Main
Main
I EARTHWORKS
EXCAVATION 104.08 cu.m 1500 156,120.00
II CONCRETING WORKS
FTG,BEAM,COL,SLAB 686 BAGS 250 171,500.00
SAND 36.84 cu.m 1,200.00 44,208.00
GRAVEL 73.55 cu.m 1,500.00 110,325.00
III FORMWORKS
PHENOLIC BOARD 179 PCS 685.00 122,615.00
2"x3"x12 LUMBER 853 PCS 85.00 72,505
IV REINFORCING STEEL BAR(6MTS)
FOOTING (20mm DIA.) 48 PCS 592.00 28,416.00
COLUMN(16mm DIA.) 84 PCS 380.00 31,920.00
LATERAL TIES (10mm DIA.) 80 PCS 150.00 12,000.00
BEAM (20mm DIA.) 68 PCS 592.00 40,256.00
STIRRUPS (12mm DIA.) 391 PCS 215.00 84,065.00
SLAB (12mm DIA.)BW 308 PCS 215.00 66,220.00
CHB REINFORCEMENT(12mm DIA.) 105 PCS 215.00 22,575.00
TIRE WIRE #16(TOTAL) 56.492 KGS 75.00 4,237.00
V MASONRY
CHB(15"x20"x40") 2574 PCS 18.00 46,332.00
PLASTERING(CEMENT) 76 BAGS 250 19,000.00
FINE SAND 3.99 cu.m 1,200.00 4,788.00
VI CARPENTRY
NAILS 33.78 or 34 KGS 145.00 11,658.00
3/4 THK MARINE PLYWOOD 46 PCS 1,300.00 59,800.00
2"x4" FLOOR JOIST 72 PCS 176.00 12,672.00
2"x3" WALL STUD 93 PCS 450.00 41,850.00
NAILER 2"x6" 8 PCS 720.00 5,750.00
2"x3" CEILING JOIST 87 PCS 450.00 39,150.00
VII DOORS AND WINDOW
WOOD PANEL DOOR 4 PCS 5,300.00 21,200.00
PVC FLUSH DOOR 3 PCS 1,400.00 4,200.00
MOLDED STEEL DOOR 1 PCS 19,000.00 19,000.00
STAINLESS PICTURE WINDOW 2 PCS 800.00 1,600.00
AWNING WINDOW 4 PCS 2,075.00 8,300.00
CASEMENT WINDOW 4 PCS 2,200.00 8,800.00
ALUMINUM CASEMENT WIND. 5 PCS 5,425.00 27,125.00
TOTAL 1,278,187.00
VIII LABOR
TOTAL MATERIALS x .45% 575,184.15
FOR FOOTING:
GIVEN:
1.5 MTRS = LENGTH OF FOOTING
1.5 MTRS = WIDTH OF FOOTING
2 MTRS = HEIGHT FROM BOTTOM TO NGL
0.10 MTRS = SPACING ON SIDE,BOTTOM OF BEAM AND FOOTING,GRAVEL BED
SOLUTION:(FOR FOOTING)
TOTAL EXCAVATION:
Te = 57 + 3.96 + 15.4 + 27.72
Te = 104.08 m3
FOR CONCRETING:
CLASS "AA" (10.5 x 0.5 x 1)
FOR FOOTING:
Vf = 1.5 x 1.5 x .40 = 0.9m3
Vf = 0.9 x 12 (NO. OF FOOTINGS)
Vf = 10.8 m3
FOR TIE BEAMS AND Tb1 = 3 - .175 - .175 = 2.65 mts Tb3 = 6 - .175 -.175 = 5.65 mts
GROUND BEAM: Tb1 = .350 x .500 x 2.65 = 0.46375 = .350 x .500 x 5.65 = 0.98875
= 0.46375 x 3 = 0.98875 x 7 = 6.92125
= 1.39125 m3 x 2(GROUND BEAM) = 6.92125 m3 x 2
= 2.7825 m3 = 13.8425 m3
ADD VOLUME:
FOOTING = 13.5 CEMENT: 10.5 x 25.5 = 267.75 or 268 bags
BEAM 1 = 2.7825 m 3
SAND: 0.5 x 25.5 = 12.75 m3
BEAM 2 = 8.9425 m3 GRAVEL: 1 x25.5 = 25.5 m3
BEAM 3 = 13.8425 m 3
Tv = 25.5 m3
Tb1 = 3 - .175 - .175 = 2.65 mts Tb3 = 6 - .175 -.175 = 5.65 mts
Tb1 = .300 x .400 x 2.65 = 0.318 = .300 x .400 x 5.65 = 0.678
= 0.318 x 3 = 0.678 x 7 = 4.746
= 0.954 m3 x 2(ROOF BEAM) = 4.746 m3 x 2 (ROOF BEAM)
= 1.908m 3
= 9.492m3
ADD VOLUME:
Tv = 1.908 + 6.132 + 9.492 CEMENT: 10.5 x 17.532= 184.086 or 185 BAGS
Tv = 17.532m3 SAND: 0.5 x 17.532 = 8.776m3
GRAVEL: 1 x 17.532 = 17.532m3
FOR PLASTERING:
Perimeter = 46 mts
Height = 3 mts
standard THK of plaster: 0.012
CEMENT:
= 227.36 x .216 = 49.11 or 50 BAGS
SAND:
= 227.36 x .012 = 2.728 m3
FOR COLUMN:
COLUMN HEIGHT: 5.68
COLUMN: .350x.350
NO OF COLUMNS: 12
SOLUTION:
= .350x.350 = 0.1225m2
= 0.1225x5.68 = 0.6958m3
= 0.6958x12= 8.3496m3
CLASS "AA"(10.5x.5x1)
CEMENT:
= 8.3496 x 10.5 = 87.67 or 88 CEMENT BAGS
SAND:
= 8.3496 x .5= 4.1748 cu.m
GRAVEL:
= 8.3496 x 1 = 8.35 cu.m
COMMON T&B GF
= 24.33 x .216 = 5.26 or 6 CEMENT BAGS
= 24.33 x 0.012 = 0.29196 cu.m OF FINE SAND
T&B GUESTROOM:
= 11.22x.216 = 2.423 or 3 CEMENT BAGS
= 11.22x0.012 = 0.13464 cu.m
LAUNDRY ROOM:
= 15.03 x 0.216 = 3.2465 or 4 CEMENT BAGS
= 15.03 x 0.012 = 0.1804 cu.m OF FINE SAND
W3 = 5x W4 = 1x
= 1 x 1.2 = 1.2 sqm = 1.5 x 1.2 = 1.8 m2
= 1.2 x 5(no of windows) = 6m2
D1 = 1x D2= 2x
= 2.2 x .8 (including hamba) = 2.2 x 9 (including hamba)= 1.98
= 1.76sqm = 1.98 x 2 = 3.96 m2
TOTAL AREA:
TA = 0.6 + 10.2 + 6 + 1.8 + 1.76 + 3.96
= 24.32m2
CHB NEEDED FOR WALLS:
TA = 125.4 - 24.32 = 101.08 m2
T&B (GUEST ROOM): = 2 + 1.5 + 1.5 = 5mtrs - .350 - .350 = 4.3mtrs TOTAL:
= 4.3 x 3 = 12.9m2 - 1.68 = 11.22m2 EXTERIOR = 1,264pcs
=11.22 x 12.5 = 140.25 or 141 pcs PANTRY = 318pcs
T&B(COMMON) = 301pcs
LAUNDRY ROOM: = 3.5 + 2 = 5.5mtrs x 3 T&B(GUEST ROOM) = 162pcs
= 16.5m2 - 1.47 = 15.03m2 x 12.5 T&B(MASTERS) = 341 pcs
= 187.87 or 188 pcs LAUNDRY ROOM = 188 pcs
TOTAL: 2574 pcs of 15x20x40 CHB
T&B(MASTERS BEDROOM): = 2.1 + 2.1 + 3 + 3 = 10.2mtrs - .350 - .350 =
= 9.5mtrs x3 = 28.9m2
= 28.9 - 0.2 - 1.47 = 27.23m2 x 12.5 =
= 340.38 or 341 PCS
REBARS IN FOOTINGS
TAKE NOTE:
W=1.6mtr
CONCRETE COVER=0.075
6-20mm DIA. O.C BW
0.080mts BEND OF REBAR
SOLUTION:
REBARS IN COLUMNS(VERTICAL):
HORIZONTAL
SPLICING = 3.96mts (TOTAL)
= 3mtsx4 + 3.96 = 15.96mts/6
= 2.66 or 3 x 3(no. of 3mts BEAM) = 9 pcs OF 20mm FOR THE 3M BEAM
TIE WIRE:
COLUMN:
= 31 x 4 = 124
= 124(connections) x 12(no. OF columns)=
= 1488 x.30 = 446.4mts OF #16 G.I TIE WIRE OR 446.4/53 = 8.4KLS
BEAM:
= 22 x 4(no. OF CONNECTIONS)=88
= 88 x .30 = 26.4 x 3(NO OF BEAMS)=
= 79.2mts OR 1.49kg OF #16 G.I TIE WIRE
= 44 x 4 = 176
= 176 x .30 = 52.8
= 52.8 x 7 = 369.6 mts or 6.97 kgs OF #16 G.I TIE WIRE
COMPUTATION: