIXED
STRUCTURES
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 121
9.2 Design concepts
The optimum structural design of any building is based Setting the precast elements below the top of the steel
on selecting the most appropriate type of structure for beam can make erection difficult and does not suit all
each major part of the building as distinct from allowing types for precast floors.
a single part to dictate the complete structure. Within
this selection process the optimum structural material Composite action with the steel beam is facilitated by
should also be selected for each component. the provision of stud anchors on the beam projecting
into an insitu infill between the ends of the precast
The following sections will give an overview of the use elements. The design process is similar to that for an
of precast concrete with other materials such as steel, insitu concrete floor except for staged loading of the
insitu concrete and masonry. Many of these concepts beam by the precast floor before composite action is
have already been referred to in previous chapters. taken into account. Where hollowcore floor elements
are used, as shown in figure 9.2, the flange width and/
9.2.1 Steel and precast or effective slab depth are modified to account for the
voids in the hollowcore slabs.
Uses of structural steel and precast include steel beams
supporting precast floor elements, steel permanent The effect of the bottom flange of the hollowcore is
formwork combined with precast beams and steel ignored and the width of the infill above the steel beam
elements used to support precast concrete. can be varied by filling all cores with concrete for a
distance each side of the beam. The thickness of the
Figure 9.1 shows steel beams supporting precast concrete flange is the sum of the concrete thickness
concrete floor elements. The beam may be an individual above the core plus the screed thickness. Because the
steel beam or part of a steel frame structure. The floor flange is relatively thin the effective flange width should
elements can be beam and infill, composite floor plates be limited.
or hollowcore. In all cases it is usual, and structurally
more efficient, to detail the two elements so that they Detailed guidelines are given in the fib ‘Guide to good
act compositely. practice, composite floor structures.’ [14]
122 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
Figure 9.2 Steel beam and hollowcore floor Figure 9.3 Composite steel beams and hollowcore floor
The design method for edge beams is similar to the Where a shallow floor profile is required, a steel beam
above methods but ties are required from the steel that supports the precast floor elements on its bottom
beam into the precast or screed to prevent horizontal flange can be used as shown in Figure 9.4. The main
movement of the beam. use in Australia has been as trimmer beams at openings
within floor slabs where height considerations preclude
In all cases, particularly edge beams, the stability of the use of a down-turned supporting ledge.
the steel beam during erection and pouring the screed
can be critical and some type of flange restraint or The steel beams can be fabricated sections with a profile
temporary propping or bracing may be required to to suit the particular use. PFC’s with a flange added are
prevent buckling or rotation. Friction between the steel common but they can also be UC or RHS sections with
beam and precast elements should not be relied upon flanges added. They can be detailed as either composite
to provide restraint. or non-composite.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 123
Use of these types of beams with hollowcore floor 9.2.2 Insitu concrete and precast
elements can result in reduced shear capacity of
the hollowcore due to the fact that deflection of the Insitu concrete flooring can be used with precast walls.
supporting beams induces transverse stresses across The precast walls are erected and braced in position and
the webs of the hollowcore. Where the design is based an insitu or metal deck formwork concrete slab is poured.
on full composite action between beam and hollowcore,
and reinforcement is provided to transfer all forces, Figure 9.6 a) shows the typical situation where an insitu
the reduction in shear capacity can be small. For non- floor slab is poured over the lower wall. Starter bars
composite action the reduction in shear capacity can project from the wall and lap into the slab and dowels
be significant. In both cases the shear resistance can be are cast or drilled into the slab to provide a connection to
increased by filling the cores with concrete at the slab the upper wall. Note the minimum tie force requirements
ends over a length of at least the slab depth. Extensive as set out in Chapter 5.
research has been carried out on this topic and is
available in a number of fib publications. [14, 30] A variation is shown in figure 9.6 b) where a multi-level
wall runs past the floor. In this case the load from the
Where precast floors are supported on insitu concrete floor is transferred to the wall by using the concepts of
walls a steel angle as described in Chapter 8.3.3 is shear-friction. The interface surface is roughened and
commonly used. Eccentricity of load needs to be taken reinforcement is provided across the interface to tie the
into account when designing the angle and fixings. In insitu and precast together. This tie reinforcement can be
all cases bars from the wall into the precast elements or pull-out bars or starters screwed into ferrules cast into
floor topping tie the elements together. the wall. There is no benefit in providing a recess in the
wall as this is not taken into account in the shear friction
design. The most important criteria is the roughness of
the interface. The shear-friction design method is set out
in detail in the Precast Concrete Handbook. [2]
124 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
Figure 9.7 Insitu floor and precast wall
Figure 9.8 Insitu floor to external precast wall Figure 9.9 Insitu beam and precast wall
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 125
Insitu concrete beams can be combined with precast 9.2.3 Masonry and precast
floors. This combination only becomes economical
if there is considerable repetition of beams or where The use of masonry walls to support a precast
beam depth or span precludes the use of precast beams. floor is common in low-rise domestic construction.
Where this occurs the logical option is to erect the Construction speed is much greater than for an insitu
precast floor elements onto the edge of the supported floor but buildability can be an issue with respect to
beam formwork and then pour the beam and floor crane access. Sufficient walls need to be constructed
topping in a single operation as shown in Figure 9.10. to allow erection of enough precast flooring to justify
The beam is designed as a monolithic section with the mobilisation of a crane.
flange width as described in Chapter 4.4.2. A precast
shell beam acting as permanent formwork is a variation As shown in figure 9.11, the precast floor system can
of this concept. be supported directly on top of the masonry wall in
the same manner as an insitu floor slab. An isolating
The insitu beam allows the design to be based on bearing strip is usually used on top of the wall and in
full continuity, either as reinforced or post-tensioned most cases there is no need to tie the walls into the floor
concrete and is ideal where beam depth is critical. system. The exception is where the floor is required
to act as a diaphragm and lateral loads are transferred
between the floor and walls or where lateral support is
required at the top of the wall.
126 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10 FIRE
RESISTANCE
The purpose of this chapter is to give the designer 10.3.2 Thermal expansion 132
more insight into the behaviour of a building structure 10.3.3 Thermal deformation of the cross-
exposed to fire, so that they understand what direct and section 133
indirect actions are taking place and how the concrete 10.4 Global structural analysis 134
structure is reacting as a whole. It should enable the
10.5 Member analysis 135
application of specific design philosophy extending
beyond the simple check of the fire resistance period 10.5.1 Beams 135
(FRP) of single concrete elements, as it is often the case. 10.5.2 Columns 136
10.5.3 Walls 136
The requirements with respect to the performance of a
building subjected to fire are set out in regulations such 10.5.4 Floor slabs 136
as The Building Code of Australia [10] and are expressed 10.6 Fire resistance of structural
as the Fire Resistance Level (FRL). They specify how connections 139
long a structure shall resist a normalized fire - generally 10.6.1 Beam to column connections 139
the ISO Standard fire curve. Figure 10.1 shows the typical
10.6.2 Beam to beam connections 139
ISO time temperature curve compared with that for a
hydrocarbon fuelled fire. 10.6.3 Floor to concrete beam
connections 139
The Building Code of Australia requires each of the 10.6.4Floor slab to steel beam
individual elements of a building to have a fire resistant connections 140
period (FRP) for structural adequacy, integrity and 10.6.5 Floor to wall connections 141
insulation that is not less than the required fire resistant
10.6.6Inserts and fixings 141
level (FRL).
10.6.7 Joints 141
10.7 Establishing FRP by testing 142
10.8 Conclusion 142
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 127
There are two aspects to producing a building with the Section 5 of AS3600 provides for the FRP of a structural
required FRL as nominated by the Building Code of member to be established by empirical methods based
Australia. They are the ‘passive design’ and the ‘active on member dimensions and reinforcement cover. The
design’. designer must check whether the member is able
to meet these requirements. Calculation methods
The passive design refers to the design of the building are acceptable, but no guidance is given other than
structure and envelope. The active design refers to a reference to Eurocode-2. [24] The performance of
measures that are put in place within the building to concrete buildings subject to fire is discussed in detail
enhance its performance in a fire. For example provision in the Cement Concrete & Aggregates Australia, Fire
of a sprinkler system may allow a reduction of the FRP Safety of Concrete Buildings. [36]
of all or some of the elements in the building.
1400
1200
1000
Temperature ºC
800
600 ISO-curve
Hydrocarbon-curve
400
200
0
0 60 120 180 240 300 360
Time in minutes
128 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10.2 Basic requirements
In accordance with Eurocode-2 [24] requirements the
capacity of a concrete structure to maintain its load
bearing function during the relevant fire exposure, is
expressed as follows:
Ed,fi(t) < Rd,fi(t)
where Ed,fi(t) is the design effect of actions in the fire
situation at time ‘t’.
Rd,fi(t) is the corresponding design capacity at elevated
temperatures.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 129
10.3 Fire actions
10.3.1 Reduction of material In concrete structures, the situation is completely
different due to the low thermal conductivity of the
performances material. The heating progresses much slower, and in a
When a fire occurs in a building, the temperature non-uniform way over the cross section and length of
rises fast, at least when there is enough combustible the member. For example, after one hour of ISO fire, the
material and oxygen. The exposed structural members temperature in a plain concrete floor slab can be 600°C
will heat according to the thermal conductivity of the at the bottom and only 60°C at the top. The reinforcing
materials: very fast for unprotected steel, rather slowly steel in the lower part of the cross-section warms up and
for concrete. Two phenomena occur simultaneously: a gradually loses its strength. At a certain temperature the
reduction of the material performances and a thermal reinforcing steel is no longer capable of taking up the
dilatation (expansion). Data about material performance stresses and failure occurs. This temperature is called
as a function of the material temperatures are available the critical temperature.
in Eurocode 2. [24]
For example, with a concrete cover to the reinforcement
In unprotected steel structures the temperature will rise of 25mm, the critical temperature of the reinforcing
rapidly over the whole cross-section, because of the steel (500 °C) will occur after about 90 minutes ISO
high thermal conductivity of the material. Depending on fire exposure. For a concrete cover of 35mm the critical
member sizes and fire temperature a critical limit state temperature will be reached after 120 minutes. For
will be reached in which the material strength is reduced prestressing steel the critical temperature is 100 to 150 °C
to about half, and the safety margins disappear. Plastic lower than for normal reinforcing steel. As a consequence
hinges appear everywhere and the structure collapses. the cover on the prestressing reinforcement should be
For light steel structures this can occur within about 15 increased by 10 to 15 mm to obtain the same FRP.
minutes.
130 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
In addition to the decrease of the material performance, Braced wall structures consisting of loadbearing concrete
the structure will be subjected to thermal expansion. wall panels and lightweight steel roof structures are a
Beams and columns will expand mainly in the special case where removal of the braced roof by fire can
longitudinal direction while floors and walls will expand result in the instability of the wall panels even though
in both longitudinal and transversal directions. they may not be directly affected by the fire. For this
reason the Building Code of Australia [10] has specific
The above considerations show an important difference requirements that apply to these types of buildings to
between the behaviour of concrete and steel structures ensure stability of perimeter walls after a fire.
at fire. For steel structures, the stability of the structure
depends on the resistance of the individual members
whereas for concrete structures the global behaviour of
the structure is governing, and the fire resistance of the
individual members is seldom critical.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 131
10.3.2 Thermal expansion When a fire occurs locally in the centre of a large
building, the thermal expansion will be restrained by
During a fire, concrete needs time to warm up so the effect the surrounding cold concrete structure, and very large
of thermal expansion will be much less during a short compressive forces will generate in all directions. When
intense fire than during a longer lasting less intense fire. For the fire occurs at the edge of the same building, the
this reason the ISO fire curve may not necessarily be the horizontal “blocking” will be much lower. The most critical
most unfavourable thermal action. The time temperature situation is when the fire covers a wide surface, resulting
curves on Figure 10.1 show that a hydrocarbon fire can be in large accumulated deformations.
much more intense than a standard ISO fire.
The longitudinal expansion of beams or ribbed slabs will
The most critical situation is when the fire covers a wide be considerably larger than for plain slabs. Beams are
surface, resulting in large accumulated deformations. exposed on three sides to the fire so the thermal gradient
Thermal expansions of 2-3mm per lineal metre can will be more uniform over the whole cross-section.
occur in concrete structures during a fire and parts of
the structure remote from the fire can be subjected to
significant displacement and even failure. In precast
structures cooling and contraction after a fire can
also result in failure by subjecting connections to load
reversals. For example precast floor elements slipping off
supporting ledges.
132 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10.3.3 Thermal deformation of the In a continuous floor structure the downwards
thermal deflection will be resisted by the continuity
cross-section reinforcement at the top of the slab, and the support
In addition to the longitudinal and transverse expansion, moment will increase. The increased support moment
elements subjected to fire on only one side, for example will create additional compressive stresses at the bottom
flat floors, will also undergo a deformation of the cross- of the floor and tensile stresses in the top reinforcement
section. Because of the temperature gradient over above the support will increase and in some cases even
the cross-section, the exposed underside will expand yield. In this case the increased shear induced into the
much more than the cooler upper side. This will force floor unit at the support as well as the flexural capacity
the member to deflect downwards. However, the needs to be checked.
deformation will not be directly proportional to the
temperature gradient, since the latter is generally not
linear over the cross section.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 133
10.4 Global structural
analysis
The analysis of the global structure of a building or parts In a multi-storey building with a stabilizing stair and lift
of it, should take into account the relevant failure mode shaft, the most favourable situation will be met when the
due to the fire, the temperature-dependent material stabilising core is placed in the centre of the structure,
properties and member stiffness and effects of thermal enabling an even expansion of the surrounding floors
expansion and deformations. Australian Codes do not in all directions. Figure 10.7 shows a structural layout
stipulate how to include these effects and the analysis typical for a precast building, which would probably
for fire safety is restricted to the verification of single react favourably to the thermal expansions during a
structural members to ensure they comply with the fire. The central core will take up the horizontal actions.
cross section dimensions and the minimum concrete All other components are connected to it with hinged
cover on the reinforcement for a given ISO fire exposure joints. During a fire, the restraining forces will be limited,
time. and the connections between the core and the other
structural components (columns, beams, and floors)
Experience in real fires shows that instability of concrete have a statically determined character. Slender columns
structures seldom occurs due to the decrease of material or hinged connections will deform together with the
performances at elevated temperatures, but nearly structure, without causing large blocking forces and
always because of the incompatibility of the structure shear failure. The design should allow for movement
to take the imposed thermal deformations. Fortunately, where possible, to avoid incompatibility of deformations
concrete structures not only have a high inherent fire due to thermal expansion.
resistance but they also have large redistribution
capacities due to robustness and structural integrity. The most important part in ‘fire engineering’ a concrete
Consequently, failure of concrete buildings due to fire building is to assess how the building as a whole will
seldom occurs. deform under elevated temperature and ensure that
these deformations can be accommodated without
Based on research it is possible to outline a design failure occurring. Attention to the design of the
philosophy and guidelines based on practical connections is important to ensure that they can
experiences of real fires and model simulations. accommodate not only the thermal expansion during
• More attention should be given to the overall the fire but also the contraction due to cooling after the
behaviour of the building when exposed to fire.
fire, rather than looking only at the individual
components affected by the fire.
• The shape and dimensions of the building, as well
as the static system are very important in the
behaviour of a building during a fire, especially the
effects of thermal expansion, deformations and
blocking forces. For example in small buildings
the thermal expansion will cause much smaller
blocking forces than in large buildings with a fire
in the centre.
• In buildings with large floor areas and insufficient
movement joints very large expansion may
occur. Not only should the distance between the
movement joints be considered but also the width
of each joint. As a first approximation the effect of
expansion due to a temperature rise of 100-150°C
should be checked. Figure 10.7 Favourable stability lay-out with respect
to thermal expansions
134 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10.5 Member analysis
According to AS3600, Section 5.3, [7] the FRP of a Holes through the webs of beams do not affect the fire
building element can be determined by tabulated data resistance provided that the remaining cross-sectional
from design codes or methods of calculation. area of the member in the tensile zone is not less than
Ac = 2b²min where bmin is the minimum beam width.
Testing in accordance with AS1530.4. [31] can also be
used but establishment of the FRP from tabulated data The FRP of beams can also be verified by a simplified
is the most commonly adopted method. calculation based on the Ultimate Limit State method.
The load bearing capacity is calculated with reduced
AS3600 provides solutions for the standard fire exposure material characteristics corresponding to their
up to 240 minutes. The data has been developed temperature at a given fire exposure time. The calculation
on an empirical basis confirmed by experience and method is based on the assumption that concrete at a
theoretical evaluation of tests. Minimum dimensions for temperature of more than 500°C is neglected in the
the cross-section of the components and a minimum calculation of the load-bearing capacity, while concrete
concrete cover on the main reinforcement is given. The at a temperature below 500°C is assumed to retain
information in AS3600 is mainly taken from Eurocode its full strength. In other words any concrete with a
2 - Part 1-2. [24] temperature above 500°C is neglected in establishing
the cross section dimensions.
For reinforcement levels which are larger than strictly
needed at ambient temperature, the minimum axis This method is extensively described in Eurocode 2 Part
distances given in the tables may be adjusted 1-2 [24] and in CEB Bulletin 208 [32]. These documents
are referenced in AS3600 Section 5.
For prestressing tendons in beams and slabs, AS3600
requires axis distance to be increased by 10mm. This method using the reduced cross-section may be
The reason lies in the fact that the reduction of steel applied for bending, shear and torsion in the design of
strength as a function of temperature is much faster for beams and slabs, where the loading is predominantly
prestressing steel than for normal reinforcing steel. uniformly distributed and where the design at normal
temperature is based on linear analysis. This is not
Note that by using tabulated methods in assessing the the case with hollowcore floor slabs where the shear
FRP of beams and slabs the applied actions on the capacity is dependent on the tensile strength of the
structure are not taken into account. concrete. This issue is discussed separately in further
detail in Chapter 10.5.4.1
10.5.1 Beams
Fire is considered to be an accidental action. As a result
Using AS3600, Section 5 [7] the FRP for a beam can a reduction factor may be the applied to the imposed
be obtained from a series of tables and charts plotting actions. In accordance with AS1170.0 [23] the applied
axis distance of the reinforcement against the beam action for fire is (G + ψ1Q) where ψ1 ranges from 0.4 for
width. Axis distance is based on the geometry of the residential to 0.6 for storage occupancies.
reinforcement and beam width is measured at the axis
height. Tables and charts are given for both simply
supported and continuous beams and for beams
exposed to fire on all four sides and for the more typical
precast beam case where the top flange is protected by
a slab.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 135
10.5.2 Columns 10.5.4 Floor slabs
The FRP of reinforced and prestressed columns is AS3600, Section 5.5, [7] allows for the FRP of one
influenced by several parameters: and two way solid, ribbed and hollowcore slabs to be
• Size and slenderness of the columns. established from tabulated data. The approach is similar
• Magnitude of applied load to that for beams with a further provision for a minimum
• First order eccentricity effective thickness to comply with the insulation
• Concrete strength and aggregate type requirements. For solid and ribbed slabs this is the most
• Reinforcement size and configuration effective method of establishing the FRP of the element.
• Axis distance of the reinforcement
Because of the complex interactions that affect the fire
Complex computer programs now exist, enabling the performance, particularly in the area of the support, the
calculation of the FRP of columns, taking account of the AS3600 requirements do not necessarily reflect the true
above parameters, inclusive of buckling. However, it is behaviour of hollowcore slabs, particularly in shear.
not possible to include all this information in tabulated
data. The topic of flexural and shear capacity of hollowcore
slabs subject to fire is dealt with separately in Chapters
AS3600 provides two tabulated methods to establish 10.5.4.1 and 10.5.4.2
the FRP of braced columns but both are restricted in
their application. Because the majority of precast The reference documents for hollowcore slabs subjected
buildings are braced structures this is a common method to fire are Eurocode-2 Part 1.2 [24] and European
of designing precast columns for fire capacity. Product Standard EN1168. [16]
The values in the tables apply to normal weight concrete 10.5.4.1 Flexural capacity of hollowcore subject to
(2000 to 2600 kg/m³) made with siliceous aggregates. fire
Unlike Eurocode 2, AS3600 makes no distinction
As for all types of floor slabs the FRP of hollowcore
between normal and lightweight concrete.
slabs in flexure is governed by the decrease of the
strength of the prestressing tendons as a function of
Unbraced or sway columns and braced columns that
the temperature. Full-scale fire tests have shown that
fall outside these restrictions require an alternative
the temperature within the vicinity of the prestressing
approach such as that provided by Eurocode 2 Part 1-2.
reinforcement is practically independent of the slab
[24]
thickness and slab profile. For this reason the tabulated
data in AS3600 Section 5.5 can be used to determine
10.5.3 Walls the FRP of reinforced and prestressed hollow core slabs
in flexure. The tables give the equivalent thickness of the
The FRP of walls is established in a similar manner to
slab and the values of the axis distance for reinforcement
that for columns with a further provision for a minimum
as a function of the required FRP for simply supported
effective thickness to comply with the insulation
slabs in normal weight concrete. Note that these values
requirements.
are not applicable to shear capacity.
The requirements are set out in Tables 5.7.1 and 5.7.2 in
The FRP of hollowcore slabs with respect to flexural
AS3600. This is based on the concept of insitu concrete
failure can also be determined by using simplified
and is not always applicable to precast concrete wall
calculation methods as described for beams in Chapter
panels. Precast wall panels usually have pinned ends
10.5.1 and Eurocode-2 Part 1.2. [24]
that determine the effective length, sway and P-Delta
effects.
136 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10.5.4.2 Shear capacity of hollowcore subject to fire Figure 10.8 (a) shows the appearance of vertical cracks
due to differential thermal deformation over the cross-
Prestressed hollowcore floor slabs generally have no section. Figure 10.8 (b) shows propagation of the vertical
shear reinforcement and very short bearing lengths cracks into horizontal cracks due to thermal effects, self-
at supports and this governs the shear capacity of weight and imposed actions. To assure adequate shear
hollowcore slabs subject to fire. Elevated temperatures capacity the FRP is limited so that possible cracks in the
increase the tensile stresses in the profiled webs and webs of the hollow core slabs are kept closed to enable
increase the transfer length of the prestressing tendons shear transfer by aggregate interlock mechanism.
due to possible strand slippage. The European Committee for Standardisation (CEN) in
EN1168:2005+A3:2011 [16] has published an empirical
Calculations show that after about 20 to 40 minutes formula that has been validated by means of FEM
ISO fire exposure, the tensile stresses in the central calculations and fire tests to calculate the shear and
zone of the web exceed the tensile capacity of the anchorage failure for hollowcore slabs subject to fire. The
concrete. At further fire exposure horizontal cracks method is derived from the shear formula in Eurocode-2
originate in the weakest zone of the cross-section for prestressed members at ambient temperature. By
due to shear stresses from thermal origin, self-weight, using this formula it is possible to compare the shear
imposed actions, prestressing and thermal expansion. and anchorage capacities of hollowcore slabs under fire
For circular cores the weakest section is situated in the conditions with those under ambient conditions.
middle of the cross-section, for more rectangular cores,
it is situated towards the bottom of the slab. The failure
occurs when the horizontal cracks meet the vertical
cracks. The phenomenon is of course influenced by
the slab thickness, level of the imposed forces, level of
prestressing and the total web width of the slabs.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 137
Table 10.1 expresses the shear capacity under fire Numerous fire tests in different laboratories have shown
conditions (VRd,c,fi) as a percentage of the shear that the FRP of hollowcore floors can be increased by
capacity in ambient (cold) conditions (VRd,c,cold ) for enhancing the aggregate interlock across cracks. The
a range of slab thicknesses and FRL. This shows that objective is to provide reinforcement and/or clamping
under fire conditions the effective shear capacity of forces that restrict the spread of the vertical and
un-topped hollowcore slabs can be reduced by over horizontal cracks shown in Figure 10.8. Methods used
50% and indicates that great care should be taken in include the following.
assessing shear capacity of hollowcore slabs in fire • a reinforced structural topping to tie the slabs to
particularly with deeper slabs and rectangular cores. the support, and during a fire prevent horizontal
For example a 200mm slab with a FRL90 has only 60% cracks in the lower part of the slab from opening.
shear capacity under fire compared with the calculated Structural toppings improve the fire resistance of
value at ambient temperature. hollowcore floors and are recommended where an
FRP is required.
The values in the table should be used as a guide only • tie bars in joints or in filled cores between the ends
and are based on the following relatively conservative of slabs. In order to decrease the lever arm of the
assumptions. induced force from the thermal curvature of the
• slabs are un-topped, no structural screed. floor, tie bars should be placed in the centre of the
• hollow core slabs are pre-stressed with strands cut hollowcore and not in the structural topping.
at the ends of the elements. • a shear ligature cage of reinforcement in filled cores
• a support length of 70 mm. at the ends of the slabs. The ligatures are designed
• longitudinal tie reinforcement of approximately to carry the full design shear forces.
200mm2/m is provided and placed at approximately • peripheral ties that contribute to the preservation
mid-height of the slab in joints between the slabs of the shear capacity of the hollowcore slabs when
and/or in filled cores. exposed to fire by forming perimeter beams that
• the influence of the concrete in the filled cores with resist directly and indirectly the expansion of the
embedded tying reinforcement is neglected. floor and hold adjacent slabs together.
FRL 60 70 % 65 % 60 % 60 % 55 %
FRL 90 65 % 60 % 60 % 55 % 50 %
FRL 120 60 % 60 % 55 % 50 % 50 %
FRL 180 45 % 50 % 50 % 45 % 45 %
Figure 10.8 Example of the shear capacity under fire conditions (VRd,c,fi)
as a percentage of the shear capacity in ambient (cold) conditions (VRd,c,cold )
138 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10.6 Fire resistance of
structural connections
The principles and solutions applied for the fire 10.6.3 Floor to concrete beam
resistances of structural components are also valid
for the design of connections, namely, minimum
connections
cross-sectional dimensions and sufficient cover to the The connections tying precast floors to supporting
reinforcement. The design philosophy is based on the beams are within the depth of the slab and in the colder
large insulating capacity of concrete. Most concrete zone of the structure, and hence not affected by the
connections will normally not require additional fire. The position of the longitudinal tie reinforcement
measures. This is also the case for supporting details (longitudinal means in the direction of the floor span)
such as bearing pads, since they are protected by the should preferably be in the centre of the floor thickness.
surrounding components. Other considerations are
related to the ability of the connection to absorb large In case of slabs that are continuous across the support
displacements and rotations due to thermal movements. sufficient continuous tensile reinforcement should be
Some considerations regarding specific connections are provided in the floor to cover possible induced positive
given below. and negative moments due to thermal movement.
10.6.1 Beam to column connections All of the connection types shown and described in
Chapter 7.3.6 are inherently fire resistant.
Typically beam to column connections are pinned
and perform well during a fire because of their high
rotational capacity. Pinned connections are a good
solution to transfer horizontal forces in simple supports.
They need no special considerations since the dowel is
well protected by the surrounding concrete. In addition,
dowel connections can provide additional stiffness to
the structure because of their semi-rigid behaviour. This
is normally not taken into account in the design, but
provides a reserve in safety. Care should be taken to
ensure that rotation can occur at the connection without
concrete to concrete contact causing spalling.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 139
10.6.4 Floor slab to steel beam
connections
In the typical case where a precast floor structure
is supported on top of a steel beam, the beam will
require some type of fire protection to meet any FRP
requirements. The connection between the beam itself
and the precast floor is protected within the depth of
the floor and hence not affected by the fire.
140 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
10.6.5 Floor to wall connections 10.6.6 Inserts and fixings
As shown in Chapter 7.3.6 there are many combinations Mechanical fixing devices should be protected to the
of floor to wall connections with different precast floor same degree as other structural members. Steel parts
types and different wall types. All except the steel corbel embedded in concrete will have a lower temperature
detail are inherently fire resistant. rise than non-embedded steel because of the thermal
conductivity of the surrounding concrete. However, it is
Where the precast floor is supported on a steel corbel as always recommended to provide sufficient protection
shown in Figure 10.12 the tie reinforcement and vertical to exposed parts of the connecting items, such as
leg of the corbel are protected by the concrete. bolts, steel angles etc. to ensure that yielding due to
degradation from the fire cannot occur.
For low to moderate design actions, fire protection of
the exposed steel ledge can be avoided by provision of Fixings should also be detailed to ensure that they can
reinforcement ties between the floor and the wall. These accommodate any forces or rotations that result from
ties are designed to support the design actions for fire thermal movement.
by activating shear-friction at the interface.
Chemical fixings should not be used in connections
In the case of hollowcore slabs the cores containing where an FRP is required.
tie bars should be filled with concrete over the critical
transfer length at the support and for hollowcore slabs 10.6.7 Joints
with high design loads or high FRP it is recommended
to protect the exposed steel flange by a fire insulating Joints between precast elements must be detailed in
material. such a way that they comply with the required criteria
for structural adequacy, integrity and insulation.
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 141
10.7 Establishing FRP by
testing
Tests are usually performed on simply supported Because of the limited size of test furnaces (normally up
elements, with imposed actions corresponding to the to 4 to 6 m length), and the fact that spans of precast
imposed (reduced for fire) action combination. Over elements are ranging from 6 to 20 m, tests are not really
the past 30 years, many tests and associated research relevant to the global performance of the structure and
work on precast beams, columns, double T elements other methods are needed for the assessment of the
and hollow core slabs, have been carried out. The work overall FRP of concrete buildings. This usually requires
covered a wide range of cross-sections together with the designer to look at the issues from first principles
variations in reinforcement quantities and position, and to assess how the building structure will perform
cover to soffit and lateral surface, etc. as a whole.
10.8 Conclusion
As previously noted concrete buildings have an
inherently high FRL and that the global performance
of the building is much more important than the FRP
of individual elements. This is particularly the case
for precast concrete buildings where connections
between discrete elements can be subject to significant
unanticipated load reversals under fire conditions.
142 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
11 DEMOLITION AND
DISMANTLING
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 143
11.2 Structural assessment
for demolition
An integral part of the safe dismantling or demolition The engineer responsible for assessing the demolition
of a precast concrete building is the assessment of process should consider each concrete element
the structure by a designer with expertise in building individually as the scope and nature of the work for each
construction and demolition. Where possible this concrete element may be different. A written statement
should include an assessment of the original structural should be produced that outlines how best to ensure the
design drawings as part of the evaluation process before stability and overall integrity of the building or structure
prescribing the method of demolition. Where original during demolition along with specific processes or
drawings are not available it may be necessary to carry procedures to follow during demolition. The engineer
out an investigation of the structure to determine the as should be satisfied that the prescribed method of
built details. Even with access to the original structural demolition is safe.
design drawings the engineer should satisfy themselves
that the drawings reflect the actual as-built structure.
144 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
11.3 Safe design for
demolition
Based on the proposed demolition sequence a detailed To eliminate or minimise work health and safety risks
design and associated work method statement should that may occur during the demolition process, a hazard
be prepared by the engineer and the demolition identification and risk assessment should be carried out
contractor that clearly defines the demolition process by the engineer and demolition contractor during the
and method. demolition design process.
The engineer is best placed to advise on how to A detailed work method statement should then be
treat connections and associated temporary works prepared that incorporates the demolition design and
requirements and should produce detailed step-by-step step-by-step work sequence.
drawings showing each phase of the demolition process
including how each element is to be lifted from the Further guidance on the safe design of buildings and
structure. structures, including demolition, is available in the Code
of Practice: Safe Design of Structures. [38]
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 145
11.4 Demolition or
dismantling process
During the demolition or dismantling process adequate
control measures should be maintained to ensure that
all aspects of the structure are as anticipated in the work
method statement. No deviations should occur without
the written approval of the demolition engineer.
146 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
12 REFERENCES &
LITERATURE
12.1 References
1. Federation Internationale du Beton. fib. 15. National Precast Concrete Association Australia.
(International Federation for Structural Concrete) International Federation for Structural Concrete.
Lausanne Switzerland. www.fib-international.org Precast/Prestressed Concrete Institute, USA.
2. ‘Precast Concrete Handbook.’ National Precast 16. ‘European Product Standard EN-1168.2005
Concrete Association Australia, plus amendment A3’ European committee for
www.nationalprecast.com.au standardisation. (CEN)
3. ‘Code of Practice, Tilt-up and Precast Concrete in 17. ‘Building code requirements for structural
Building Construction’ Safe Work Australia concrete. ACI 318’ American Concrete Institute.
www.concrete.org
4. ‘PCI Design Handbook’. Precast/Prestressed
Concrete Institute, USA. www.pci.org 18. ‘Bulletin 74, Planning and design handbook
on precast concrete building structures’ fib.
5. ‘Guide to good practice, Special design
ISBN 978-2-88394-114-4
considerations for prestressed hollow core floors’.
fib. ISBN 978-2-88394-046-8. 2000 19. ‘Precast Seismic Structural Systems (PRESS) frame
systems’. National Science Foundation USA and
6. ‘Bulletin 41, Treatment of imperfections in precast
Precast/Prestressed Concrete Institute, USA.
structural elements’ fib. ISBN 978-2-88394-081-9.
2007 20. ‘Guidelines for the use of Structural Precast Concrete
in Building’s’ New Zealand Concrete Society.
7. ‘Australian Standard, AS3600 Concrete structures
www.concretesociety.org.nz
code’ Standards Australia
21. ‘Multi-storey Precast Concrete Framed Structures,
8. ‘Bulletin 78. Precast concrete buildings in seismic
2nd edition’ Elliott, K S and Jolly, C. John Wiley,
areas. fib. ISBN 978-2-88394-118-2. 2016
London.
9. ‘State-of-the-art report. Precast concrete in mixed
22. ‘Eurocode EN 1991-1-7, Actions on structures’
construction.’ fib. ISBN 978-2-88394-059-8. 2002
European committee for standardisation. (CEN)
10. ‘National Construction Code’ and ‘Building Code of
23. ‘Australian Standard, AS1170, Structural Design
Australia’. Australian Building Codes Board
Actions’ Standards Australia
11. The Concrete Institute of Australia.
24. ‘Eurocode 2, Design of concrete structures’
www.concreteinstitute.com.au
European committee for standardisation. (CEN)
12. Cement Concrete & Aggregates Australia.
25. ‘Bulletin 63, Design of precast concrete
www.concrete.net.au
structures against accidental actions’ fib.
13. ‘Technical Report 93/2, Fire performance of one ISBN 978-2-88394-103-8. 2012
and two storey buildings with precast concrete ….’
26. ‘Adverse effects in high strength concrete when
CSIRO division of Building, Construction and
exposed to fire’ Sanjajan G, Concrete Institute of
Engineering.
Australia 2011
14. ‘Guide to good practice, Composite floor structures’
27. ‘Bulletin 43, Structural connections for precast concrete
Fib
buildings’ fib. ISBN 978-2-88394-083-3. 2008
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 147
28. ‘Australian Standard, AS 4100, Steel Structures 38. ‘Code of Practice, Safe Design of Structures.’
Code’ Standards Australia Safe Work Australia. July 2012
29. ‘Detailing Manual’. Hollow Core Concrete P/L 39. ‘Code of Practice, Demolition work.’
Altona Nth, Victoria Safe Work Australia
30. ‘Precast prestressed hollow core floors’ fib. 40. ‘Practical Guide to Structural Robustness and
Disproportionate Collapse in Buildings. October
31. ‘Australian Standard, AS1530.4, Fire test methods’
2010’. The Institution of Structural Engineers, UK
Standards Australia
41. ‘How to Design Concrete Buildings to satisfy
32. ‘CEB Bulletin 208, Fire design of concrete structures’
Disproportionate Collapse requirements’.
European committee for standardisation. (CEN)
The Concrete Centre. UK
33. ‘Hollowcore flooring technical manual’
42. ‘NSTR 7396.Best Practices for Reducing the
National Precast Concrete Association Australia
Potential for Progressive Collapse in Buildings’.
34. ‘British Standard BS 8110, Structural use of concrete’ National Institute of Standards and Technology,
British Standards Institute USA.
35. ‘Australian Standard, AS3850 Prefabricated 43. ‘Understanding Grouted Precast Joints,
Concrete Elements’. a guide for Engineers and Contractors’.
36. ‘Fire Safety of Concrete Buildings’. National Precast Concrete Association Australia,
Cement Concrete & Aggregates Australia
37. ‘Seismic Design of Reinforced Concrete and
Masonry Buildings’. Paulay T and Priestly N J.
John Wiley and Sons 1992
148 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
12.2 Literature
Elliott, K.S. & Jolly, C.K. ‘Multi-storey Precast Concrete Fédération Internationale du Béton, (fib), Bulletin 43,
Framed Structures’, Second edition. John Wiley, London Structural Connections for Precast Concrete Buildings,
2013. ISBN 978-1-4051-0614-6. Guide to Good Practice, 370 pp, February 2008
Elliott, K. S., Precast Concrete Structures, 2nd edition. Manual for the design of hollow core slabs - 2nd
CRC Press / Taylor Francis, Florida, edition; PCI Precast Prestressed Concrete Institute
Both these books are excellent reference works covering 175 West Jackson Boulevard, Chicago, Illinois 60604 -
the design, detailing and construction of precast skeletal ISDN 0-937040-57-6
structures. They also contain numerous calculation
examples of precast skeletal structures. Recommendations for design of wall-slab connections
- Matti Pajari, VTT Technical Research Centre of Finland
National Precast Concrete Association Australia, - VTT Building and Transport.
‘Precast Concrete Handbook’. National Precast Concrete
Association Australia and Concrete Institute of Australia FIP Recommendations “Precast prestressed hollow
core floors” - FIP Commission on Prefabrication,
Federation Internationale du Beton. (fib). Bulletin 74, Thomas Telford 1988 - ISBN 0 7277 1375 2
Planning and design handbook on precast building
structures. ISBN 978-2-88394-114-4. 2014 FIP Guide to good practice “Composite floor
structures” - FIP Commission on Prefabrication,
Precast/Prestressed Concrete Institute, ‘PCI Design SETO 1998, ISBN 1 874266 38 7
Handbook’. Precast/Prestressed Concrete Institute, USA
Matti Pajari, Shear resistance of hollow core slabs
Hasan, Elliott and Ferreira. Experimental investigation on beams. Summary of projects FS and FS11.
on the moment continuity of precast concrete Internal report 4/1995. Technical Research Centre
beam-column connections under gravity loads. Finland (VTT)
Fédération Internationale du Béton, (fib) Symposium,
Prague 2011. ISBN 978-80-87158-29-6 Shear resistance of prestressed hollow core floors
exposed to fire - Arnold Van Acker - journal of the fib
Fédération Internationale du Béton, (fib), Bulletin Structural concrete. 2003. 4. N° 2
19, Precast Concrete in Mixed Construction,
State-of-art Report, 68 pp, 2002 EN 1168: CEN Standard Precast concrete products -
Hollow core slabs for floors
Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd 149
150 Precast Concrete Design Guide © Hollow Core Concrete Pty Ltd
151