PMC Road Quotation
PMC Road Quotation
4 Providing and applying Prime Coat using cationic bituminous emulsion of 1000 Sqm
approved grade over prepared surface including cleaning of surface with
broom applying tackcoat including the cost of all materials, labour.
6 Providing & applying Prime Coat using cationic bituminous emulsion of 3000 Sqm
approved grade over prepared surface including cleaning of surface with
broom applying tackout including the cost of all materials, labour.
Providing and laying 20 mm thick open graded Premix Carpet using 13.2 mm
7 @ 0.018 M3/M2 and 11.2 mm @0.009 M3/M2 size stone agreegates including 3000 Sqm
through cleaning of the surface applying tackcoat preheating stonechips and
fully precoating the same with hot matrix @ 54.00 Kg/M 3 of agreegates laying
the premixed chips uniformly over the surfacein proper level rolling with
power roller, including the cost and carriage of all materials, related
machinaries and labour.
Providing & Laying premixed 6 mm Thick Seal Coat (type-B) with approved
8 quality of sand @ 0.6 M3/100 M2 and hot bitumen buider on throughly 3000 Sqm
cleaned black top surface including heating and mixing cleaned sand
uniformly with hot binder @113.5 kg/M3 of sand suitable pan/mix plant
followed by rolling with power roller including the cost and carriage of all
materials, related achinaries and labour (Using Red sand type B).
Drainage Portion Work (Length - 80 mtr x Breadth - 1 Mtr)
Providing and Laying Plain cement concrete (100 mm Thick) including site
10 mixing, pouring, compacting with vibrator, finishing, curing etc complete with 4.2 Cum
all materials and labour at all depths and including all othe incidental charges
in this connection. 1:3:6 (Site Mixing)
RCC M30 Grade concrete at road by RMC with Broom finish, pouring,
12 compacting with vibrator, finishing curing etc. complete with all material 12.6 Cum
(Steel), shuttering, labour, tools & tackles at all depths and incliding all other
incidental charges in this connection. (Site Mixing with 10/20 Concrete mixing
machine)
13 Shuttering work with 15 mm thick ply including wooden runner, planks etc. 160 Sqm
complete and removing after 24 hours of concreting.
Rate Amount
130.00 130000.00
80.00 240000.00
4510.00 451000.00
115.00 115000.00
250.00 250000.00
115.00 345000.00
260.00 780000.00
245.00 735000.00
2500.00 75000.00
8800.00 36960.00
130000.00 182000.00
10500.00 132300.00
750.00 120000.00
Total= 3592260.00