JSP For Installation of Cable Tray
JSP For Installation of Cable Tray
3)
Project Name: Contract No. :
Department /Division: Electrical Date Prepared: 26/07/2023
Employee Job Title: WORKERS, FOREMAN, SUPERVISOR Location:
PPE: HELMET, VEST, SAFETY SHOES, HEARING, WELDING SHEILD, FACE SHIELD
Job/Task Title: Installation of cable tray PROTECTION PPE
Tools and Equipment: HAND TOOLS AND POWER TOOLS
:JSP Prepared By Muhammad Husnain (HSE Team Leader Q&E) :Signature Date: 26/07/23
:JSP Accepted By :Signature :Date
:JSP Approved By (REA) :Signature :Date
:JSP Approved By (SEC) :Signature :Date
Page 1 of 11 Rev.2 [08-April-2019) Projects Business Unit
JOB SAFE PRACTICES (JSP's) (5.19.3)
PTW shall be reviewed and evaluated by issuer and receiver to
ensure that all hazard and risk is identified and complete.
1.3. Verifying the site condition as Open areas, protruding sharp The workplace shall be pre-checked, free from any obstruction and
per requirements mentioned in objects, falling objects limited in safe good working condition prior to a combined verification
the application of Permit to illuminations and other construction visit.
Work by both the Permit hazards may cause accidents during All Issuer and receiver must be aware of the hazard present in the
Receiver and Permit Issuer. the verification visit. area and must be familiar with the ingress and egress of the
Unfamiliarity with access to the project site.
areas.
1.4. Issuance of approved Permit to Untrained personnel. Permit Issuer and Receiver must be qualified, trained and
Work from Permit Issuer to Incomplete information on Permit to competent.
Permit Receiver. work. Permit Issuer shall ensure that the site was visited to ensure that
workplace hazards and risk are adequately identified and
mitigating measure shall be established.
Permit Issuer and Receiver shall ensure that all the information
required in the permit to work are reviewed, completed and
signed.
1.5. Verifying the approved Permit to Inadequate coordination and area Permit to Work shall be displayed at the worksite
Work by the assigned SEC control protocol. Permit Receiver shall not leave the area for the whole duration of
Consultant. Unauthorized work to be performed permit to work.
within a defined location and Work shall not proceed without the presence of approved PTW
boundary. and the Permit Receiver overseeing the activity.
Permit Receiver shall account all workers under his Permit to Work
before the start of work.
Work shall not be started until duly approved Permit to Work is
available at the site and that Safety Toolbox meeting was
conducted.
Ensure all the information required in the permit to work shall be
completed, signed and updated by the authorized personnel.
2. Survey and preparation of the area where the installation is to be done
2.1 Review drawing and Poor office layout and storage Proper storage and segregation of all material supplies must be
specifications. arrangements resulting in insufficient observed at all times.
circulation space. Storage racks must be properly labeled for easy identification.
Contact with furniture if insufficient Storage areas must not be congested of materials. Space capacity
space to move around. must be strictly observed.
Overloaded filing cabinets. Good housekeeping must always be maintained in storage and
Inadequate illumination in the area. working areas to avoid slip, trip, and fall.