This document provides a quantity survey for a slab culvert with a 1.5m clear span and 4m roadway. It includes 8 items describing various components of the culvert including earth works, foundations, brick work, deductions, cement pointing, string courses, PCC for the slab, and reinforcement. Quantities for length, breadth, height and units are provided for each item.
This document provides a quantity survey for a slab culvert with a 1.5m clear span and 4m roadway. It includes 8 items describing various components of the culvert including earth works, foundations, brick work, deductions, cement pointing, string courses, PCC for the slab, and reinforcement. Quantities for length, breadth, height and units are provided for each item.
prepare a quantity survey of slab culvert of 1.5m clear span and 4 m roadway as shown in drawing below
foundation 1:2:4 PCC
Brick Work Frisrt class 1:4 Exposed Part Should be pointed 1:2 C/S up to 15cm below ground String Course 8cm Deep and 12cm Thick 1:4 C/s
SN Description of Works No. Length Breadth Height Quantity Unit Remarks
1.0 Earth Works in Excavation Abutment Walls 2.0 5.30 0.75 0.75 5.96 5.3=5+0.15+0.15 Wing Walls 4.0 1.40 0.75 0.75 3.15 1.4=1.4-0.15+0.15 Total 9.11 Cum 2.0 PCC in Foundation (1:2:4) 2.1 Abutment Walls 2.00 5.30 0.75 0.30 2.39 Wing Walls 4.00 1.40 0.75 0.30 1.26 Total 3.65 Cum 3.0 First Class Brick Work 3.1 Abutment Walls 2.0 5.00 0.45 1.55 6.98 1.55=0.45+0.9+0.2 Wing Walls 4.0 1.40 0.45 1.55 3.91 Parapet Walls 45 cm thick 2.0 5.30 0.45 0.33 1.57 0.33=0.25+0.08 Parapet Walls 35 cm thick 2.0 5.30 0.35 0.40 1.48 4.0 Deductions 4.1 Bearing of RCC Slab (2.0) 5.00 0.30 0.20 (0.60) Total 13.34 Cum 5.0 Cement pointing/plaster 15 cm Below bed Inner faces the abutments 2.0 5.00 - 1.05 10.50 Level to below 1.05=0.9+0.15 slab Face walls 2.0 5.30 2.02 21.41 Or 2.02=0.15+1.3+0.25+0.4-0.08 Inner side of parapets 2.0 5.30 0.65 6.89 2 of 2
Slab Culvert 2018 Spring
prepare a quantity survey of slab culvert of 1.5m clear span and 4 m roadway as shown in drawing below
foundation 1:2:4 PCC
Brick Work Frisrt class 1:4 Exposed Part Should be pointed 1:2 C/S up to 15cm below ground String Course 8cm Deep and 12cm Thick 1:4 C/s
SN Description of Works No. Length Breadth Height Quantity Unit Remarks
End of parapet(45cm) 4.0 0.45 0.33 0.59 4=2*2 End of parapet(35cm) 4.0 0.35 0.40 0.56 4=2*2 Deductions Rectangular Opening (2.0) 1.70 1.05 (3.57) Triangular opening of face wall hidden by (4.0) A= 0.98 (3.92) A=1/2*1.4*1.4 1.25=1.4-0.15 earth filling Total 32.47 Sqm 6.0 String Course (8cm*12cm) 6.1 2.0 5.30 - 10.60 Total 10.60 Rm 7.0 PCC for RCC in slab - PCC for RCC in slab 1.0 5.00 2.30 0.20 2.30 2.3=1.7+0.3*2 Total 2.30 Cum 8.0 Reinforcement - Along short direction (16mm bar) 51.0 2.30 w/m= 1.58 184.96 Along long direction (10mm bar) 12.0 5.00 w/m= 0.62 37.00 Total 221.96 Kg