Deliverable 6: Team GM2
Deliverable 6: Team GM2
Team GM2
GM2
Lane Ballard Amber Mazooji
Tom Burns Minja Penttila
John Celmins Chris Piscitelli
Paul Glomski Tomer Posner
1
Tray Table 3D-Positional View
Closed Position
2
Armature – 3D View
Pull Here
To Lower
Ratchet Latch
(spring retains pressure) Ramp Converts
Downward Force To
Inward Force
3
4
5
6
7
8
9
10
11
12
13
14
15
Structural Analysis
The loads we predict for the tray-table are much too small to The deflections derived are quite insignificant for our product.
cause failure or breakage. Our main concern is for the flexure Instead, we believe that the real danger for the table “giving”
of the system during usage. under loading are the interfaces between the components. We
paid special attention to these in our detailed design, and
The rods and table are each unlikely to show much bending, as intend to build the prototype in a way that will prove this
shown by the calculations below: physically.
Table
Length 0.5 Meters (runs L-R for passenger)
W idth 0.2 Meters
Thickness 0.0125 Meters
Rod
Radius 0.005 Meters
Length 0.2 Meters
16
Bill of Materials (BOM)
Part Prototype
Number Part Name Quantity Image Prototype Material Manufacture
The Bill of Materials (BOM) includes the required manufacturing processes. We have purchased
a standard Cadillac SRX armrest, and plan to manufacture most of the rest of the pieces, as
noted in the BOM.
Web resources:
McMaster offers a wide range of products and supplies:
http://www.mcmaster.com
We purchased an arm rest from a Cadillac dealer found on the Cadillac corporate web site. The
purchase was necessary because we have yet to receive parts directly from GM.
http://www.cadillac.com/
18
Production Sketch
19
Production Sketch
20
Updated Schedule
GM Lap Tray - Team #2
Page 1 of 1 4/12/04
Final Presentation
Preparation 4/29 5/9
21
Process Notes
Process Reflection
• The major difficulty in this period was to decide whether to stay with the original concept idea of detachable table after receiving critique during
both the GM presentation and advisor meetings. To assist the decision making, the team conducted yet another customer survey focusing on
target customer market of “soccer mums”. The results showed, that nobody in our target market would not buy the table because it is detachable.
The table would mainly be used during longer trips, in which case slightly more complicated “assembly” was not seen as a problem. Customers
noted that a detachable table would be easy to clean and replace if broken. Customers also mentioned that the concept would enable different
tray tops for different purposes. The main disadvantage was the fear of loosing the table.
• While the team realizes the many challenges, it was unanimously decided to stay with the selected concept. The reasons were:
– lack of time and resources to come up with an attached mechanism within the armrest that would meet the “must have” customer needs,
such as aesthetically pleasing, durable, and useful for children
– Importance of providing GM an alternative concept different from that of the other team’s
– encouraging feedback from target customer market
– the ability to accommodate big enough tray table, as indicated by the customer surveys
• For the product to be accepted by target market, it needs to have the feel of German quality, low enough price and good functionality (large
enough table to fit a coloring book). The team also faces the challenge how to convince the audience during final presentations. The major risk for
the selected concept is therefore uncertainty in customer survey information accuracy.
• Another issue, which is typical of the product development process, was lack of perfect information. To address this, the team purchased an
armrest from a Cadillac dealer.
Group Meetings 3/30, 4/1/2004
• Team was not in full strength due to holidays and illnesses. However, feedback from the GM presentation was seriously discussed, and viability of
our concept questioned. It was decided to conduct a customer survey with concept pictures, to compare the feedback from GM with input from the
target market.
• Individual tasks for the next lengthy assignment were divided.
Group Meeting – 4/6/2004
• Paul reviewed customer survey and interview feedback. After lengthy discussion of pros and cons the team members decided to stay with the
existing concept.
• The materials for final prototype were discussed; team decided to make a prototype that would provide the “wow” factor from an aesthetics
standpoint, but also provide enough functionality to demonstrate the concept. The team had not yet identified a machine shop to do the final
prototype.
Group Meeting – 8/4/2004
• Tomer managed to secure us the opportunity to use graduate students’ mechanical workshop.
• The schedule for assignment was checked and the team reviewed the status of the CAD drawings.
• Seats were still not available, but the team remained hopeful to receive a sample arm rest to use in building the final prototype.
Advisor Meeting – 8/4/2004
• The team met with Roemer, Kressy and Whitney to discuss the status of the project. Roemer and Kressy questioned the feasibility of the
detachable concept, but understood our reasoning to go forward with it. However, they highlighted the importance of convincing our audience
during the final presentation. Whitney gave good ideas for how to mechanically lock-in the table top.
22
MIT OpenCourseWare
https://ocw.mit.edu
For information about citing these materials or our Terms of Use, visit: https://ocw.mit.edu/terms.