Controlled Switching Experience
Controlled Switching Experience
net/publication/355619992
CITATIONS READS
4 911
3 authors:
Urmil Parikh
ABB Limited Vadodara India
19 PUBLICATIONS 553 CITATIONS
SEE PROFILE
All content following this page was uploaded by Rehana Perveen on 18 July 2022.
REVIEW PAPER
123
J. Inst. Eng. India Ser. B
In this paper, different controlled switching method- (RDDS) of CB, breakdown of the dielectric medium take
ologies for transformer and reactor have been discussed. place earlier than mechanical contact touch of CB contacts
Review of present practices and their effectives have been which leads to pre-arcing [11]. The rated mechanical
elaborated in depth. operating time of CB is stored in CSD and the required pre-
Dielectric property of insulating medium and CB arcing time can be either fed to controlled or it can be
mechanical properties play a major role in the effective evaluated by CSD as per network conditions. Therefore,
implementation of CS and the influence of same have been the objective of CS is to initiate electrical closing rather
elaborated for different cases. Further, the selection of than mechanical closing; the difference between electrical
suitable voltage slope (rising or falling) also impacts the and mechanical closing influences the efficacy of CS.
effectiveness of controlled switching and has been dis- Figure 2 depicts the working principle of controlled
cussed in the paper. switching operation of three phase independent pole
operated CB. Electrical closing (Telect) refers to the total
operating time taken by CB after release of latch from
Controlled Closing Operation closing coil till current initiation as given in relation
Eq. (1). Further, the target instant (angle) for all the three
Closing of CB at unfavourable time instant causes phases of CB shall be different due to phase displacement
switching transients and affects the dielectric thermic life among phases.
of system. In case of transformers, the inrush current is Telect ¼ Toperating Tarc ð1Þ
generated during random charging due to possible core
saturation and reduction in inductance (due to doubling Peak voltage charging is the optimum strategy for
effect). The effect will be aggravated in the presence of transformers having independent magnetic circuits
residual flux remains in the core [8, 9]. The inrush current however there exists diversity in connections
generated during random charging can exceed 3–4 pu level configurations and magnetic coupling. The charging
with considerable DC content [10]. Damping of such angles recommended by CIGRE dis-regarding residual
asymmetric inrush current takes longer time due to the high flux are shown in Table 1, wherein R-phase is selected as
system X/R ratio. Further, the random charging in weak a lead phase and balance two phases shall be charged
grid systems poses additional power quality issues and a quarter cycle later (for coupled case). The individual
voltage dip may exceed the specific Grid Code require- phase can be switched at peak of the voltage for
ments. Due to inductive nature of transformer, its switching independent magnetic circuits. The selection of lead
at zero voltage poses worst inrush current. phase can be R-phase or other based on user decision.
Controlled closing refers to the release of control volt- For a coupled transformer with neutral earthed, the
age to closing coil of CB such that switching i.e electrical
conduction could take place at optimum instant. Intentional
delay is added to random command received from Bay
control unit. CSD during this period evaluate zero crossing
for the purpose of synchronization of closing command.
Due to specific rate of decrease of dielectric strength
123
J. Inst. Eng. India Ser. B
123
J. Inst. Eng. India Ser. B
123
J. Inst. Eng. India Ser. B
Chandrasena et al. [16] Delayed closing with residual flux measurement 1200MVA 500/230/46 kV 0.013 pu
Mercier et al. [19] Rapid closing with residual flux measurement 465MVA 18/315 kV 0.01 pu
Goldsworthy and Roseburg [11] Delayed closing 1008MVA, 525/241/34 kV Magnetization current
Li et al. [20] Rapid closing with residual flux 750MVA, 500/230/33 kV 0.3 pu
Parikh and Bhalja [14] Rapid closing with flux locking 1500 MVA, 765/400/33 kV Magnetization current
CIGRE Guidelines [5] Delayed closing 375MVA, 315 kV Magnetization current
Bronzeado et al. [21] Rapid closing with residual flux 100MVA, 230/138 kV Magnetization current
Prikler and Bánfai [22] Rapid closing with residual flux 155MVA, 132/15 kV 0.35 pu
RDDSðabsolute of CBÞ Fig. 8 Peak energization with 1.0 pu RDDS and ± 1.0 ms CB
RDDSpu ¼ pu ð3Þ scatter
System voltage max dv/dt
Value of maximum voltage derivative shall be energy). This small variation is statistical in nature and
considered as 1pu and actual RDDS of CB shall be cannot be compensated. This mechanical time variation of
expressed with its relative. Pre-arcing time based on RDDS CB is called CB scatter and is usually approximated by
can be evaluated by the following expression: Eq. (5):
Voltage DTstatistic ¼ 3rmech ðmsÞ ð5Þ
Tprearc ¼ ðmsÞ ð4Þ
RDDS kVms The CB scatter for controlled switching purpose is
intended to fit in 99.8% values as shown in Fig. 6. The
The CB due to its inertial and mechanical linkage has EHV AC CBs has typical CB scatter of ± 0.5
different operating time even in same environmental
conditions (including control voltage, pressure, drive
Fig. 7 Peak energization with 1.0 pu RDDS and ± 0.5 ms CB Fig. 9 Peak energization with 0.75 pu RDDS and ± 1.0 ms CB
scatter scatter
123
J. Inst. Eng. India Ser. B
Statistical variation
1331 0.05 1.19
Continuous
variation
1000 0.03 1.05
Fig. 10 Pre-arcing characteristics with 0.6 pu RDDS and ± 1.0 ms
scatter
123
J. Inst. Eng. India Ser. B
from first phase. Following two sets of simulations were reactors can be charged with rapid charging method.
carried out:- Generally, shunt reactors are energized at peak voltage to
avoid asymmetry [5]. As discussed above, peak charging
a) Fixed variations of targets within set range
imposes sudden voltage on windings and can weaken the
b) Random variations of targets within set range
dielectric characteristics. Therefore, considering CB scatter
For the first category, the charging targets for varied and dielectric consideration, maximum angle approach is
with 0.1 ms step for 2.0 ms for three phases and a total of the best suited approach for reactor charging.
1331 (11 9 11 9 11) simulations were carried out. For
the second category, the CB is modeled as a statistical
function and the individual pole peak target is varied in Selection of Feedback System for Confirmation
a range of 4.0–6.0 ms (1st pole) randomly. A set of 1000 of Closing Operation
simulations were carried out. The simulation results are
depicted in Table 3. CSD works in a close loop manner wherein the actual
The inrush currents from transformer are in the range of switching (closing/opening) time of CB is measured and
no-load current values when charging is done at an opti- compared to rated/intended targets. The difference in
mum angle. From the above results, it can be appreciated actual and rated timing is stored in CSD and used as
that inrush currents vary from no load values to 1.19 pu an adaption for the next switching operation. Hence, this
level (approx) considering scatter at peak of reference error is based on the accuracy of the feedback system and
phasor. The variations shall be increased if the intended plays important role in the effective operation of CSD.
target lies in falling slope. Therefore, the objective of Following are the feedback systems used in CS [5]:
optimum controlled switching is to attain a target within
a) Current feedback
the persisting scatter range and not a single absolute angle.
b) Voltage feedback
For evaluating the consistency of CS, the series of tests
c) Auxiliary contact feedback
needs to be done whether they falls within 1 pu range
considering scatter or not. One successful closing operation Among the above methods, voltage feedback is the most
with no load values can mislead the efficacy of method- suited system for observing the actual switching point,
ology. Peak voltage charging is optimum for the reduction however, in most cases the load voltage is not avail-
in inrush currents (thermic stress) however the sudden able. The voltage threshold are required for evaluating
application of step voltage may impose dielectric stress to actual voltage start viz-a-viz small leakage voltage.
the transformer. Winding turns near to the HV end may In the case of shunt reactors, the saturation point is
experience dielectric more stress. The maximum angle higher than the transformer and therefore currents shall
approach entails charging at reduced voltage as compared initiate alongwith electrical closing. Hence, current starting
to peak and is also helpful in managing the dielectric instant can be considered as a charging point in the case of
health. reactors. However, time to saturation in case of the trans-
With the increase in capacity of a transformer, the former varies depending upon flux dynamics and current
capacitance value increases considerably, and hence, the flow may start after a lapse of few milli second period.
residual flux that resides in the core reduces to 0.1–0.3 pu Therefore, the current initiation detection method is not
values. If we consider the target correction for residual flux an optimal method for use as feedback to the CSD con-
0.3 pu, it will reside near the extreme points of CB scatter. troller in case of a transformer. Moreover, the current
Therefore, the effect of residual is partially accounted in
CB scatter.
123
J. Inst. Eng. India Ser. B
123
J. Inst. Eng. India Ser. B
Reactors installed with a neutral grounding reactor The centre of re-ignition free window for reactors above
(NGR) require additional correction as per the above 63MVAR 420 kV rating is generally more than 7.0 ms [5].
table depending on the ratio of reactor inductance to Further, the effect of scatter is less pre-dominant during
NGR inductance. opening due to high speed. The disturbance record as
The opening operation of CB is done at high speed as shown in Fig. 15 depicts the controlled opening of shunt
compared to closing operation; thus, the CB scatter is less reactor having a rated CB opening time of 21 ms. The
predominant. However, evaluation of arcing time is opening process has been carried out considering arcing
a critical parameter in efficient implementation of con- time of 5.0 ms and the opening did not
trolled opening of the reactor. A highly inductive current happened effectively. The dark black vertical line
of the shunt reactor can result in re-ignition/re-strike if the indicates the time of release of trip command and blue
dielectric property of insulation medium is not properly dotted line indicates the actual opening occured, all the
accessed. The rate of built of dielectric strength of insu- three phases didnot complete the half cycle period during
lation medium during the opening process is termed as last cycle which indicates harmful TRV and possible re-
Rate of Rise of Dielectric Strength (RRDS). The maximum ignition.
rate of change in voltage for 400 kV, 50 Hz system shall be
102.5 kV/ms (1 pu). The current shall be successfully
interrupted if the RRDS is higher than the system voltage Selection of Voltage Slope for Switching Operation
derivative. High voltage transient recovery voltage (TRV)
developed across CB terminals due to current chopping as It is always preferable to energize/de-energize a trans-
shown in Fig. 14. former or reactor on rising slope rather than falling slope.
The concept of re-ignition free window [5] is useful in The objective behind this selection is consideration of error
the proper assessment of arcing time for reactor opening magnification.
123
J. Inst. Eng. India Ser. B
123
J. Inst. Eng. India Ser. B
mechanical device have considerable inertia and mechan- Annual Conference for Protective Relay Engineers, 1–3 Apr
ical linkages therefore there are unavoidable statistical 2008, College Station, TX, USA (2008)
12. H. Ito, A. Mercier, M. Waldron, Controlled switching, in
variations in mechanical operating time. CB with low Switching Equipment. ed. by H. Ito (CIGRE Green Books.
scatter and high RRDS/RDDS are preferable for CS Springer, Cham, 2019)
applications. Close coordination of CB and CSD is 13. U. Parikh, B. Bhajla, Challenges in field implementation of
required for achieving the desired performance. In addition controlled energization for various equipment loads with circuit
breakers considering diversified dielectric and mechanical char-
to above, the feedbacks used in CS plays a vital role in acteristics. Electr. Power Energy Syst. 87, 99–108 (2017)
deciding corrections for subsequent switching operation 14. K.A. Bhatt, B.R. Bhalja, U. Parikh, Evaluation of controlled
and needs calibration during routine maintenance. Field energization of an unloaded power transformer for minimizing
examples have been discussed and proved that absence of the level of inrush current and transient voltage distortions using
PIR-CBs. IET Gener. Transm. Distrib. 12(11), 2788–2798 (2018)
proper assessment of arcing time setting & auxiliary con- 15. K.A. Bhatt, B.R. Bhalja, U. Parikh, Evaluation of controlled
tact feedback results in an undesirable responses from CS. energization of shunt reactors for minimizing asymmetric DC
component of charging current with circuit breaker having pre-
insertion resistors. Electr. Power Energy Syst. 93, 340–351
Funding This study and all authors have received no funding. (2017)
16. W. Chandrasena, D. Jacobin, P. Wang, Controlled Switching of
Declarations 1200MVA Transformer in Manitoba. IEEE Trans. Power Deliv.
31(5), 2390–2400 (2016)
Conflict of interest The authors declare that they have no conflict of 17. P. Wang, et. al., Application of converter transformer controlled
interest. switching in Nelson River Bipole III HVDC system. In Session
Papers & Proceedings B4-110, CIGRE 2018, Paris France
18. R. Gonzalez, A. Soler, J. Macias, G. Cordero, Controlled
switching strategies for transformer inrush current reduction: a
References comparative study. Electr. Power Syst. Res. 145, 12–18 (2017)
19. A. Mercier, et al., Transformer controlled switching taking into
1. D. Wang, et al., Research of controlled switching strategy to account the residual flux. In CIGRE 2002 Session 13-201, Paris
restrain inrush current during the energization of converter 20. G. Li, D.F. Rodriguez, U. Parikh, M. Stanek, Controlled
transformer. In IET, The 14th IET International Conference on switching of unloaded power transformer case with 500/230/
AC and DC Power Transmission (2018) 33kV auto transformer. In 2018 IEEE PES Transmission &
2. X. Lin et al., Abnormal operation behavior analysis and coun- Distribution Conference and Exhibition - Latin America (T&D-
termeasures on the differential protection of converter trans- LA), 18–21 Sept 2018, Lima, Peru
former. Electr. Power Energy Syst. 64, 516–525 (2015) 21. H.S. Bronzeado, S.O. Pinto, P. Jonsson, J.C. de Oliveira, M.L.R.
3. B. Zheng, et al., Study on influence and countermeasures of Chaves, Transformer controlled switching to eliminate inrush
coupling transformer charging inrush current to Hami-Zhengzhou current—part II: field tests on a 100MVA three-phase trans-
UHV DC Project. In 2016 IEEE PES Asia-Pacific Power and former. In 2006 IEEE/PES Transmission & Distribution Con-
Energy Conference-Xi’an—China ference and Exposition: Latin America, 15–18 Aug 2006,
4. Z.S. Joukhan, ‘Operation of HVDC Converters for transformer Caracas, Venezuela
inrush current reduction’, Doctoral Thesis, Universitat Politec- 22. L. Prikler, G. Bánfai, G. Bán, P. Becker, Reducing the magne-
nica De Caatalunya (2017) tizing inrush current by means of controlled energization and de-
5. CIGRE WG3.35, Guidelines and best practices for the commis- energization of large power transformers. In International Con-
sioning and operation of controlled switching projects (2019) ference on Power System Transients, New Orleans, USA (2003)
6. Controlled switching of HVAC circuit breaker: guide for appli- 23. A. Ebner, M. Bosch, R. Cortesi, Controlled switching of trans-
cation lines, reactors, capacitors, transformers: part-I, ELECTRA formers—effects of closing time scatter and residual flux uncer-
183, CIGRE Working Group A3.07, April 1999, pp. 22–33 tainty. In 2008 43rd International Universities Power
(1999). Engineering Conference, 1–4 Sept 2008, Padua, Italy (2008)
7. Controlled switching of HVAC circuit breaker: guide for appli- 24. H. Hamada, et al., RDDS (rate of decrease of dielectric strength)
cation lines, reactors, capacitors, transformers: part-II, ELEC- measurement for gas circuit breaker. In Transmission and
TRA 185, CIGRE Working Group A3.07: April 1999, pp. 37–57 Distribution Conference and Exhibition 2002: Asia Pacific.
(1999). IEEE/PES, 6–10 Oct 2002, Yokohama, Japan (2002)
8. J.H. Brunke, K.J. Frohlich, Elimination of transformer inrush 25. M. Waldron, F. Ait-Abdelmalek, A. Ficheux, J.L. Rayon, Qual-
current by controlled switching: part-II-application and perfor- ification process of a GIS 400 kV SF6 high voltage circuit breaker
mance considerations. IEEE Trans. Power Deliv. 16(2), 281–285 controlled switching solution. In CIGRE Paris Session 2014-A3-
(2001) 204
9. J.H. Brunke, K.J. Frohlich, Elimination of transformer inrush 26. H. Ito, Factory and field tests of controlled switching in accor-
current by controlled switching: Part-I-theoretical considerations. dance with IEC62271-302 standard. Technical Report,
IEEE Trans. Power Deliv. 16(2), 276–280 (2001) https://www.advance.mitsubishielectric.com/advance/pdf/2007/
10. CIGRE, Working Group A3.07, Controlled switching of HVAC vol117.pdf
circuit-breakers: guidance for further applications including 27. ABB SwitchsyncTM PWC600 Version 1.0, https://library.e.abb.
unloaded transformer switching, load and fault interruption and com/public/935511e718684db888a2c910b98060a0/511346-EN_
circuit breaker uprating. Jan 2004 (2004) UM_PWC600I_1p0.pdf
11. D. Goldsworthy, T. Roseburg, Controlled switching of HVAC 28. Schneider Electric, manual, https://www.studiecd.dk/cahiers_
circuit breakers: application examples and benefits. In 2008 61st techniques/The_behaviour_of_SF6_puffer_circuit_breakers.pdf
123
J. Inst. Eng. India Ser. B
29. H. Heiermeier, Testing of reactor switching for UHV circuit 32. High-voltage switchgear and control gear—part 302: alternating
breakers. IEEE Trans. Power Deliv. 30(3), 1172–1178 (2015) current circuit-breakers with intentionally non-simultaneous pole
30. S. Grebovic, N. Oprasic, A. Balota, Influence of shunt reactor operation. IEC/TR 62271–302 ed1.0; 06–2010
switching on overvoltages in 400 kV substation. In 9th 33. R. Thomas, Controlled switching of high voltage SF6 circuit
Mediterranean Conference on Embedded Computing, 8–11 June breakers for fault interruption. Thesis, Chalmers University of
2020, Budva, Montenegro Technology, Sweden
31. M. Sonagra, U. Parikh, V. Upadhyay, Controlled switching of
non-coupled & coupled reactor for re-ignition free de-energiza- Publisher’s Note Springer Nature remains neutral with regard to
tion operation. In 2019 5th International Conference for Con- jurisdictional claims in published maps and institutional affiliations.
vergence in Technology, Pune, India, 29–31 March 2019 (2019)
123