Variable Density TBM - Combining Two Soft Ground TBM Technologies
Variable Density TBM - Combining Two Soft Ground TBM Technologies
This paper highlights the new generation of soft ground machines that
combine the two basic soft ground technologies in one and the same
machine. With the design of the new generation of multi-mode soft ground
machine it is possible to smoothly switch between the different modes
(EPB and Slurry) in the tunnel by maintaining permanent and full control of
face pressure, and without the need for excavation chamber interventions.
This new machine generation is called Variable Density TBM and offers
maximum safety and flexibility in the choice of tunnel face support and
discharge of muck.
Figure 1 – Multi-mode TBM for Socatop, slurry and earth pressure mode.
Development of Multi-mode Soft
Ground TBMs
The first multi-mode TBM was designed back in the 1980s for a tunneling
project that was built in variable ground conditions comprising stable to soft
rock, mixed face and water-bearing soils. Since then the technology has
been continually refined and updated to the high degree of maturity of
today’s available machine design, the Variable Density TBM (K. Bäppler,
W. Burger, 2016).
In 2000, a multi-mode TBM was successfully applied for the road tunnel
project Socatop in Paris. The project comprised the construction of the A86
West Tunnel that forms the final link of the 80-km A86 ring road around
Greater Paris. The tunnel has been built to relieve traffic congestion and
improve traffic links between the suburbs of Paris. The multi-mode TBM
that was used for the construction of this tunnel had a diameter of 11.56 m
and was at that time the first innovative TBM that could be operated in
EPB and slurry mode.
The tunnel was built by three of the biggest construction and road industry
companies in France – Vinci, Eiffage Construction and Colas. To justify the
significant effort of a machine design that is capable to completely change
from EPB to slurry mode in the tunnel there must be special project
conditions. The Socatop project featured such conditions. The tunnel has a
length of 10 km of which approximately 60% of the subsurface conditions
are soils suitable for the use of an EPB shield. The remaining 40% of the
alignment comprised an optimum condition for a TBM operation with a
slurry supported tunnel face. The TBM and tunneling concept for the
project considered in particular that the respective geological formations
occurred in long associated sections. Both slurry shields and EPB shields
are operated with a filled excavation chamber and a controlled support
pressure for the tunnel face. The major differences between the two
operation modes are the properties of the chamber filling such as viscosity,
shear strength, density and the type of chamber and face pressure control.
With slurry shields, the face pressure is controlled by a remote pressurized
air bubble that is in most cases provided by separating the excavation
chamber in two compartments by means of a submerged wall. With an
EPB shield the face pressure is controlled by the advance speed and muck
extraction volume via the screw conveyor speed.
The design of both cutting wheel and excavation chamber does not require
any compromises between the operation modes. The major mechanical
differences are muck transportation and muck handling systems in the
excavation chamber and in the tunnel. Slurry shields use a closed,
pressurized slurry circuit with a slurry treatment plant at surface; EPB
shields use a screw conveyor for controlled muck extraction out of the
excavation chamber and an open tunnel transport system with muck cars
or conveyors. The generous amount of space available with the large
diameter soft ground TBM for the Socatop project allowed the parallel
arrangements of both muck removal systems in the invert area of the
excavation chamber with some minor functional compromises. If slurry
operation was required in prevailing geological conditions with possible
blocks, boulders or larger stones, a jaw crusher could be moved in from a
parking position and activated in front of the suction grid. This required a
manual intervention and additional mechanical effort to change the
operation mode. With TBM diameters smaller than 8 m this becomes even
more difficult.
Tunnelling for the Miami Port Tunnel in the Biscayne Bay was realized in
porous and variable subsoil conditions of mainly sand and limestone and
chloride groundwater. Due to high ground permeability in the porous
formation and environmental concerns related to possible loss of slurry into
the Biscayne Bay aquatic preserve, an EPBM (Ø12.87m)
from Herrenknecht was selected to excavate and line the twin tube
tunnels. The TBM could be adapted to deal with the variable ground
conditions of locally high permeability where it was required to control the
water and extract the rock at the tunnel face. The machine could be
operated both in EPB mode with material discharge through the screw
conveyor onto a continuous conveyor muck handling system and in a
water controlled process (WCP) mode with hydraulic mucking as the
machine crossed beneath the channel and entered into the highly
permeable rocks.
The WCP mode bypasses the discharge gate and the muck is processed
directly from the screw conveyor through a crusher and into a slurry
pipeline to get pumped to a separation plant on surface. The system does
not incorporate a crusher in the excavation chamber as done in a standard
slurry machine. The cutterhead tool configuration is designed to limit the
particles that can enter the excavation chamber to a size suitable for the
installed screw conveyor. The WCP mode as designed for the EPBM that
excavated the Port of Miami tunnels is a simplified system or preliminary
step in the development of the Variable Density TBM where a rotary
crusher-slurryfier box was designed in combination with the screw
conveyor outlet. The rotary crusher-slurryfier box has to be moved into a
parking position before the belt conveyor can be put in operation.
Figure 2 – Functional Principles used for The “WCP – Mode” on the Port of Miami TBM.
Figure 3 – Variable Density TBM, different tunneling modes for optimum adaptability in difficult soft ground.
Based on the positive application of the Variable Density TBMs for the
challenging underground sections in the Kuala Lumpur Limestone
formation of Metro Line 1, four additional Variable Density TBMs were to
be delivered to Kuala Lumpur mid and end of 2017 to excavate and line
approximately 7 km of the new Metro Line 2.
The TBM is designed with a double screw conveyor of DN1150. The twin
screw arrangement has a flat gate between the first and second screw and
a muck discharge gate at the end of the first screw for the discharge of
muck onto a belt conveyor in pressurized or open EPB mode. In slurry
mode the discharge gate of the first screw is closed and the flat gate
between the first and second screw is open thus that the muck can be
discharged into a slurryfier box (capacity of 36 cubic m) that is installed at
the end of the second screw. The slurryfier box contains a stone crusher
(jaw crusher) that reduces larger particles to a size suitable for liquid
transport through the attached slurry circuit to the Slurry Treatment Plant at
surface. In slurry and high density mode the muck transfer along the screw
conveyor is a combination of a mechanical and hydraulic transportation.
Three sections, the two western tunnels and the up-track tunnel of the
eastern section are planned to be excavated using a Mixshield. The first
Mixshield drive started operation in March 2016. The Variable Density
TBM (Ø7.41m), was launched in August 2016 to excavate the down-track
shallow tunnel section of the eastern tunnels. This section is characterized
by large portions within fill material that is frequently composed of rock fill
blocks in the previous temporary seawall zone. The Variable Density TBM
can continuously adapt to the face density to deal with the demand of the
predicted heterogeneous and shallow ground conditions. The TBM can be
operated both in a slurry and high density mode. The latter mode is used
to cope with the very variable geology associated with shallow cover of
locally less than 1 diameter where possible risks such as blow outs and
settlements might have been an issue in slurry mode. As the TBM can be
operated also with HDSM the Slurry Treatment Plant on surface is
accordingly designed to supply the TBM with HDSM.
Two Variable Density TBMs (Ø7.05m)
for Forrestfield Airport Link in Perth,
Australia
Salini Impregilo S.p.A. and NRW Pty Ltd. JV was contracted to construct
the twin tube rail tunnels for the Forrestfield Airport Link project in Perth,
Australia. The Forrestfield Airport Link is a new rail line including two twin
tube tunnels that have a bored tunnel length of about 7.14 km. This new
rail line will connect Bayswater Junction with Forrestfield. A major section
of the alignment crosses beneath the Perth airport precinct. This includes
sensitive area beneath the airport runways, taxiways and buildings.
The expected subsurface conditions along the bored tunnel alignment are
characterized to be variable, sand, clayey sand and cemented layers with
varying degrees of strength and cementation. The majority of the tunneling
ground is expected to be composed of mixed face conditions beneath the
groundwater table.
With focus on the predicted varying geological units and their varying
strength the application of two Variable Density TBMs is considered. The
TBMs with a diameter of 7.05 m will be operated along the entire tunnel
alignment in closed pressurized mode to guarantee ground stability during
excavation. The machines will be launched at Forrestfield dive portal,
extending westward and ending at the Bayswater dive portal.
The Variable Density TBMs for the Forrestfield Airport project are
configured to operate in closed EPB and in slurry mode with a filled
excavation chamber and a controlled support of the tunnel face pressure.
Both in EPB and slurry mode the muck is extracted out of the pressurized
excavation chamber via the screw conveyor and further processed with
liquid mucking respectively hydraulic material transport via a closed,
pressurized slurry circuit according to the slurry mode or HDSM operation
with a slurry treatment plant at surface. To support the hydraulic muck
transport, the muck is transferred at the end of the screw conveyor into a
slurryfier box to liquefy the excavated material. A roller crusher is installed
in the slurryfier box that processes the material to a size suitable for
hydraulic mucking via slurry circuit.
The two Variable Density TBMs for Perth started tunneling in July and
September 2017.