Global Extraction Sequences in Sublevel Stoping: E Villaescusa
Global Extraction Sequences in Sublevel Stoping: E Villaescusa
E Villaescusa1
FIG 1 - Section view showing stoping blocks and details of top down extraction sequence at Mount Charlotte (after Ullah, 1997).
both sides. This means that the third stope within the strike slot
must wait until the second stope fill mass has cured. However,
later on the extraction sequence (stopes 7, 8, 10 and 11) are
sequenced to expose fill masses in both sides as shown in
Figure 5. A better alternative for stope sequencing is shown
conceptually before in Figure 3, where the fill masses are
exposed on a single surface and the adjacent stopes sequenced to
provide enough time for the filled stopes to cure.
FIG 3 - Plan view showing discontinuous strike slot sequence for a massive orebody.
continuously stepped out to access primary stoping blocks. number of fill exposures as mine life progresses. A chequer
The extraction was designed with large, 40 m by 300 - 400 m board sequence is dependent upon successful mass blasting
east-west transverse pillars for access, ventilation and services practices and the development of stable fill masses that provide
(Grant and DeKruijff, 2000). support to adjacent rock masses with minimal dilution during
The advantages of a properly designed chequer board multiple fill exposures.
extraction sequence includes stable primary stopes which must
be timely tight filled to provide support to the remaining stopes EXTRACTION SEQUENCES IN STEEPLY DIPPING
and crown pillar (Alexander and Fabjanczyk, 1982). A OREBODIES
disadvantage is the large amount of ore tied up within the
remaining tertiary stope pillars, where localised stope design can In the case of steeply dipping and relatively narrow orebodies,
be complex and a function of existing development and the the most common orebody access is via crosscuts off access
drives that are connected to ramps usually located in the footwall
of the orebodies. The crosscuts intersect the orebodies from
footwall to hangingwall and ore drives are developed from the
crosscuts along the strike of the intersected orebodies.
FIG 4 - Plan view showing stress shadowing across a series of FIG 5 - Plan view showing continuous stoping sequence
stopes. (after Trotter, 1991).
FIG 6 - Plan view of the 1100 Orebody showing major faults, extracted and scheduled stopes. Stope extraction advancing to the south
(August 1993).
Top down or bottom up bench stoping and allows for an optimised stress redistributions as the initial
stopes can be located in the centre of the mining block with
In cases where bench stoping is used (Villaescusa et al, 1994), subsequent retreat towards the abutments.
the stopes can be retreated towards the crosscuts using either a
top-down or a bottom-up sequence as shown in Figure 7.
A top down bench stope extraction sequences usually requires
Primary and secondary stope extraction
permanent rib pillars to minimise dilution between individual In cases where multiple lift sublevel stoping is used to mine
stopes along strike. In addition, a series of crown pillars maybe relatively wide orebodies, a series of primary and secondary
required to control overall stability, dilution and to isolate any stopes can be designed for extraction along the strike of a
unconsolidated fill that may be introduced into the upper stopes deposit. Stope extraction in multiple levels increases production
as extraction progresses downward (see Figure 8). A bottom up and flexibility. Primary stopes are excavated smaller than
sequence requires fill in order to provide a working floor as the secondary stopes (pillars) to minimise the use of cemented fill
extraction proceeds upward. The need for a crown pillar is and the secondaries are designed large enough to enable safe
minimised by the use of rib pillars along the strike of the orebody recovery between primary stopes. This method has been applied
and the beneficial impact of the fill masses (Villaescusa and widely in single tabular orebodies such as the Lead Mine in
Mount Isa Mines in Queensland and the Kanowna Belle gold
Kuganathan, 1998).
mine in Kalgoorlie. Figure 10 shows the stoping sequence for a
Flexibility and productivity in bench stoping can be greatly mining block where the extraction sequence was based upon a
enhanced with the introduction of two access crosscuts as shown primary stope extraction and filling with consolidated fill, before
in Figure 9. Although costly, this configuration increases tonnage the secondary pillars were extracted. The numbers on the figure
refer to the stope extraction sequence.
FIG 7 - Longitudinal view of top-down and bottom up sequences of FIG 9 - Longitudinal view of a sequence of extraction with double
extraction. access.
FIG 8 - Schematic of top-down up-hole bench extraction sequences, Osborne Mine (after Kasehagen and Boffey, 1998).
FIG 10 - Longitudinal view of a complete stoping block extraction using primary and secondary stoping geometries.
FIG 12 - Long section view of 8 and 5 orebodies at Mount Isa Mines showing layout and extraction sequence (after Bywater and Fuller, 1983).
A variation to this method has been implemented for the A disadvantage of a 1-5-9 (or 1-4-7) extraction sequence using
George Fisher orebody in Australia, where a 1-5-9 stoping short lift stopes is their inefficient stope mucking characteristics.
sequence has been selected for extraction (Neindorf and The method effectively requires (a bottom up) moving drawpoint
Karunatillake, 2000). Stopes 1-5-9 are extracted as two lift sequence (even in primary stopes), which necessarily follows the
vertical retreat of the stopes as shown in Figure 18. This implies
primaries and filled with consolidated fill (see Figure 17). This is
that mucking is carried out in areas that had previously been
followed by another set of primary two lift stopes (3-7-11), also subjected to stress distribution and stope blasting at the stope
filled with consolidated fill. Following the fill cure within the crowns. Each stope access becomes a stope drawpoint and a
primary stopes 1-3-5-7-9-11, a set of single lift stopes (2-6-10) is significant amount of reinforcement using cablebolting is
then extracted and filled with unconsolidated fill. This creates a required in all the stopes access and exposed backs.
pendant pillar, which has many degrees of freedom and relies on Reinforcement can be largely inefficient within the bottom of
the fill support from the primary stopes for stability. Finally, pendant secondary pillars where remote mucking is required for
the single lift stopes 4-8-12 are extracted and filled with 100 per cent of the tonnage. Furthermore, additional footwall
unconsolidated fill before the entire sequence is repeated up-dip. development access in waste may be required on each sublevel,
The extraction of stopes 4-8-12 also creates pendant pillars. as more than one access may be required for effective mucking
of each individual stope.
FIG 17 - Longitudinal section view of George Fisher orebody (Neindorf and Karunatillake, 2000).