FMM Manish
FMM Manish
MICRO PROJECT
TITLE OF PROJECT
2
Gather information of hydroelectric
power plants
Member details
3
Name of member Roll Enrollmen Seat no.
Sr no. t no
no.
1.
2.
3.
4.
Name of Guide
MAHARASHTRA STATE
BOARD OF TECHNICAL EDUCATION
4
Certificate
This is to certify that Mr. Manish Gaykar, Roll No. 609 of 4rd
Semester of Diploma in Mechanical Engineering of Institute,
ShivajiRao .S. Jondhale Polytechnic, Ambernath (E) (Code:
0147) has completed the Micro Project satisfactorily in
Subject – Fluid Mechanics and Machinery (22445) for the
academic year 2023- 2024 as prescribed in the curriculum.
Sign of Student
MAHARASHTRA STATE
BOARD OF TECHNICAL EDUCATION
5
Certificate
Sign of Student
MAHARASHTRA STATE
BOARD OF TECHNICAL EDUCATION
6
Certificate
Sign of Student
MAHARASHTRA STATE
BOARD OF TECHNICAL EDUCATION
7
Certificate
Sign of Student
8
INDEX
2. Working
5. Lake tapping
9
Hydroelectric power plants
10
Working of Hydroelectric Power Plant
11
5. Transmission and Distribution:
The electricity generated by the hydroelectric plant is then stepped up
to higher voltages for efficient transmission over long distances
through power lines.
Finally, the electricity is stepped down to usable voltages for
distribution to homes, businesses, and industries.
12
Advantages and Disadvantages of Hydroelectric Power Plant
13
14
Gather information of hydroelectric power plants in
Maharashtra -koyana dam
The koyana Dam is one of the largest dams in Maharashtra, India. It is a rubble
concrete dam constructed on koyana River which rises in Mahabaleshwar, a hill
station in the Sahyadri ranges. It is located in koyana Nagar, Satara district,
nestled in the Western Ghats on the state highway between Chiplun and Karad.
The main purpose of the dam is hydroelectricity with some irrigation. Koyama
Hydroelectric Project is the largest completed hydroelectric power plant in
India having a total installed capacity of 1,920 MW. Due to its electricity
generating potential Koyama river is considered the 'lifeline of Maharashtra.
History
>In the early 20th century, there was a survey of the koyana River as a
hydroelectric source by the Tata Group.
> The 1928 financial crisis caused the project to be shelved.
> After the independence of India, it was taken over by the Government of
Maharashtra.
15
> In 1951 koyana Dam division started to look into the project. The project was
approved in 1953 and work commenced in early 1954 and was completed in
1962
Features
Dam and spillways
Type of dam-Rubble-concrete dam
impounds-Koyna River
Height-103.2 m (339 ft)
Length-807.2 m (2,648 ft)
Reservoir Creates -Shivajinagar Lake
Total capacity -2,797,400,000 m3 (2,267,900 acre . ft)
Surface area-891.78 km2 (344 sq mi)
The spillway of the dam is located at the center. It has 6 radial gates. The dam
plays a vital role in flood control during monsoon season.
The catchment area dams the koyana river and forms the Shivajisagar Lake
which is approximately 50 km (31 mi) in length. It is one of the largest civil
engineering projects commissioned after Indian independence. The koyana
hydroelectric project is run by the Maharashtra State Electricity Board.
Repairs of dam
In 1973 the non-overflow portion of the dam was strengthened, followed
by the strengthening of the spillway section in 2006.
Also, internal holes were drilled to relieve the hydrostatic pressures in the
body of the dam.
an Indian scientific establishment has formulated an ambitious project to
drill a deep borehole in the region and intensely study earthquake activity.
Now the dam is expected to be safe against any future earthquake even of
more intensity than that of 1967.
16
17
koyana Hydroelectric Project
18
Stage I and II
> 1st and 2nd stages share the same powerhouse with a total of eight Pelton
turbine units.
> Capacity, four turbines having of 65 MW each for 1st stage and 75 MW each
for 2nd stage.
> The water from The Shivajinagar reservoir is taken through an intake
structure known as Navja tower near the village of Navja into the headrace
tunnel.
> Then it travels towards the surge tank. It is further divided into four pressure
shafts which run vertically downward delivering water to the turbines.
> A dam foot powerhouse was also constructed which is used to generate
electricity by the water which is discharged from the koyana Dam for irrigation
purposes.
19
> It has two Francis turbine units of 20 MW each. This powerhouse is run
according to the irrigation requirements of the downstream areas.
> The combined installed capacity of the two stages and the dam foot
powerhouse is 600 MW.
Stage III
• It was observed that the water still had a hydraulic head of about 120 m which
could be used.
• To use this head, the Kolkewadi Dam was constructed at this location.
• It forms a balancing reservoir and maintains the head.
• This dam impounds the tailrace water from Stage 1 and II.
• This water is drawn through penstocks and electricity is generated by four
Francis turbine units with a capacity of 80 MW each
• the tailrace water from these stages then flows through a channel and joins the
Arabian Sea near Chinlun.
• The installed generating capacity of this stage is 320 MW.
Stage IV
• Later in the 1980s, the electricity demand of Maharashtra increased
tremendously resulting in inadequate power supply.
• This scheme also draws water from the existing Shivajinagar reservoir same
as Stages I and II.
21
Lake tapping
The water in the headrace tunnel is directly drawn from the reservoir and
delivered to the head surge tank. The four huge Francis turbine units of
250 MW each generate electricity and tailrace water is taken into the
Kolkewadi Dam reservoir through the tailrace tunnel. A revolutionary
gas-insulated switchgear system is used in the underground powerhouse
of this stage. The installed capacity of this stage alone is 1000 MW. This
stage is mostly used to cater to the peak hour demands of the electric grid.
22
Stage Unit number Installed capacity ( MW) Date of commissioning Status
Stage 1 70 1962 May Running
Stage I 2 70 1962 August Running
Stage I 3 70 1963 January Running
Stage I 4 70 1963 February Running
Stage II 5 80 1967 June Running
Stage II 6 80 1966 November Running
Stage II 7 80 1966 June Running
Stage II 8 80 1966 March Running
Stage III 9 80 1975 July Running
Stage III 10 80 1976 January Running
Stage III 11 80 1977 May Running
Stage III 12 80 1977 Running
Stage IV 13 250 1981 Running
Stage IV 14 250 1981 Running
Stage IV 15 250 1981 Running
Stage IV 16 250 1981 Running
23
Shivaji Rao S. Jondhale polytechnic, Ambernath
Academic Year 2023-2024
Teacher Evaluation sheet for Micro project
Program title: Mechanical Engineering
Course
Semester: Fourth
Name of student: -
Signature:
24
Weekly progress report of Microproject
25