Maximizing Reliability by Optimal Siting of Distributed Generation and Protective Devices.
Maximizing Reliability by Optimal Siting of Distributed Generation and Protective Devices.
R by Optimal Siting
S of
Distributed Generation and Protectivee Devices
Maurice Tristan G. Donalvo
Adonis Emmanuel DC. Tio
Wilbert Rey D. Tarnate
Eleectrical and Electronics Engineering Institute
University of the Philippines Diliman
Quezon City, Metro Manila, Philippines
[email protected]
[email protected]
[email protected]
Abstract— The placement of protective andd switching devices, Average Interruption Frequeency Index (SAIFI), System
as well as distributed generation (DG), affecct the reliability of Average Interruption Duration Index (SAIDI), and Momentary
distribution systems. Existing placement methodologies
m give Average Interruption Frequenccy Index (MAIFI) or by using
suboptimal solutions since device placem ment is optimized cost indices.
separately from DG placement, and vice verssa. In this paper, a
binary formulation for the System Average Interruption In these studies, differentt optimization algorithms have
Frequency Index (SAIFI) as a function of thee locations of fuses, been used. Some studies have used
u the deterministic method in
reclosers, and DGs is developed. Commercially-available obtaining the optimal locationn of these devices [2,3,5,6,7,9],
optimization software is used to minimize SAIFI to get the while some have used heuristtic method such as the Genetic
optimal location of fuses, reclosers, and DGs, subject to various Algorithm [4,8,11,12], ant-coloony algorithm [10], and binary
constraints. Using this methodology, the t simultaneous particle swarm algorithm [13]. We can see that studies
optimization of fuse, recloser and DG placemment is achieved for regarding finding the optimal location of protective devices
maximum reliability. have been done using either thhe deterministic or the heuristic
approach. On the other hand, studies regarding finding the
Keywords— Reliability; SAIFI; Protective Devices;
D Distributed optimal location of both protective devices and DGs have been
Generation done using only the heuristic method.
m
I. INTRODUCTION In this paper, a binary moodel for SAIFI is presented and
The goal of the distribution system iss to continuously used to determine the location of “fuse-blow” and “fuse-save”
supply power to their customers, achievinng high reliability. fuses, reclosers, and distributted generation that will yield
However, because of certain factors like eqquipment failures, optimum system reliability. Havving the binary model for SAIFI
vehicular accidents, weather conditions, and many more, will allow the use of determ ministic methods in finding the
customers experience interruptions [1]. These factors, optimal location of protective devices
d and DGs.
combined with the fact that the distribution system is radial in
nature, add up to low distribution system reliaability. II. OPERATION OF RAD
DIAL DISTRIBUTION SYSTEM
2) Recloser where:
Reclosers are protective devices that have both fault- = permanent failure rate of section i
interrupting and reclosing capabilities. Reclosers will open
whenever they detect faults, thus cutting the flow of current = momentary failure rate of section i
from the source to the loads downstream of the device. = repair rate of section i
Because of their reclosing capability, recloser “recloses”. It
checks whether the fault is still there, since faults can be = number of customers at section i
momentary. If the fault still exists, then it opens again. After = total number of customers.
some preset number of times, the recloser will reach its lockout
state. At lockout state, the recloser will be permanently open
until an action is made.
III. METHODOLOGY
Before formulating the binary model for SAIFI, a test
system was developed to represent a general distribution 1 4
system in the smallest size possible. A reliability calculator
based on the load-point method [14] was developed in order to
validate the results of the binary formulation.
In the optimization problem, the objective function is the 1
SAIFI of the system. The SAIFI formulation is a function of ,
5
the location of both the protective devices and DGs. From [7],
the binary formulation for SAIFI as a function of location of
,
protective devices is already determined.
To determine the SAIFI formulation considering the
location of both protective devices and DG, the following
1
assumptions were considered:
• DGs have unlimited capacity. Thus, cost will not be a
part of the objective function. 6
,
• DGs operate in the grid-parallel mode.
• DGs are non-intermittent. 1
• DGs have on-site recloser for overcurrent protection.
• DGs have zero failure rates.
• Voltage profile, line loss, and power quality are not 1
considered. , ,
shown in Figure 2. The reliability parameters are shown in 5. Fuses cannot be installed in the main feeder.
Table II.
6. DGs can only be installed in the main feeder.
TABLE II. RELIABILITY PARAMETERS OF THE DEVELOPED TEST 7. Recloser is installed in section 1.
SYSTEM
Section λ γ r Customers
The three test case studies are as follows:
1 0.1 0.2 0.5 100
3 0.2 0.3 1 125 Case 1 - Fixed Location of Devices, Optimal Location of DG:
Case 1 represents the situation of finding the optimal
4 0.15 0.3 1.25 500
location of DG given that the locations of the protective
5 0.3 0.1 1.2 300 devices are fixed. Table III shows the assumed location of
8 0.6 0.3 3 50 protective devices for the purpose of discussion in this paper.
9 0.25 0.4 2.5 1000
11 0.4 0.3 3 400 TABLE III. FIXED LOCATION OF PROTECTIVE DEVICES FOR CASE 1
12 0.4 0.6 4.5 200 Fuse with fuse- Fuse with fuse-
Recloser
13 0.5 0.55 2 250 blow scheme save scheme
16 0.3 0.4 5 100 1,2,7,12 5 3,11,13
17 0.4 0.5 5 50
18 0.7 0.9 4.7 40
Case 2 - Fixed Location of DG, Optimal Location of Devices:
Case 2 represents the case of finding the optimal location of
From the figure, the candidate locations for protective protective devices given that the location of the DG is fixed. In
devices are denoted by a square, while the candidate locations this case study, we will assume that a DG is installed in
for DG are denoted by a circle. In total, there are 18 candidate Location 26.
locations for protective devices and 12 candidate locations for
DG. TABLE IV. RESULTS OF THE THREE TEST CASES
In these case studies, the developed test system has the Fuse with Fuse with
Distributed
following constraints: Case Recloser fuse-blow fuse-save SAIFI
Generation
scheme scheme
1. Only four reclosers are available. 0 1,7,12,15 5 3,11,13 N/A 0.7277
2. Only four fuses are available. 1 1,2,7,12 5 3,11,13 20 0.6823
3. Only 1 DG is available. 2 1,7,10,12 5 3,11,13 26 0.5367
4. One fuse-blow fuse must be installed in the system. 3 1,4,7,12 6 11,13,15 29 0.5154
Case 3 - Optimal Location of Devices and DGs: system and (2) the optimal location of protective devices and
Case 3 represents the case of simultaneously finding the DGs are, indeed, dependent on each other and thus,
optimal location of protective devices and DG. simultaneously optimizing both of them will yield better
system reliability.
The result of the three test cases is shown in Table IV. Note
that Test Case 0 is a base test case. This test case shows the REFERENCES
optimal location of protective devices given that no DG is [1] R. Brown, “Electric Power Distribution Reliability”, CRC Press, Taylor
installed in the system. From the results, we can conclude the and Francis Group, 2009.
following: [2] F. Soudi and K. Tomsovic. “Optimized distribution protection using
binary programming,” IEEE Transactions on Power Delivery, Vol. 13,
No. 1. 1998. Page(s) 218-224.
1. The location of protective devices affects the optimal [3] E. Zambon, D. Bossois, B. Garcia, E. Azeredo. “A novel nonlinear
location of DG. This can be seen on Test Cases 1 and programming model for distribution protection optimization”, IEEE
3. In Test Case 1, the location of the protective devices Transactions on Power Delivery, Vol. 24, No. 4, 2009, Page(s) 1951-
is fixed, leading to a solution where the optimal 1958
location of DG is on location 20. However, from the [4] L. da Silva, R. Pereira, J. Mantovani, “Allocaton of protective devices in
result of Test Case 3, a different set of location of distribution circuits using nonlinear programming models and genetic
algorithms,” Electric Power Systems Research, Vol. 69, 2004, Page(s)
protective devices have led to a different optimal 77-84.
location of DG. This time, the optimal location of DG [5] R. Bupasiri, N. Wattanapongsakorn, J. Hokierti and D. Coit.“Optimal
is on location 29. electric power distribution system reliability indices using binary
programming,” Annual Reliability and Maintainability Symposium,
2. The location of DG affects the optimal location of 2003. Page(s) 556-561.
protective devices. This can be seen on Test Cases 2 [6] F. Soudi and K. Tomsovic. “Optimal trade-offs in distribution protection
and 3. In Test Case 2, the location of the DG is fixed at design,” IEEE Transactions on Power Delivery, Vol. 16, No. 2, 2001.
location 26, leading to the optimal location of Page(s) 292-296.
protective devices when the DG is installed at location [7] A.E.D.C. Tio, I.B.N.C. Cruz, B.M. Malquisto, R.D. del Mundo. “A
26. However, from test case 3, a different location of binary programming model for reliability optimization considering fuse-
DG has led to a different optimal solution. blow and fuse-save schemes.” TENCON 2012 – 2012 IEEE Region 10
Conference, 2012, Page(s) 1-6.
3. Since the location of DG affects the optimal location of [8] W.R.D. Tarnate, I.B.N.C. Cruz, B.M. Malquisto, R.D. del Mundo.
protective devices, and on the other hand, the location “Maximizing service restoration in reliability optimization of radial
of protective devices affects the optimal location of distribution systems.” TENCON 2012 – 2012 IEEE Region 10
Conference, 2012, Page(s) 1-6.
DGs, then to improve further the reliability of the
[9] A.E.D.C. Tio, I.B.N.C. Cruz. “A binary formulation of SAIDI for the
system, DGs and protective devices must be optimized predictive reliability assessment of radial distribution systems with tie
simultaneously. The effect of it is seen on the third lines.” Page(s) 1-5.
case in Table IV. [10] L. Wang, C. Singh. “Reliability-constrained optimum placement of
reclosers and distributed generators in distribution networks using an ant
V. CONCLUSION colony system algorithm.” IEEE Transactions on Systems, Man, and
Cybernetics, Vol. 38, No. 6, 2008, Page(s) 757-764
In this paper, a binary formulation for SAIFI as a function
[11] Pregelj, M. Begovic, A. Rohatgi. “Recloser allocation for improved
of fuses, reclosers, and DGs was presented. It was used to reliability of DG-enhanced distribution networks.” IEEE Transactions
determine the optimal location of these devices to obtain on Power Systems, Vol. 21, No.3, 2006, Page(s) 1442-1449.
optimal system reliability. The developed binary formulation [12] Weiwei, W. Yafeng, L. Wenxia. “Optimal allocation of switches in DG
was validated by replicating published test results and by enhanced distribution systems.” Power and Energy Engineering
replicating results using a reliability calculator based on the Conference (APPEEC), 2011 Asia-Pacific, 2011, Page(s) 1-5.
load-point method. [13] W. Prommee, N. Pongprapunt, W. Ongsakul. “Improved reliability
model and optimal protective device placement in micro grid by
The binary formulation was then used to determine the improved binary particle swarm optimization,” 8th International
optimal location of fuses, reclosers, and DGs of a sample Conference on Power Electronics – ECCE Asia. 2011. Page(s) 1514-
feeder. Commercially-available software such as MS Excel and 1519
MATLAB were used in the optimization process. [14] R. Billinton, R. Allan, Reliability Evaluation of Power Systems, 2nd
edition, Plenum Press, New York, 1996.
Test cases were developed to demonstrate the effect of [15] Sustainability Victoria, “Guide to Connecting a Distributed Generator in
simultaneously optimizing the location of protective devices Victoria,” www.sustainability.vic.gov.au, Accessed September 5, 2013
and DGs. It was demonstrated that (1) installing DGs in the [16] L.Willis. “Power Distribution Planning Reference Book.”Marcel Dekker
distribution system can definitely improve the reliability of the Inc., 2004.