Chapter 6 KT322H
Chapter 6 KT322H
PROJECT APPRAISAL
Chapter 6
FINANCIAL ANALYSIS OF THE PROJECT
Recall
• Organizing the drafting of the investment project
• Organizing the appraisal of the investment project
• Market analysis of the project
• Technical analysis of the project
• Organizing management and personnel
• Financial analysis of the project
1
31/03/2024
Contents
• The basic parameters of the project
• Financial analysis of the project
• Breakeven point and Payback period
• Selection of the discount rate for the project
• Net present value (NPV)
• Benefit-cost ratio (BCR)
• Internal rate of return (IRR)
2
31/03/2024
Other parameters
3
31/03/2024
Payable (P)
Inventory (I)
WC= C + R – P + I
4
31/03/2024
10
5
31/03/2024
11
Other parameters
• These parameters affect the effectiveness of the project:
– Taxes
– Inflation
– Exchange rate
• The systematic presentation of a project's financial parameters helps
investors to
– Figure the context of the project;
– Identify risks of the project;
– Determine which vital information to collect and review;
– Make the right investment decision.
12
6
31/03/2024
14
7
31/03/2024
Land 1.000
Factory
Machinery 3.200
Total 4.200
15
16
8
31/03/2024
Repayment plan
Item Year 0 Year 1 Year 2 Year 3
17
18
9
31/03/2024
19
20
10
31/03/2024
21
22
11
31/03/2024
23
Total costs
Fixed costs
Units sold
2
24 4
12
31/03/2024
25
Payback Period
• Payback period is the number of years it takes to recover all the
capital invested.
• The payback rule states that a project should be accepted if its
payback period is less than some specified cutoff period.
26
13
31/03/2024
27
28
14
31/03/2024
Future Value
0 1 2 n
P F1
F2
F1 = P + P.r = P( 1 + r ) Fn
F2 = F1 + F1 .r = P( 1 + r ) + P( 1 + r ).r = P( 1 + r )2
Fn = P( 1 + r )n
Present Value
Fn
Fn = P( 1 + r )n P=
( 1 + r )n
2
29 9
n
Bi n
Ci
NPV = PV − PC = −
i =0 ( 1 + r ) I =0 ( 1 + r )
i i
Advantages
•Assume that the cash flow is reinvested following the rate of return;
•Taking into account the time value of cash flow;
•Examining the entire cash flow.
Drawbacks
• Depending on the discount rate (the opportunity cost of capital)
3
30 0
15
31/03/2024
31
3
32
16
31/03/2024
n
Bi
PV (1+ r ) i
BCR = = i=1
PC C
n
i
3
34 4
17
31/03/2024
3
35
• Example 2: The two projects have the same investment capital of 250
million VND, and the construction period of these two projects is one
year, with r = 10%/year and net income as follows. Calculate
• Discounted Payback Period?
36
18
31/03/2024
Feasible project
IRR NPV1
IRR = r1 + *(r2 − r1 )
r2
NPV1 + NPV2
r1
Unfeasible project
NPV2
37
38
19
31/03/2024
Example 3: Information of the two projects is as follows, r=12%. Based on the criteria
of the payback period, NPV, BCR, IRR to evaluate? Assuming that the risk is 5% and
10%.
Investment capital Net income
Year A B A B
-1 2.000 1.500
0 3.000 1.000
1 1.500 300 1.750 1.000
2 1.800 1.200
3 1.850 1.300
4 2.000 1.050
5 2.100 950
6 2.500 850
3
39 9
40
20
31/03/2024
41
Year 0 1 2
Small Project -100 0 400
Big Project -100.000 0 156.250
Calculate Tpp, IRR, NPV, BCR (12%)? Which project is more preferred?
42
21
31/03/2024
Year 0 1 2 3
Project A -900 1.000 500 100
Project B -900 114 600 1.100
Calculate Tpp, IRR, NPV, BCR (12%)? Which project is more preferred?
43
NPV
IRR
400
200
0 5 12 32,5 52,4
Discount rate (%)
44
22
31/03/2024
NPV
With r>12%, Project A
400
is the best!
200
0 5 12 32,5 52,4
Discount rate (%)
45
46
23
31/03/2024
47
48
24
31/03/2024
49
50
25