Tut 4
Tut 4
The following production cost and machine hour data are available:
E F G H
Variable production cost (RM per unit) 32 27 34 35
Fixed production cost (RM per unit) 6 14 8 16
General purpose machine hours per unit 5 6 7 8
The fixed production costs represent a share of factory-wide costs that have
been related to the individual components by using a direct labour hour rate.
There are no fixed costs which can be specifically related to individual
components.
From next month the company’s monthly manufacturing requirements are
for 2,000 units of each component. The maximum number of machine hours
available for component manufacture is 35,000 per month.
The company can purchase any quantity of each component from Sergeant
Ltd at the following unit prices next month:
E F G H
RM48 RM51 RM55 RM63
Merryl Ltd aims to minimise its monthly costs.
Required:
a) Calculate the shortfall in general purpose machine hours next month.
(Answer: 1,700 hrs)
b) Determine how many units of which components should be purchased
from Sergeant Ltd next month.
ANSWER: E F G H
1
ABMC3084 Information for control and decision making
c) Briefly explain THREE other factors that the management of Merryl Ltd
should consider before making a final decision to buy in components
from Sergeant Ltd for next month.
i) Material requirements:
3 kg material M1 – see note 1 below
2kg material P2 – see note 2 below
1 Part No.678 – see note 3 below
Note 1:
Material M1 is in continuous use by the company. 1,000 kg are
currently held in stock at a book value of RM4.70 per kg but it is
known that future purchases will cost RM5.50 per kg.
Note 2:
1,200 kg of material P2 are held in stock. The original cost of this
material was RM4.30 per kg but as the material has not been required
for the last two years it has been written down to RM1.50 per kg scrap
value. The only foreseeable alternative use is as a substitute for
material P4 (in current use) but this would involve further processing
costs of RM1.60 per kg. The current cost of material P4 is RM 3.60
per kg.
Note 3:
It is estimated that Part No. 678 could be bought for RM 50 each.
2
ABMC3084 Information for control and decision making
iii) Overhead:
JB limited absorbs overhead by a machine hour rate, currently RM20
per hour of which RM7 is for variable overhead and RM13 for fixed
overhead. If this contract is undertaken it is estimated that fixed costs
will increase for the duration of the contract by RM 3,200.
Spare machine capacity is available and each component would
require four machine hours.
Required:
a) State whether or not the contract should be accepted and support your
conclusion with appropriate figures for presentation to management.
(Answer: Accept the contract= RM 1,400 contribution)
3
ABMC3084 Information for control and decision making
3. Supervision costs have been charged to the project on the basis of 33 1/3 %
of labour costs and will be carried out by existing staff within their
normal duties.
6. The project will need the utilisation of machinery that will have no other
use to the company after the project has finished. The machinery will
have to be purchased at a cost of RM10,000 and then disposed of for
RM5,250 at the end of the project.
4
ABMC3084 Information for control and decision making
The production manager tells you that the overseas customer is prepared to
pay up to a maximum of RM30,000 for the project and a competitor is
prepared to accept the order at that price.
He also informs you the minimum that he can charge is RM40,000 as the
above costs show RM32,000 and this does not take into consideration the
cost of machine and profit to be taken on the project.
Required:
a) Cost the project for the production manager, clearly stating how you have
arrived at your figures and give reasons for the exclusion of other figures.
(Answer: Relevant cost= RM18,000, contribution =RM12,000,
OK to accept at RM30k contract)
d) What would be your advice if you were told that the organisation was
operating below breakeven point ?
Give reasons for your advice.
5
ABMC3084 Information for control and decision making
Question 4:
A factory manager is preparing the production plan for the next quarter
ending 31 March 2013. One of the major components manufactured in this
factory is component C121. The following relates to the budgeted cost of
manufacturing 1,200 units of component C121:
RM per unit
Direct material 28
Direct labour - skilled 24
- unskilled 15
Variable overheads 10
Fixed overheads 20
The factory manager has received an offer from a supplier that can supply
1,200 units of this component at a price of RM78 per unit.
The management accountant has informed the factory manager that 60% of
the fixed overheads of component C121 represents absorbed fixed cost. The
remainder 40% of the fixed overheads is avoidable if component C121 is not
manufactured.
Required:
6
ABMC3084 Information for control and decision making
Question 4:
Component C121: RM RM
The factory manager is advised to buy 1,200 units of component C121 from the supplier
as this would result in cost savings of RM8,400.