General Conditions of Contract For Construction
General Conditions of Contract For Construction
FOR
CONSTRUCTION
TABLE OF CONTENTS
CLAUSE DESCRIPTION PAGE
1. DEFINITIONS 3/4
2. INTERPRETATION OF THE CONTRACT 3/5
3. REPRESENTATIVES OF THE COMPANY 3/5
4. REPRESENTATIVES OF THE CONTRACTOR 3/6
5. THE WORK 3/7
6. THE RESPONSIBILITY OF THE CONTRACTOR TO INFORM ITSELF 3/8
7. THE RESPONSIBILITY OF THE CONTRACTOR TO INFORM THE COMPANY 3/8
8. USE OF SHELL PRODUCTS 3/9
9. SUBCONTRACTS 3/9
10. PERSONNEL OF THE CONTRACTOR AND THE SUBCONTRACTOR 3/10
11. COOPERATION WITH OTHERS 3/12
12. VARIATION 3/12
13. INSPECTION AND TESTING 3/12
14. SCHEDULING 3/14
15. FORCE MAJEURE 3/14
16. SUSPENSION 3/15
17. TERMINATION, DISCONTINUANCE OF THE WORK AND DEFAULT 3/16
18. COMPLETION 3/20
19. RESPONSIBILITY FOR THE WORK 3/21
20. CONTRACT PRICE 3/22
21. TAXES 3/22
22. TERMS OF PAYMENT 3/22
23. AUDIT RIGHTS OF THE COMPANY 3/24
24. LIENS 3/24
25. OWNERSHIP 3/25
26. RESPONSIBILITIES AND INDEMNITIES 3/25
27. INSURANCE 3/27
28. PERMITS, LAWS AND REGULATIONS 3/29
29. HEALTH, SAFETY AND ENVIRONMENT 3/29
30. MILESTONE ZERO 3/30
31. PUBLIC AND INDUSTRIAL RELATIONS AND PUBLICITY 3/30
32. BUSINESS ETHICS 3/31
33. GENERAL LEGAL PROVISIONS 3/31
34. SUBSTANCE ABUSE 3/32
35. CUSTOMS CLEARANCE/DUTIES 3/33
36. INTELLECTUAL PROPERTY RIGHTS 3/33
37. INFORMATION SECURITY 3/34
38. EMPLOYMENT AND TRAINING 3/34
1. DEFINITIONS
(1) (a) "ASSOCIATES" means Brunei Shell Marketing Company Sendirian Berhad, Brunei
LNG Sendirian Berhad and Brunei Shell Tankers Sendirian Berhad.
(b) "COMPLETION DATE" means the date on which the WORK is required to have
been completed in accordance with the CONTRACT, and in relation to a term
contract means the expiry of that contract.
(c) "CONTRACT" means the FORM OF AGREEMENT and the several documents
listed therein.
(d) "CONTRACT PRICE" means the sum or sums or unit prices to be ascertained and
paid in accordance with the provisions of the CONTRACT.
(e) "CONTRACT HOLDER" means the person appointed as such by the COMPANY
and named as such in the CONTRACT, having the authorities set forth in the
Clause headed REPRESENTATIVES OF THE COMPANY.
(f) "COMPANY REPRESENTATIVE and/or COMPANY SITE REPRESENTATIVE(S)"
means the person(s) appointed as such in writing by the CONTRACT HOLDER
having the authorities set forth in the Clause headed REPRESENTATIVES OF THE
COMPANY.
(g) "CONTRACT MANAGER" means the person appointed as such by the
CONTRACTOR and named as such in the CONTRACT, having the authorities set
forth in the Clause headed REPRESENTATIVES OF THE CONTRACTOR.
(h) "CONTRACTOR REPRESENTATIVE and/or CONTRACTOR SITE
REPRESENTATIVE" means the person(s) appointed as such in writing by the
CONTRACT MANAGER having the responsibilities and authorities set forth in the
Clause headed REPRESENTATIVES OF THE CONTRACTOR.
(i) "EQUIPMENT" means any consumables, equipment, facilities, implements, plant,
sanitary facilities, supplies, temporary buildings or structures, tools, transport,
utilities, watercrafts or other items required or necessary for the satisfactory
performance of the WORK but excludes MATERIALS.
(j) "HSE" means Health, Safety and Environment.
(k) "HSE STANDARDS" means any safety laws, rules, regulations and any COMPANY
HSE STANDARDS, industry standards, codes of practice and equipment
manufacturers specifications applicable to the WORK and any revision thereof.
(l) "COMPANY HSE STANDARDS" means those documented HSE Standards
referred to in the current COMPANY HSE STANDARDS Master Index (Document
Reference TMS0434) and detailed both in that Master Index and the associated
modules.
(m) "MATERIALS" means any goods, machinery, materials, consumables and other
items to be incorporated or intended to be incorporated into the WORK.
(n) "PERSONNEL" means the person or persons provided by the CONTRACTOR
under the CONTRACT.
(o) "SUBCONTRACT" means any contract between the CONTRACTOR and any party
(other than the COMPANY or the CONTRACTOR'S employees) for the
performance of any part of the WORK.
(p) "SUBCONTRACTOR" means any party (other than the CONTRACTOR) to a
SUBCONTRACT approved by the COMPANY.
(q) "VEHICLE" means the unit of transportation provided by the CONTRACTOR in
accordance with the requirements of the CONTRACT as more specifically described
in Section 5 hereto.
(r) "VARIATION" means any alteration to the WORK of a type specified in Clause
headed VARIATION in the CONTRACT.
(6) The COMPANY shall have the right to replace the CONTRACT HOLDER and the
CONTRACT HOLDER shall have the right to replace the COMPANY REPRESENTATIVE
and the COMPANY SITE REPRESENTATIVE(S) at any time at their sole discretion and
they shall notify the CONTRACT MANAGER accordingly, in writing.
(7) The supervision, inspections, acts or omissions of the CONTRACT HOLDER, the
COMPANY REPRESENTATIVE, the COMPANY SITE REPRESENTATIVE(S) shall not in
any manner relieve the CONTRACTOR from his duties, obligations and liabilities under
the CONTRACT.
(8) Only the CONTRACT HOLDER and the COMPANY REPRESENTATIVE are authorised
to receive on behalf of the COMPANY, notifications, information and decisions of the
CONTRACTOR under the CONTRACT.
(9) Instructions, information and decisions from anyone other than the CONTRACT HOLDER,
the COMPANY REPRESENTATIVE or COMPANY SITE REPRESENTATIVE(S) acting
within the terms of their respective delegated authority shall have no contractual force or
validity even if they are written on COMPANY headed note paper.
5. THE WORK
(1) The CONTRACTOR shall comply with all instructions with regard to the WORK that the
COMPANY in its absolute discretion may from time to time issue. The CONTRACTOR
shall perform the WORK in accordance with the requirements of the CONTRACT, in
accordance with the best industry standards, in compliance with all relevant laws and
regulations, and in such a manner as will always safeguard and protect the COMPANY'S
interests.
(2) The CONTRACTOR shall provide all MATERIALS, EQUIPMENT, PERSONNEL,
supervision, engineering and other services and all other things required or necessary for
the satisfactory performance and completion of the WORK except those items specified in
SECTION 6 – PROVISIONS BY COMPANY AND CONTRACTOR as items to be provided
by the COMPANY.
(3) The CONTRACTOR shall be responsible for the timely provision of all matters referred to
in sub-clause (2) herein including the timely ordering and delivery of all MATERIALS and
EQUIPMENT to be provided by the CONTRACTOR and for the timely call off of the
COMPANY supplied MATERIALS and EQUIPMENT (in accordance with procedures set
out in the CONTRACT) in order to ensure that performance of the WORK is not delayed
or impeded.
(4) If by reason of any accident or failure or other event occurring to or in connection with the
WORK or any part thereof any emergency remedial or other work or repair is in the
opinion of the COMPANY urgently necessary for security, safety or for any other purpose
which justifies immediate action, then as soon as may be reasonably practicable after
such occurrence the COMPANY shall notify the CONTRACTOR to that effect. Where
practicable the CONTRACTOR shall be given an opportunity to perform such work but
where the CONTRACTOR is unable or is unwilling to perform that work forthwith then the
COMPANY may carry out all work or repair by itself or allocate to other Contractors with
or without existing Contract with the COMPANY as the COMPANY considers necessary.
The COMPANY shall be entitled to recover from the CONTRACTOR all costs incurred by
the COMPANY in so doing and shall adjust the CONTRACT PRICE and/or the
COMPLETION DATE at COMPANY'S sole reasonable discretion.
(5) Without prejudice to the CONTRACTOR'S other obligations with respect to MATERIALS
under the CONTRACT, the CONTRACTOR shall ensure that all MATERIALS shall, when
installed, be new and unused, of correct design and workmanship, within the
specifications, or if no such specifications exist, fully suitable for the use intended and the
CONTRACTOR shall obtain in the name of the COMPANY the best obtainable suitable
guarantees and warranties for MATERIALS provided by the CONTRACTOR in this
respect from their suppliers, valid for a period which shall at least be compatible with the
requirements of Clause headed RESPONSIBILITY FOR THE WORK.
The foregoing does not relieve the CONTRACTOR of any of its obligations under Clause
headed RESPONSIBILITY FOR THE WORK.
(6) The CONTRACTOR shall use and shall cause any SUBCONTRACTOR to use such
EQUIPMENT as will be adequate, in quality and number, to carry out the WORK in
accordance with the CONTRACT. The CONTRACTOR shall maintain and operate all
EQUIPMENT strictly in accordance with the manufacturer's printed instructions. The
COMPANY shall have the right to inspect all EQUIPMENT records.
If, in the opinion of the COMPANY any item of EQUIPMENT is not or is no longer suitable
for the purpose intended, then the CONTRACTOR shall at no additional cost to the
COMPANY and at the option of the COMPANY, either make adequate repairs or arrange
for immediate replacement.
If, in the opinion of the COMPANY the number of items of EQUIPMENT is inadequate,
then the CONTRACTOR shall provide the necessary additional EQUIPMENT at no cost to
the COMPANY to ensure timely completion of the WORK.
(7) Non-Exclusivity
(a) The CONTRACT shall not confer on the CONTRACTOR an exclusive right to
provide any or all of the WORK described in SECTION 4 – SCOPE OF WORK.
(b) The COMPANY shall have the right at its sole discretion to award contracts to
others for the provision of the WORK described in SECTION 4 – SCOPE OF
WORK, or to perform the WORK itself.
(8) Save as provided elsewhere in the CONTRACT, in the event that the rate of progress of
the WORK or any part of it is at any time, in the opinion of the COMPANY, too slow to
ensure completion by the COMPLETION DATE then (without prejudice to any other rights
and remedies of the COMPANY), the COMPANY may require the CONTRACTOR, and
the CONTRACTOR shall take immediate steps at its own cost, to expedite progress of the
WORK (including without limitation working overtime or using additional personnel or
additional or better EQUIPMENT on the WORK) so as to ensure completion of the WORK
by the COMPLETION DATE.
(4) The CONTRACTOR shall keep the COMPANY fully informed of the progress of the
WORK and shall comply with the reporting requirements set out in the CONTRACT.
9. SUBCONTRACTS
(1) The CONTRACTOR shall ensure that the rights of the COMPANY and the requirements
in the CONTRACT regarding SUBCONTRACTORS are effectively provided for in any
SUBCONTRACT.
(2) The CONTRACTOR shall not subcontract the whole or the majority of the WORK but
where a SUBCONTRACT is provided for in the CONTRACT or where the CONTRACTOR
wishes to enter into a SUBCONTRACT, then before the CONTRACTOR enters into any
SUBCONTRACT, the COMPANY shall be given an adequate opportunity to review the
form of the SUBCONTRACT, the choice of the SUBCONTRACTOR, the part of the
WORK which shall be covered under the SUBCONTRACT, and any other details the
COMPANY shall request or specify. The CONTRACTOR shall not enter into the proposed
SUBCONTRACT until the requirements of this Clause have been met and until the
COMPANY has given its written consent to the proposed SUBCONTRACT.
(3) No SUBCONTRACT shall bind or purport to bind the COMPANY and each
SUBCONTRACT shall provide for its immediate termination in the event of termination of
the CONTRACT or suspension in the event of suspension of the WORK. Each
SUBCONTRACT shall provide that it shall be assigned to the COMPANY or its nominee if
the COMPANY gives written notice to the SUBCONTRACTOR that it requires such an
assignment if the COMPANY terminates the CONTRACT. Unless such an assignment
takes place the SUBCONTRACTOR shall only be responsible to the CONTRACTOR, who
shall in turn be responsible to the COMPANY.
(4) The CONTRACTOR shall be responsible for all work, acts, defaults and breaches of duty
of any SUBCONTRACTOR or its employees or agents as fully as if they were the work,
acts, defaults or breaches of duty of the CONTRACTOR.
(5) Where applicable the CONTRACTOR shall ensure that appropriate Brunei organisations
and suppliers are given full and fair opportunity to tender for the supply of goods and
services.
(6) The CONTRACTOR agrees that it shall furnish to the COMPANY, if requested,
satisfactory evidence that all SUBCONTRACTORS (including suppliers to the
CONTRACTOR) have been paid on time and in full for work done or goods supplied in
connection with the performance of the WORK. If such satisfactory evidence is not
supplied then the COMPANY shall not be bound to make any further payment to the
CONTRACTOR for that part of the WORK until it is supplied.
(7) Furthermore the COMPANY may deduct from payments due to CONTRACTOR the
amount not paid to such SUBCONTRACTORS, and may then make such payment
directly to such SUBCONTRACTORS. Such direct payment to SUBCONTRACTORS shall
be deemed to be payment under the CONTRACT and the CONTRACTOR shall have no
further entitlement to such amount.
(8) Nominated Subcontractor
(a) The COMPANY may request the CONTRACTOR to enter into SUBCONTRACTS
with SUBCONTRACTORS nominated by the COMPANY. The CONTRACTOR
shall not be bound to enter into a SUBCONTRACT with such a nominated
SUBCONTRACTOR if the CONTRACTOR has reasonable objection to the
nomination. The COMPANY shall in that event provide another nominated
SUBCONTRACTOR and the CONTRACTOR shall have the same right to raise
reasonable objection or the CONTRACTOR may nominate a subcontractor
acceptable to the COMPANY.
(b) The CONTRACTOR shall be responsible for finding another SUBCONTRACTOR
that is acceptable to the COMPANY if any nominated SUBCONTRACTOR fails
either totally or partially to perform any SUBCONTRACT. The COMPANY shall only
pay to the CONTRACTOR what it would have been bound to pay had such
nominated SUBCONTRACTOR correctly performed the SUBCONTRACT in
question. Any additional costs incurred by the CONTRACTOR arising from the
removal or replacement of any nominated SUBCONTRACTOR and/or in having the
relevant activities performed by another shall be for the account of the
CONTRACTOR.
the right during the course of the CONTRACT to require the removal of any
CONTRACTOR PERSONNEL who is diagnosed to be suffering from any communicable
and/or contagious diseases and the CONTRACTOR shall provide suitable replacement
PERSONNEL (such PERSONNEL shall be required to undergo and pass a similar
medical examination) at the CONTRACTOR'S expense.
The CONTRACTOR shall forthwith, upon written request by COMPANY, deliver to
COMPANY'S Chief Medical Officer results of such medical examination of any of the
CONTRACTOR's PERSONNEL or agents (including those of its SUBCONTRACTORS).
(8) The CONTRACTOR warrants that any major new work, whether said work is related to a
new or an existing contract, will not adversely affect the CONTRACTOR'S allocation of its
own fully qualified and experienced personnel and other resources necessary to carry out
the WORK in accordance with the requirements of the CONTRACT.
(9) The COMPANY shall have the right to require the CONTRACTOR in writing to remove
any PERSONNEL or agent of either the CONTRACTOR or its SUBCONTRACTOR from
any location of the COMPANY or from any site where WORK are being performed without
the COMPANY offering any reason for the request providing that such right is not
exercised frivolously or vexatiously. The PERSONNEL or agent shall be removed
forthwith and shall not be employed on any other contract between the CONTRACTOR
and the COMPANY or sited in any location or premises of the COMPANY without the prior
written approval of the COMPANY. The COMPANY shall give the CONTRACTOR the
opportunity to make representations to cancel the removal but only after such removal has
been effected. A request by the COMPANY for the removal of PERSONNEL or agents of
either the CONTRACTOR or its SUBCONTRACTOR shall not itself give rise to
disciplinary action against such persons. Within 24 (twenty four) hours or such longer time
as agreed between the COMPANY and CONTRACTOR to be practical, those persons
who have been removed from the WORK shall be replaced, if the COMPANY so requires,
by other similar and suitably qualified persons acceptable to the COMPANY. All costs
incurred in the removal of any person shall be for the sole account of the CONTRACTOR.
(10) The CONTRACTOR agrees that upon request it shall furnish to the COMPANY as soon
as possible, satisfactory evidence that the CONTRACTOR'S PERSONNEL who are
engaged in the WORK have been paid on time and in full for their wages and for any other
payments required by law to be paid to them. In the event that the CONTRACTOR does
not provide such evidence, the COMPANY may make such payments directly to such
PERSONNEL or to any persons on their behalf or withhold such amounts that COMPANY
deems appropriate until COMPANY receives evidence that payment of wages has been
made to the CONTRACTOR's PERSONNEL. Any such payments made by the
COMPANY shall be deemed to be payments to the CONTRACTOR under the
CONTRACT and the CONTRACTOR shall have no further entitlement to any amounts so
paid.
(11) In the event the CONTRACTOR fails/had failed to pay its employees for their wages in full
or for any other payments required by law to be paid to them, the COMPANY at its sole
discretion shall have the right to terminate the CONTRACT.
(12) Unprofessional Conduct
(a) Notwithstanding any other provisions in the CONTRACT, CONTRACTOR warrants
that any personnel employed or engaged otherwise by the CONTRACTOR to
perform any task in connection with the WORK shall carry out their duties in
accordance with good and generally acceptable practices and procedures of their
trade or profession and in accordance with the professional and ethical standards of
that trade or profession.
(b) In the event that the CONTRACTOR or its personnel or any other person engaged
by the CONTRACTOR to perform tasks in connection with the WORK, in the
reasonable opinion of the COMPANY act in contravention of sub-clause (12) herein,
such act(s) shall constitute breach of CONTRACT by the CONTRACTOR, and
without prejudice to any other remedies which COMPANY may have under the
provisions of the CONTRACT, COMPANY shall be entitled to terminate the
CONTRACT summarily without notice or compensation to CONTRACTOR.
12. VARIATION
(1) The COMPANY shall issue a VARIATION whenever it is required to do so by any other
clause in SECTION 3 – GENERAL CONDITIONS OF CONTRACT.
In addition the COMPANY may by issuing a VARIATION at any time during the period of
the CONTRACT order any change in the form, quality or quantity of the WORK which the
COMPANY wishes to make.
(2) The following shall not be VARIATIONS:-
Instructions, interpretations or decisions or acts of the COMPANY which are:
(a) to achieve compliance with the CONTRACT by the CONTRACTOR, or
(b) to require the CONTRACTOR to correct errors, omissions, poor engineering,
defective workmanship or any other failure of the CONTRACTOR to comply with the
CONTRACT, or
(c) to avoid failure by the CONTRACTOR to achieve compliance with the CONTRACT.
(3) The COMPLETION DATE shall be subject to adjustment only as a result of a VARIATION.
(4) A VARIATION shall in no way affect the rights or obligations of the parties except as
expressly provided for in that VARIATION. Any VARIATION shall be governed by all the
provisions of the CONTRACT.
(5) If the CONTRACTOR considers that an occurrence has taken place that should give rise
to a VARIATION or considers that any instruction, interpretation, decision or act of the
COMPANY should give rise to a VARIATION, then the CONTRACTOR shall request
immediately in writing that the COMPANY shall issue a VARIATION in respect of such
claim. If the CONTRACTOR does not request a VARIATION within 28 (twenty eight) days
of the said occurrence, instruction, interpretation, decision or act then the COMPANY shall
be released and discharged from all liability arising from or in connection with the said
occurrence, instruction, interpretation, decision or act and the claim in question shall be
deemed to be time barred. The CONTRACTOR shall make such a request at the earliest
practicable time before proceeding with any WORK affected. The COMPANY shall then
notify the CONTRACTOR within 14 (fourteen) days of receipt of such a request whether
he thinks the said occurrence, instruction, interpretation, decision or act does or does not
justify a VARIATION.
The CONTRACTOR shall keep and maintain and cause any SUBCONTRACTOR to keep
and maintain full records relating to any such claim and necessary to support such claim,
and shall keep the COMPANY informed of outstanding claims on a monthly basis.
(6) The cost of any VARIATION issued by the COMPANY under Clause 12(1) herein shall be
valued at the rates set out in Section 8 SCHEDULE OF PRICES; or in accordance with
the star rates clause as applicable or in the absence of any applicable rates or star rate
clause, at such rates as may be agreed in writing between the COMPANY and the
CONTRACTOR; or failing such an agreement, at such rates as may be provisionally
determined by the COMPANY pending the appointment and decision of a mutually
acceptable expert.
(2) In order to confirm that the requirements of the CONTRACT are met the COMPANY shall
have the right, but not the obligation, at all times to inspect and test all EQUIPMENT,
MATERIALS and VEHICLES provided and all WORK or services or documentation
relating thereto performed by the CONTRACTOR or any SUBCONTRACTOR.
(3) The CONTRACTOR, at its cost, shall carry out such inspection or tests on any
EQUIPMENT, MATERIALS or VEHICLES provided by the CONTRACTOR or on any part
of the WORK as the COMPANY may from time to time require and the COMPANY shall
have the right to witness and verify any such inspection and/or tests. The CONTRACTOR
shall give the COMPANY such period of prior notice of any such inspections and/or tests
as is specified in the CONTRACT and in the event that no period is specified not less than
forty eight (48) hours notice shall be given.
(4) No part of the WORK shall be covered up or put out of view without the written approval of
the COMPANY. If any part of the WORK is covered before the required inspection or
witnessing of testing without the written consent of the COMPANY then, if required by the
COMPANY, the part of the WORK shall be opened or uncovered for inspection or
witnessing of testing and re-covered by the CONTRACTOR.
(5) (a) If the COMPANY becomes aware of any matters indicating that any workmanship,
services, EQUIPMENT, MATERIALS, VEHICLES and/or any part of the WORK may
not comply with the CONTRACT, then the COMPANY may order the
CONTRACTOR to cease the WORK in order to allow such matters to be
investigated. The COMPANY may conduct such investigations by itself and/or by a
third party, and the COMPANY may also instruct the CONTRACTOR to carry out
such investigations either concurrently or independently. In all cases the
CONTRACTOR shall cooperate with the utmost diligence with such investigations.
Such investigations may include tests and opening up.
(b) If such investigations under sub-clauses (2), (3) or (5) (a) herein do reveal non
compliance with the CONTRACT, then the COMPANY may order further
investigation and/or further opening up of the WORK to determine the full extent of
such non-compliance.
(c) As an alternative to the COMPANY's right in sub-clause (6) herein the COMPANY
may by issue of a VARIATION make any changes to SECTION 4 – SCOPE OF
WORK and/or SECTION 5 – SPECIFICATION AND DRAWINGS and to WORK
already completed that are in his opinion necessary or expedient to cure or mitigate
the effects of the non-compliance in question. Notwithstanding the provisions of
Clause headed RESPONSIBILITY OF CONTRACTOR TO INFORM ITSELF, any
VARIATION ordered under this sub-clause (5) (c) herein shall neither entitle the
CONTRACTOR to claim any extra cost nor an extension to the COMPLETION
DATE.
(d) If the initial investigations show in the COMPANY'S opinion that there was
compliance with the CONTRACT, then the COMPANY shall issue a VARIATION in
respect of the unavoidable cost incurred as a result of stoppage of the work and
initial investigations.
(6) The COMPANY shall have the right to reject any workmanship, services, EQUIPMENT,
MATERIALS, VEHICLES and any part of the WORK which does not conform with the
CONTRACT. The CONTRACTOR shall remove promptly any items so rejected and shall
immediately repair or replace the same and shall carry out such further inspections or
tests on other parts of the WORK as the COMPANY may require to ensure that there are
no similar parts of the WORK that fail to conform with the CONTRACT.
(7) The CONTRACTOR shall be responsible for all costs of repair or replacement and for
costs of uncovering, reinstating, testing and inspection except as provided under this
Clause.
Subject to sub-clause (5) herein where the COMPANY require any tests or inspections or
requires the CONTRACTOR to uncover or open up any part of the WORK for any
inspection or testing that is additional to the requirements of the CONTRACT and is not
required as a result of a failure to conform with the CONTRACT on some other similar part
of the WORK, and in either case where the inspection or test shows that the part of the
WORK concerned is in accordance with the CONTRACT, then the COMPANY shall
authorise a VARIATION for such testing and inspection and for uncovering and reinstating
such WORK.
(8) No failure on the part of the COMPANY to inspect, witness or test the WORK nor failure to
discover defects nor failure to reject WORK performed by the CONTRACTOR which is not
in accordance with the CONTRACT shall relieve the CONTRACTOR from any liability or
obligation under the CONTRACT.
14. SCHEDULING
(1) The CONTRACTOR shall be responsible at all times for scheduling, progress reporting,
forecasting and independently controlling progress to achieve the expeditious and efficient
performance of the WORK in accordance with the CONTRACT.
(2) Not later than 1 (one) week (unless the CONTRACT otherwise provides) before the date
for commencement of the WORK the CONTRACTOR shall, after close consultation with
the COMPANY, produce a programme for the WORK. This programme shall be revised
by the CONTRACTOR from time to time at the COMPANY'S request, or as may be
necessary to take account of any VARIATIONS.
(3) The CONTRACTOR shall obtain prior approval from the COMPANY on the current
programme prepared by the CONTRACTOR for the WORK before it is implemented.
(4) Where applicable, the COMPANY shall, in consultation with the CONTRACTOR, produce
a programme for the WORK and shall revise it from time to time as circumstances require
or as may be necessary to take account of any VARIATIONS.
use its best efforts to remedy the situation forthwith and shall notify the other party of the
steps being taken to remedy the situation.
(3) Should the CONTRACTOR be delayed in the performance of the WORK by an
occurrence which the CONTRACTOR considers is a force majeure occurrence and the
CONTRACTOR is unable to avoid or prevent such delay by any reasonable effort, within 7
(seven) days of such occurrence the CONTRACTOR shall request in writing that the
COMPANY initiate the procedure for a VARIATION. If the COMPANY at its sole discretion
agrees that the occurrence is a force majeure occurrence, then, as soon as practicable
the COMPANY shall authorise a VARIATION making any required adjustment to the
COMPLETION DATE to allow for the extent to which the delay is due to a force majeure
occurrence and cannot be reduced by the CONTRACTOR carrying out its obligations to
reschedule under the CONTRACT. No amounts shall be payable by the COMPANY to the
CONTRACTOR in respect of any such periods of delay except as provided in sub-clause
(5) herein.
(4) Where the CONTRACTOR is delayed in the performance of the WORK by a force
majeure occurrence for a period less than 30 (thirty) consecutive days, the COMPANY,
when authorising any VARIATION in accordance with sub-clause (3) herein shall make no
adjustment to the CONTRACT PRICE for such delay.
(5) Where the CONTRACTOR is delayed in the performance of the WORK by a force
majeure occurrence for a period of 30 (thirty) or more consecutive days, the COMPANY,
when authorising any VARIATION in accordance with sub-clause (3) herein, shall make
an adjustment to the CONTRACT PRICE only for such extra costs as the CONTRACTOR
unavoidably incurs by reason of such force majeure occurrence to the extent that the
CONTRACTOR cannot reduce or mitigate them by exercising best endeavours to do so or
the COMPANY may terminate the CONTRACT and the COMPANY shall pay the
CONTRACTOR any sum due prior to the date of commencement of such force majeure
occurrence.
(6) If any period of the force majeure occurrence exceeds 90 (ninety) consecutive days either
party may request to terminate the CONTRACT in accordance with the Clause headed
TERMINATION, DISCONTINUANCE OF THE WORK AND DEFAULT.
16. SUSPENSION
(1) The COMPANY may, by notice instruct the CONTRACTOR to suspend the WORK or any
part of the WORK. The CONTRACTOR shall cease work on such suspended part of the
WORK on the date specified in the notice, but shall continue to perform any unsuspended
part of the WORK. During the suspension, the CONTRACTOR shall properly protect and
secure the suspended part of the WORK so far as is necessary in the opinion of the
COMPANY.
(2) If the COMPANY suspends all or any part of the WORK other than:
(a) for the proper execution of the WORK, or any part thereof, or
(b) because of some mistake, error or default on the part of the CONTRACTOR, or
(c) for non-compliance to the Health, Safety and Environment requirements of the
CONTRACT, for the protection of the environment, or
(d) for non-compliance with Milestone Zero, or
(e) otherwise provided for in the CONTRACT;
then for the part of the WORK suspended, the COMPANY shall for items (a) to (e) below
reimburse the CONTRACTOR only for such extra costs as the CONTRACTOR
unavoidably incurs by reason of such suspension to the extent that the CONTRACTOR
cannot reduce or mitigate them by exercising best endeavours to do so:-
(a) the CONTRACTOR'S personnel designated as "Key Personnel" in the CONTRACT;
(b) the CONTRACTOR'S facilities dedicated to the WORK, to the extent that the
CONTRACTOR is unable to otherwise use said facilities during the period of
The rights of the COMPANY under this provision are in addition to any other rights which
the COMPANY may have under the CONTRACT or at law.
(2) In the event of Garnishee proceedings being served on the COMPANY in respect of a
judgment against the CONTRACTOR or the CONTRACTOR becoming bankrupt or
making a composition or arrangement with its creditors or having a winding up order made
or (except for the purposes of amalgamation or reconstruction) a resolution for voluntary
winding up passed or having a provisional Liquidator, Receiver or Manager or
Administrator of its business or undertaking appointed, or having possession taken by or
on behalf of the holders of any debenture secured by a Floating Charge of any property
comprised in or subject to the Floating Charge, the COMPANY shall have the right to
terminate the CONTRACT by giving the CONTRACTOR notice of termination.
(3) In addition to the COMPANY'S rights under sub-clause (1) and (2) herein the COMPANY
shall also have the right at any time and at its absolute discretion to either discontinue part
of the WORK by giving the CONTRACTOR notice of discontinuance or to terminate the
CONTRACT by giving the CONTRACTOR notice of termination.
(4) In the event of the COMPANY giving the CONTRACTOR notice of termination of the
CONTRACT or of discontinuance of part of the WORK such notice shall become effective
immediately upon delivery of the notification to the CONTRACTOR or on such later date
as specified in the notification, whereupon the CONTRACTOR at such date shall
immediately:
(a) discontinue the WORK or part of the WORK specified in the notice;
(b) allow the COMPANY or its nominee full right of access to the WORKSITE so as to
remove and/or take over the WORK or the relevant part of the WORK so far
completed and to remove and/or to take over possession of all EQUIPMENT and
MATERIALS in connection with all or part of the WORK and to allow the COMPANY
to obtain completion by another contractor;
(c) assign to the COMPANY, or its nominee, to the extent desired by the COMPANY,
all or the relevant part of the rights, titles and liabilities relating to the WORK which
the CONTRACTOR may have acquired;
(d) remove all the EQUIPMENT and MATERIALS (other than that required under sub-
clause (4)(b) herein) of the CONTRACTOR from the WORKSITE unless the parties
agree otherwise;
(e) within 30 (thirty) days of the effective date of discontinuance or termination return to
the COMPANY all documents, data or other information provided by the COMPANY
and all originals, copies and reproductions of all drawings, specifications,
requisitions, calculations, programme listings, plans, schedules, documents and all
other data in whatever format prepared by the CONTRACTOR or any
SUBCONTRACTOR.
(f) take all such further steps as are necessary to enable the COMPANY or its nominee
to take over the CONTRACTOR'S position in the performance of the WORK with
the least possible disruption, all in accordance with the COMPANY
REPRESENTATIVE'S instructions.
(5) In the event of discontinuance of part of the WORK or termination of the CONTRACT by
the COMPANY under sub-clause (3) herein or by the CONTRACTOR under Clause
headed SUSPENSION hereof, the COMPANY shall authorise a VARIATION to cover:
(a) the actual costs incurred by the CONTRACTOR in the performance of the part of
the WORK completed in accordance with the CONTRACT up to the effective date of
discontinuance or termination, broken down according to the following categories:
(i) the man-hour costs of the CONTRACTOR'S home office personnel and the
CONTRACTOR'S customary overhead thereon;
(ii) the man-hour costs of the CONTRACTOR'S personnel at the WORKSITE and
the CONTRACTOR'S customary overhead thereon;
(iii) the cost of such items of EQUIPMENT as are owned by the CONTRACTOR,
during the period they were at the WORKSITE for purposes required under
the CONTRACT (calculated at the CONTRACTOR'S normal rental rates or
comparable compensation, including a reasonable depreciation);
(iv) any direct costs and expenses not covered by (i), (ii) and (iii) above including
but not limited to financing costs, and mobilisation costs of the
CONTRACTOR'S personnel under (ii) above and EQUIPMENT under (iii)
above and costs of demobilisation thereof to their next destination or to the
CONTRACTOR'S base works, whichever are the lower;
(v) any amounts properly paid or to be paid by the CONTRACTOR to any
SUBCONTRACTOR.
(b) subject to sub-clause (4) (b) herein, the actual costs (if any) in as far as not already
covered under sub-clause (8) herein, incurred by the CONTRACTOR as a result of
termination of the SUBCONTRACTS and other obligations not assigned to the
COMPANY pursuant to sub-clause (4) (c) herein;
(c) an amount to cover the CONTRACTOR'S profit for the part of the WORK performed
up to the date of discontinuance or termination, which amount shall be the sum of
the following:
(i) an amount equal to 10% of the total of the nominal salary and legal social
burden components of the man-hour costs referred to under sub-clause (5)
(a) (i) herein plus the CONTRACTOR'S customary overhead thereon; (i.e.
10% of the said total plus overhead on the said 10%)
(ii) an amount equal to 10% of the total of the nominal salary and legal social
burden components of the man-hour costs referred to under sub-clause (5)
(a) (ii) herein plus the CONTRACTOR'S customary overhead thereon. (i.e.
10% of the said total plus overhead on the said 10%)
(6) The amounts established in accordance with sub-clause (5) herein shall be expressed in
the currencies in which the expenditure has been or will be made.
(7) The actual costs referred to under sub-clause (5) (a) and (5) (b) herein shall, if the
COMPANY so wishes, be established as sound by external auditors to be appointed by
the COMPANY. All costs involved therein shall be for the COMPANY'S account. The
CONTRACTOR shall keep appropriate accounting records in order to enable such audit to
be carried out without difficulty or delay, as and when required.
(8) As soon as the parties have reached agreement on the total sum of money to which the
CONTRACTOR is entitled pursuant to sub-clause (5) herein, they shall establish the
difference expressed in the currencies in question between that sum and the total of the
amounts already paid to the CONTRACTOR by the COMPANY in those currencies under
the CONTRACT. The amount of the difference so established shall be settled in the
currencies concerned between the parties within 45 (forty-five) days of the date of receipt
by the debtor of a debit note submitted by the creditor to the debtor.
(9) (a) In the event of the COMPANY giving the CONTRACTOR a notice of discontinuance
in respect of part of the WORK under the clause headed COMPLETION hereof or
termination under sub-clause (2) herein or after the COMPANY has issued notice of
discontinuance or termination under sub-clause (1) herein, the CONTRACTOR shall
be entitled to payment only as set out below for the part of the WORK completed in
accordance with the CONTRACT up to the date of termination or discontinuance,
which payment shall be reduced by any additional costs incurred by the COMPANY
as a result of the default of the CONTRACTOR. These additional costs, as defined
in sub-clause (9) (c) herein, may be offset by the COMPANY against any moneys
due or which may become due to the CONTRACTOR from the COMPANY.
(b) In the event of such discontinuation or termination as referred to in sub-clause (9)
(a) herein, the CONTRACTOR shall, subject to sub-clause (9) (g) herein, in the first
instance only be entitled to the actual cost, including the CONTRACTOR'S
customary overheads, incurred by the CONTRACTOR in the performance of the
part of the WORK completed in accordance with the CONTRACT up to the date of
discontinuation or termination referred to in sub-clause (9) (a) herein.
Any costs incurred by the CONTRACTOR in taking the steps such as indicated in
sub-clause (4) herein shall be for the CONTRACTOR'S account.
The actual costs referred to under sub-clause (9) (b) herein shall be examined and
certified as sound by external auditors appointed by the COMPANY. All costs
involved therein shall be for the CONTRACTOR'S account. The CONTRACTOR
shall keep appropriate accounting records in order to enable such audit to be
carried out without difficulty or delay, as and when required.
(c) The additional costs referred to in sub-clause (9) (a) herein shall be calculated as
follows:
Additional Costs = Ultimate Cost for - CONTRACT PRICE for
the part of the the part of the
WORK in question WORK in question
Where the 'ultimate cost' shall be an amount consisting of:
(i) the sum of money to which the CONTRACTOR is entitled pursuant to sub-
clause (9) (b) herein;
plus
(ii) the cost actually and necessarily incurred by the COMPANY for completion of
the part of the WORK not performed by the CONTRACTOR;
plus
(iii) cancellation charges, if any, incurred by the COMPANY in terminating
SUBCONTRACTS originally placed by the CONTRACTOR but in the
COMPANY'S opinion unacceptable for the further performance of the WORK.
(d) The COMPANY undertakes, at the CONTRACTOR'S specific request to that effect,
to supply the CONTRACTOR, at the CONTRACTOR'S expense, with a certificate of
independent auditors, certifying the total "ultimate cost" referred to in sub-clause (9)
(c) herein as sound.
(e) To the extent that the COMPANY is unable to offset such additional costs against
sums due to the CONTRACTOR under herein, then the CONTRACTOR shall pay
such additional costs to the COMPANY failing which the COMPANY shall have the
power to sell in such a manner and for such a price as it may think fit any or all of
the surplus MATERIALS and to recover the said additional cost out of the proceeds
of such sales.
(f) Upon completion of the WORK by the COMPANY or at such earlier date as the
COMPANY thinks appropriate, the COMPANY shall inform the CONTRACTOR that
the EQUIPMENT referred to in sub-clause (4) (b) herein is held available for the
CONTRACTOR at such place at or near the WORKSITE as the COMPANY will
indicate.
The CONTRACTOR shall thereafter without delay remove or arrange for the
removal of such EQUIPMENT from such place. Subject to sub-clause (9) (g) herein
the cost of removal and further cost of demobilisation of such EQUIPMENT shall be
for the CONTRACTOR'S account.
(g) Should it appear that the aforesaid "ultimate cost" is lower than the CONTRACT
PRICE, the COMPANY shall pay the CONTRACTOR:
(i) a reasonable amount for profit on the part of the WORK performed by the
CONTRACTOR,
(ii) a reasonable depreciation for the use of the CONTRACTOR'S EQUIPMENT
referred to in sub-clause (4) (b) herein,
(iii) the reasonable cost of removal and further cost of demobilisation of the
EQUIPMENT, as referred to in sub-clause (9) (f) herein.
on the understanding that the aggregate amount of any or all payments under (i)
through (iii) above shall under no circumstances exceed the amount by which the
"ultimate cost" underruns the CONTRACT PRICE.
(h) In the event of discontinuance of part of the WORK under sub-clause (9) herein
then the provisions of sub-clause (9) herein shall apply mutatis mutandis.
(10) Discontinuance of part of the WORK or termination of the CONTRACT, shall not relieve
the CONTRACTOR of any continuing obligations or liabilities under the provisions of the
CONTRACT nor shall it affect any statutory or common law rights of the COMPANY or the
CONTRACTOR.
(11) Except as provided in this Clause, any costs, loss or damage sustained by the
CONTRACTOR from discontinuance of part of the WORK, or from termination of the
CONTRACT shall be for the account of the CONTRACTOR.
18. COMPLETION
(1) When the CONTRACTOR considers that the WORK has been completed, the
CONTRACTOR shall notify the COMPANY accordingly.
(2) Upon the receipt of such notification from the CONTRACTOR, the COMPANY shall
proceed forthwith to determine whether the WORK has been performed and completed in
accordance with the CONTRACT. Within 14 (fourteen) days of receipt of the above
notification from the CONTRACTOR or within a reasonable period if the WORK is to be
performed outside Negara Brunei Darussalam, the COMPANY shall either:-
(a) issue to the CONTRACTOR a Certificate of Completion that the WORK appears to
have been completed and stating the date of completion; or
(b) notify the CONTRACTOR that the COMPANY has found the WORK or part thereof
not to have been performed in accordance with the CONTRACT. The COMPANY
shall detail in writing the specific nature of the defect in performance and the
Clause, part or Section of the CONTRACT which contains the obligation of the
CONTRACTOR, which the CONTRACTOR has failed to meet. The CONTRACTOR
shall take immediately all action necessary to remedy the defect, so as to enable
the COMPANY to issue to the CONTRACTOR a Certificate of Completion; or
(c) notify the CONTRACTOR that the COMPANY has found the WORK or part thereof
not to have been performed in accordance with the CONTRACT and that the
COMPANY requires the CONTRACTOR not to remedy the defect in performance.
The COMPANY shall, in respect of such WORK, issue a notice of discontinuance in
accordance with Clause headed TERMINATION, DISCONTINUANCE OF THE
WORK AND DEFAULT hereof and the COMPANY shall be entitled to the rights and
remedies set out in that Clause. In respect of the remainder of the WORK, the
COMPANY shall also either notify the CONTRACTOR under sub-clause (2)(b)
herein or shall issue a Certificate of Completion.
(3) The issue of a Certificate of Completion by the COMPANY or the expiry of the guarantee
period or periods referred to in Clause headed RESPONSIBILITY FOR THE WORK
hereof shall not relieve the CONTRACTOR from any continuing obligations or liabilities
under the provisions of the CONTRACT including but not limited to the Clauses headed
RESPONSIBILITY FOR THE WORK, AUDIT RIGHTS OF THE COMPANY,
INTELLECTUAL PROPERTY RIGHTS, RESPONSIBILITIES AND INDEMNITIES and
INSURANCE, nor shall it affect any statutory or common law rights held by the
COMPANY or the CONTRACTOR.
(4) The provisions of this Clause may, at the COMPANY'S discretion, be applied to separate
parts of the WORK and shall be applied for any milestones identified in the CONTRACT.
(1) The CONTRACTOR shall perform the WORK with all proper skill and care and shall
ensure that the WORK and facilities, services, MATERIALS and EQUIPMENT used to
produce or incorporated into the WORK shall be fit for their intended purpose and of good
quality and workmanship.
(2) In addition to the obligations under sub-clause (1) herein, the CONTRACTOR shall ensure
that the WORK and all services, MATERIALS and workmanship used for or incorporated
into the WORK shall all be free from errors, defects, shrinkages and failures for the
relevant guarantee periods which shall expire at the later date of either:
(a) the end of the guarantee period specified for the WORK or for the particular part of
the WORK, services, MATERIALS or workmanship in SECTION 4 – SCOPE OF
WORK; or
(b) where no period has been specified pursuant to sub-clause (2)(a) herein, the end of
the period of one year from the date of completion stated on the relevant Certificate
of Completion; and
(c) in respect of any services, MATERIALS or workmanship repaired or replaced by the
CONTRACTOR under the provisions of sub-clause (4) herein, until the date that the
repair or replacement has been completed to the satisfaction of the COMPANY and
has been free from errors, defects and failures for the period specified in sub-clause
(2) (a) or (b) herein as appropriate.
(3) The CONTRACTOR shall not be liable for any breach of sub-clauses (1) or (2) herein to
the extent that:
(a) the errors, defects or failures are due to negligent operation by the COMPANY; or
(b) the CONTRACTOR acted reasonably in relying on the technical, design, fabrication
or procedural requirements of the COMPANY specified in the CONTRACT; or
(c) the COMPANY has specified in the CONTRACT the environment for the
performance of the WORK or part thereof in respect of which the breach has
occurred and the actual environment for the performance of the WORK were more
severe than those specified by the COMPANY elsewhere in the CONTRACT and
caused the breach; or
(d) the breach is due to a defect or failure in MATERIALS supplied by the COMPANY
which could not reasonably have been discovered by the CONTRACTOR complying
with the CONTRACTOR'S obligations under SECTION 6 – PROVISIONS BY
COMPANY AND CONTRACTOR.
(4) In the event of any breach of sub-clauses (1) or (2) herein (other than a breach set out in
sub-clause (3) herein) the CONTRACTOR shall be responsible at its cost for:
(a) the repair or correction, or at the option of the COMPANY, the replacement of any
defective services, MATERIALS or workmanship; and
(b) the carrying out of all work of uncovering, removal, procurement and reinstallation
as may be necessary; and
(c) any other resulting loss or damage incurred by the COMPANY that is not allocated
as the responsibility or liability of the CONTRACTOR or the COMPANY under
Clause headed RESPONSIBILITIES INDEMNITIES & INSURANCE.
(5) In the event of a breach of sub-clause (2) herein (other than a breach as set out in sub-
clause (3) herein) the COMPANY shall notify the CONTRACTOR of the breach. Upon
receipt of such notification from the COMPANY the CONTRACTOR shall immediately
carry out the CONTRACTOR'S obligations under sub-clause (4) herein. Alternatively the
COMPANY may undertake at its option any of the CONTRACTOR'S obligations under this
Clause in which case the COMPANY shall notify the CONTRACTOR of its intention and
shall be entitled to recover from the CONTRACTOR all costs incurred by the COMPANY
in carrying out such obligations.
(6) The rights and remedies of the COMPANY provided in sub-clause (5) herein are in
addition to those available in respect of sub-clause (1) herein and without prejudice to the
COMPANY'S other remedies at law. The provisions of this Clause 20 shall not affect the
obligations of the COMPANY or the CONTRACTOR under the Clauses headed TERMS
OF PAYMENT, RESPONSIBILITIES AND INDEMNITIES AND INSURANCE.
21. TAXES
(1) The CONTRACTOR shall assume full and exclusive liability for payment of all taxes,
duties, levies, charges and contributions of any nature whatsoever that are from time to
time imposed by either:
(a) the Government of Negara Brunei Darussalam; or
(b) any other country in which the WORK is being performed; or
(c) any other fiscal or other authority whatsoever,
in respect of:
(i) employees or agents of the CONTRACTOR and its SUBCONTRACTORS (whether
or not such taxes, duties, levies, charges and contributions are measured by wages,
salaries and/or other remuneration); and
(ii) the gains of the CONTRACTOR and its SUBCONTRACTORS arising directly or
indirectly out of the performance of the WORK.
(2) The CONTRACTOR shall, and shall cause its SUBCONTRACTORS to report and pay all
such taxes, duties, levies, charges and contributions directly to the appropriate authorities
and otherwise comply with any applicable laws and regulations.
(3) The CONTRACTOR hereby covenants and undertakes to defend, indemnify and hold
harmless the COMPANY from any and all claims, suits, costs, liabilities, judgments, fines,
penalties, demands, loss or damage including any and all expenses, disbursements,
costs, legal fees, sums and amounts which the COMPANY suffers, incurs or is put to
resulting from, or in any way connected with, any assessment or imposition, for which by
the terms of this Clause the CONTRACTOR is liable.
(2) Each invoice shall include the CONTRACT reference number and title and shall be
forwarded together with full documentary evidence including, where appropriate, originals
of certified time sheets and full details of expenses claimed to:
Brunei Shell Petroleum Company Sendirian Berhad,
FAC/212,
Seria KB3534,
BRUNEI DARUSSALAM.
Brunei LNG Sendirian Berhad,
FFC,
Belait KC2935,
BRUNEI DARUSSALAM.
Brunei Shell Marketing Sendirian Berhad,
BMF,
Bandar Seri Begawan BS8811,
BRUNEI DARUSSALAM.
The CONTRACT reference number of this CONTRACT is shown in the FORM OF
AGREEMENT. If the CONTRACT reference number is not shown on any invoice then the
COMPANY shall not be bound to pay such invoice and may return it to the
CONTRACTOR unpaid.
Only original invoices will be accepted for payment. If the original invoice is lost in transit
or mislaid, a certified true copy of such invoice signed by the CONTRACTOR shall be
submitted.
Eraser or white ink shall not be used for alteration, and invoices amended in this way shall
be rejected.
(3) If the COMPANY finds the invoice so submitted to be correctly prepared, adequately
supported and in conformity with the requirements of the CONTRACT, then the
COMPANY shall within 30 (thirty) days of receipt of the invoice in question remit the
invoiced amount into the bank account nominated by the CONTRACTOR.
(4) In the event of the COMPANY disputing any item of any invoice submitted by the
CONTRACTOR, the COMPANY shall within 30 (thirty) days notify to the CONTRACTOR
the item in dispute and shall specify its reasons for dispute. Payment in respect of such
item in dispute shall be withheld until settlement of the dispute but all undisputed items of
such invoice shall be paid in accordance with sub-clause (3) herein.
(5) The CONTRACTOR shall be responsible, at its own cost, for foreign exchange approval,
foreign exchange clearance, transfers into other currencies, or bank accounts.
(6) Following CONTRACT completion and after fulfillment by CONTRACTOR of all its duties
and obligations under this CONTRACT, the CONTRACTOR shall render to the
COMPANY the final invoice stating that all charges relating to the WORK have been
included therein and that there are no outstanding charges or claims.
(7) From any sum due to the CONTRACTOR under the CONTRACT, the COMPANY may
deduct the amount of any sum which it in good faith regards as being owed by the
CONTRACTOR to the COMPANY or its ASSOCIATES whether under the CONTRACT or
otherwise.
(8) Insofar as the CONTRACT or any part thereof is cost reimbursable the CONTRACT
PRICE shall constitute the only income of the CONTRACTOR in connection with the
CONTRACT which inter alia implies that it shall not accept any trade commission,
discount allowance or indirect payment or other consideration in connection with the
CONTRACT, without notifying and accounting for same to the COMPANY. Failure to
notify and account the above mentioned to the COMPANY shall be a breach of the
CONTRACT and the COMPANY may at its sole discretion terminate the CONTRACT
under Clause headed DISCONTINUANCE AND TERMINATION and recover such cost for
any trade commission, discount allowance or indirect payment or other consideration in
connection with the CONTRACT.
(9) The CONTRACTOR may nominate a different or new bank account for payment due
herein, in which case such nomination shall be communicated in writing.
24. LIENS
(1) The CONTRACTOR agrees that it shall not claim any lien or charge on the WORK or on
any property of the COMPANY in the possession of the CONTRACTOR or at the
WORKSITE.
(2) If at any time there shall be evidence of any lien, attachment, charge or claim to which, if
established, the COMPANY or its property might be subjected and which is made against
the CONTRACTOR, the COMPANY shall have the right to retain out of any payment to be
made under the CONTRACT an amount sufficient to indemnify the COMPANY completely
against such lien, attachment, charge or claim. Should there prove to be any lien,
attachment, charge or claim upon the property of the COMPANY after all payments
hereunder have been made the CONTRACTOR agrees to refund to the COMPANY the
costs incurred by the COMPANY in discharging any such lien, attachment, charge or
claim imposed on the property of the COMPANY in consequence of the default of the
CONTRACTOR. The CONTRACTOR shall notify immediately the COMPANY of any
possible lien, attachment, charge or claim which may affect the WORK or any part thereof.
(3) Without prejudice to the provisions of this Clause 25 the CONTRACTOR shall hold
harmless and indemnify the COMPANY from and against all liens, attachments, charges
or claims by any SUBCONTRACTOR or persons alleging to be a SUBCONTRACTOR in
connection with or arising out of the CONTRACT. The COMPANY shall have the right to
withhold the amount of any such lien, attachment, charge or claim from any payment to
the CONTRACTOR under the CONTRACT until removal of such claim by any
SUBCONTRACTOR. If such liens, attachments, charges or claims fall within the scope of
the insurances of the CONTRACTOR, it shall remain the responsibility of the
CONTRACTOR to furnish the COMPANY with satisfactory written certification from the
insurer of the CONTRACTOR that any such lien, attachment, charge or claim is covered
by the insurance of the CONTRACTOR before the COMPANY shall release any money
withheld hereunder.
(4) For the purpose of this Clause reference to the COMPANY shall include its
ASSOCIATES.
25. OWNERSHIP
(1) All MATERIALS provided by the CONTRACTOR or any SUBCONTRACTOR shall
become the property of the COMPANY upon delivery to the WORKSITE or appropriation
to the CONTRACT or payment by the COMPANY whichever is the earliest. The property
in any MATERIALS provided by the CONTRACTOR or any SUBCONTRACTOR which
are not in accordance with the CONTRACT and which are rejected by the COMPANY
shall revest immediately in the CONTRACTOR or SUBCONTRACTOR as applicable. All
MATERIALS provided by the CONTRACTOR or SUBCONTRACTOR and not
incorporated into the WORK shall become the property of the CONTRACTOR or the
SUBCONTRACTOR at the completion of the WORK or such earlier date as may be
approved by the COMPANY.
(2) Unless otherwise agreed title to, access to, copyright in, the right to, possession of and
the free right of use of all things created under or arising out of the WORK shall vest in the
COMPANY immediately upon the date of commencement of the WORK or creation of the
article or document or item as applicable.
(3) The CONTRACTOR shall grant and procure that the SUBCONTRACTORS grant the
COMPANY a full free and unrestricted licence for the use of all MATERIALS and
EQUIPMENT provided by the CONTRACTOR or the SUBCONTRACTORS for the
performance of the WORK. The licence shall not terminate upon the suspension,
discontinuance or termination of all or part of the WORK and shall continue until the
WORK has been completed.
(5) The WORK shall be and remain the sole property of the COMPANY.
(4) The CONTRACTOR warrants that there are no retention of title clauses in force and
applying to any MATERIALS provided by the CONTRACTOR and shall indemnify the
COMPANY against all costs arising from each and every breach of the aforesaid
warranty.
(6) Notwithstanding the foregoing, risk in and the care and custody of any part of the WORK
and all MATERIALS and EQUIPMENT shall remain with CONTRACTOR until the WORK
is certified complete under Clause headed COMPLETION hereof or until its removal from
the WORKSITE, whichever is the later.
to such personal injury, loss or damage, and the CONTRACTOR shall not seek
contribution from such person or persons for such reason.
The indemnity and hold harmless in this sub-clause (5) shall be limited to US$5,000,000
or equivalent and in excess of such level liability shall be governed by applicable law.
(6) Consequential Losses
Subject to any express provisions in this CONTRACT, COMPANY and CONTRACTOR
agree that they shall in no event be liable one to the other for their respective
consequential damage not limited to but including indirect losses and loss of revenue,
profit or anticipated profits whether or not due in whole or in part to the negligence of
either party except to the extent of any liquidated damages provided for in the
CONTRACT.
27. INSURANCE
(1) Without limitation of its obligations and responsibilities the CONTRACTOR shall maintain
for the duration of the CONTRACT the following insurances in the joint names of the
CONTRACTOR, the COMPANY and its ASSOCIATES with a cross liability provision
where appropriate and with insurers acceptable to the COMPANY:-
(a) Employer's Liability and/or Workmen's Compensation Insurance with a minimum
limit of B$5,000,000 for any one accident or series of accidents arising out of one
occurrence, unlimited in the aggregate and as may be required by statute or similar
regulations in countries where the WORK is being performed in respect of the
CONTRACTOR's personnel in connection with the CONTRACT.
(b) adequate waterborne craft and motor vehicle insurance for owned, non-owned or
hired craft and motor vehicles, covering liabilities arising from the use and/or
operation of the waterborne craft and motor vehicles including liability contractually
assumed to third parties under this CONTRACT, liability to passengers and liability
for damage due to collision.
The CONTRACTOR shall ensure that its SUBCONTRACTORS maintain such insurances
where applicable similar insurances as referred to above in respect of their personnel,
waterborne craft and motor vehicles (whether owned, non-owned or hired).
(2) Approval by the COMPANY of any insurer or terms of insurance proposed by the
CONTRACTOR shall not relieve the CONTRACTOR of any obligation or liability under or
arising from the CONTRACT or generally at law.
(3) Without limitation of the CONTRACTOR's obligation and responsibilities under Clause
headed RESPONSIBILITIES AND INDEMNITIES, the COMPANY shall provide at its
expense for the benefit of the COMPANY the CONTRACTOR and SUBCONTRACTORS,
the following insurances.
(a) Construction All Risk insurance to cover the WORK and the Materials at the
WORKSITE.
(b) Insurance in the sum of US$5,000,000 or equivalent for any one accident or series
of accidents arising from one event in respect of the CONTRACTOR's liabilities
under sub-clause (5) headed RESPONSIBILITIES AND INDEMNITIES including the
contractual liability thereby assumed by the CONTRACTOR to third parties.
(4) The insurances under sub-clause (3)(a) and (b) herein will be to the benefit of the
COMPANY, CONTRACTOR, SUBCONTRACTORS and any ASSOCIATE. If the
Certificate of Completion of the WORK cannot be issued by the COMPANY, for
circumstances due to the CONTRACTOR or any Subcontractor, any additional premium
for continuation of the insurance shall be for the account of CONTRACTOR. None of the
insurances referred to in sub-clause (3) above shall cover either motor vehicles or
waterborne craft liability.
The insurances under sub-clause (3)(a) and (b) herein includes damage to the WORK
and/or liabilities to third parties after issue of the Certificate of Completion, if such damage
and/or liabilities:-
(i) occur during the guarantee period up to a maximum of 12 months from the date of
issue of the Certificate of Completion, mentioned in Clause headed
RESPONSIBILITY FOR THE WORK from a cause arising before the date of issue
of the Certificate of Completion. If the guarantee period is more than 12 months,
then the Contractor is responsible at its own cost for purchasing the required
insurance coverage for period(s) in excess of the 12 months.
(ii) are caused by the CONTRACTOR in the course of fulfilling its obligations under
Clause headed RESPONSIBILITY FOR THE WORK within 12 (twelve) months from
the date of issue of the Certificate of Completion or within 12 (twelve) months from
the date of the start of any period of initial operations that may be provided for in the
CONTRACT, whichever is the earlier.
(5) The insurance policies the CONTRACTOR is required to have and those additional
policies which the CONTRACTOR feels desirable to have in connection with the WORK
shall, as far as applicable, name the COMPANY and its ASSOCIATES as co-insured, and
shall contain a waiver of insurers' subrogation rights against the COMPANY, its
ASSOCIATES and their respective employees.
In addition, any reference in any of the CONTRACTOR's insurance policies pertaining to
"Avoidance of certain Terms and Rights of Recovery" or similar clause shall be endorsed
to the effect that such clause is not applicable to the COMPANY and its Associates and
their respective employees by virtue of their inclusion as joint or co-assured.
(6) The COMPANY shall have the right to inspect all policies of insurances provided for in the
CONTRACT and the receipts for the current premiums.
(7) The CONTRACTOR's liability under the CONTRACT will not be restricted, limited or
altered by any stipulation or arrangements in the CONTRACT with regard to insurance
policies. The deductibles applying under the insurances arranged by the CONTRACTOR
or its Subcontractors shall be for the account of the CONTRACTOR or such
Subcontractors.
In respect of the insurance provided by the COMPANY under sub-clause (3) herein there
shall be payable by the CONTRACTOR or SUBCONTRACTOR claimant as a deductible
in respect of each and every claim the relevant amount shown below:-
(a) the first B$50,000 in respect of onshore WORK including third party liability;
(OPTION)
(b) the first B$350,000 in respect of offshore WORK including third party liability;
(for contract with ACV below B$1.75 Million)
or
(b) the first B$875,000 in respect of offshore WORK including third party liability;
(for contract with ACV of B$1.75 Million and above)
Any excess deductible above these figures shall be for the COMPANY's account.
(8) Should the CONTRACTOR fail to procure or maintain any of the aforesaid insurance for
which it is responsible or by any act or omission validate or invalidate any of the aforesaid
insurances whoever is responsible for them, the CONTRACTOR shall indemnify the
COMPANY and the other beneficiaries of said insurance to the extent they or any of them
suffers loss or damage liability or expense in consequence of such failure, act or
omission.
(9) Without prejudice to sub-clause (7) herein, if the CONTRACTOR fails to effect or keep in
force the insurance provided for in this Clause or any other insurance which it may be
required to effect under the terms of the CONTRACT then the COMPANY may effect and
keep in force any said insurance and pay the premium or premiums as may be necessary
for that purpose and from time to time deduct the amount so paid by the COMPANY as
aforesaid from any monies due or which may become due to the CONTRACTOR or
recover them as a debt due from the CONTRACTOR. If the COMPANY does so act it
shall authorise a VARIATION under Clause 8 hereof to reduce the CONTRACT PRICE by
an amount equal to the COMPANY's costs in procuring such insurance.
(10) The CONTRACTOR shall notify the COMPANY of any occurrence likely to give rise to a
claim under any insurance policy as soon as possible and in any event within fifteen (15)
days of such occurrence. Thereafter the CONTRACTOR shall handle the claim directly
with the relevant insurers, and shall act in the best interests of both parties to this
CONTRACT.
relating to environmental protection which has been signed or, ratified by Negara
Brunei Darussalam or which has been specified in the CONTRACT.
(b) The CONTRACTOR shall comply with the COMPANY'S policy on protection of the
environment.
(c) The CONTRACTOR shall only use products which shall not cause any impact on
the environment when used in accordance with the instructions of the supplier.
Products shall be stored in a manner which shall cause minimum undue impact on
the environment.
(d) The CONTRACTOR shall take the necessary precautions to prevent damage to the
WORKSITE and to property and the environment adjoining the WORKSITE. The
CONTRACTOR shall be responsible should there be a claim arising from such
damage. In the event of any such damage, the CONTRACTOR, at its own cost,
shall take whatever remedial measures are considered necessary by the
COMPANY.
(e) The disposal of any waste materials from the WORKSITE shall be in accordance
with the COMPANY'S procedures. The disposal of waste materials must be agreed
with the COMPANY in advance and shall only be to waste disposal sites approved
for the purpose.
(f) At all times during the CONTRACT the CONTRACTOR shall keep the WORKSITE
and its surroundings clean, tidy and in good order. The CONTRACTOR shall
remove any waste materials and faulty equipment as soon as reasonably practical.
(g) The WORK shall not be deemed to have been completed until the CONTRACTOR
has removed from the WORKSITE and its surroundings all waste, debris, scrap, left
over materials, and temporary structures and has delivered the WORKSITE to the
COMPANY in a state of good order and cleanliness. The degree of rehabilitation of
the WORKSITE shall be in accordance with the requirements of the CONTRACT.
and properly certified if applicable and maintained all in accordance with the HSE
STANDARDS.
(c) any PERSONNEL or agents who are suspected of having consumed alcohol or
illegal drugs or other prohibited substances while performing the WORK shall be
required to undergo tests to detect such;
(d) any PERSONNEL and agents who are in breach of the provisions of sub-clauses 2
(a) or 2 (b) above or refuse to be tested in accordance with the provisions of sub-
clause 2 (c) above or who have been tested positive shall be subject to disciplinary
action which may include instant dismissal without compensation of any kind.
(3) The CONTRACTOR shall undertake not to provide to the COMPANY any personnel and
agents who have violated any of the provisions of sub-clause (2).
(4) The CONTRACTOR shall use its best endeavours to ensure that any personnel it recruits
would pass a drug test.
(5) Notwithstanding the Clause 34 (2), the COMPANY have the right to conduct random
testing on any of the PERSONNEL provided by the CONTRACTOR in the execution of
the CONTRACT. Any PERSONNEL tested positive for substance abuse shall be removed
immediately from the COMPANY’s WORKSITE(s) and shall be subject to the
CONTRACTOR’s disciplinary actions.
training programmes for such persons which are planned to be carried out during the term
of the CONTRACT.
(2) The CONTRACTOR shall provide the COMPANY with all necessary information to enable
the COMPANY to monitor the progress of the CONTRACTOR towards implementation of
the CONTRACTOR'S employment and training plans for citizens and permanent residents
of Brunei.
necessary or required by the COMPANY or by any duly constituted authority, for the
protection of the WORK, or for the safety and convenience of the public or others. The
CONTRACTOR shall thereby ensure that no unauthorised person enters the WORKSITE.
WORK. In the event that COMPANY carries out such tests in spite of CONTRACTOR'S
prior written statement, any damage to the WORK shall be for the COMPANY'S account.
(6) As and when the WORK or any separate part of it shall have passed all the Completion
Tests referred to in this Clause the COMPANY shall notify the CONTRACTOR
accordingly.
Notification that the WORK or any part of the WORK has passed Completion Tests shall
not relieve the CONTRACTOR from any liability or obligation under the CONTRACT nor
shall it constitute a Certificate of Completion under Clause headed COMPLETION.
(7) If the WORK or any part of it fails the Completion Tests the COMPANY shall so notify the
CONTRACTOR and may state reasons for the failure. The CONTRACTOR shall with all
speed remedy the defect and/or bring the performance up to such levels as are
guaranteed in the CONTRACT. The CONTRACTOR shall then repeat the tests at its own
cost under the same terms and conditions.
(8) If the WORK or any part of it fails the Completion Tests or any repetition thereof under
sub-clause (7) herein, the COMPANY may:-
(a) order a further repetition of the said tests under the terms of sub-clause (7) herein,
or
(b) reject the WORK or the part thereof if the test results show that the WORK or the
part of it in question fails to meet the performance or the agreed tolerances
specified in the CONTRACT, or if there are none if the results show that the WORK
or the part of it in question is not in accordance with the CONTRACT, or
(c) agree to take over the WORK or part of it in question subject to the COMPANY
receiving such liquidated damages for diminution of value as may be provided for in
the CONTRACT or failing such provision, as may be agreed by the parties or failing
agreement, at the sole discretion of the COMPANY.
(9) No Certificate of Completion shall be given under the Clause headed COMPLETION
hereof until the WORK has either passed all the Completion Tests or has been taken over
pursuant to sub-clause (8) (c) herein.
(10) If any repairs, corrections or replacement of WORK during the guarantee period under
Clause headed RESPONSIBILITY FOR THE WORK hereof are of such a nature that they
may, in the COMPANY'S reasonable opinion, affect the fitness for purpose of the WORK
then the COMPANY may require the Completion Tests to be repeated in which case such
tests shall be carried out as provided in this Clause and the CONTRACT.
(11) Any testing, failure to test or repetition of test shall, unless with the prior written consent of
the COMPANY not constitute a waiver of the COMPLETION DATE.
be deemed to be a correct record thereof. In any event the CONTRACTOR shall provide
the three (3) certified copies of the test results and all associated test reports.
(4) The CONTRACTOR shall provide at its own cost all things necessary to carry out the said
tests.
(5) As and when the part of the WORK in question shall have passed the factory tests
referred to in this Clause the COMPANY shall notify the CONTRACTOR accordingly.
Notification that a part of the WORK has passed factory tests shall not relieve the
CONTRACTOR from any liability or obligation under the CONTRACT nor shall it
constitute a Certificate of Completion under Clause headed COMPLETION.
(6) If the part of the WORK in question fails the said factory tests then the COMPANY shall so
notify the CONTRACTOR, and shall state reasons for the failure. The CONTRACTOR
shall with all speed make good the defect and (unless the COMPANY dispenses with
further tests) repeat the tests at its own cost under the same terms and conditions.
(7) Unless the COMPANY shall otherwise direct, no part of the WORK that has to undergo
factory tests shall be delivered to the COMPANY until it has passed the factory tests in
question.
(8) Any delays as a result of the said factory tests or re-testing required by the COMPANY
shall not be regarded as a waiver by the COMPANY of any of its rights under the
CONTRACT or at law.
strengthening is unnecessary, then the COMPANY shall negotiate the settlement of and
pay all sums due in respect of such claims.
APPENDIX TO CLAUSE 41
Dear Sir,
In consideration of Brunei Shell Petroleum Company Sendirian Berhad ("the COMPANY") granting
CONTRACT Number (#CON_NO#) ("the CONTRACT") to
____________________________________________________ ("the CONTRACTOR") and in
consideration of the sum of $1 payable by the COMPANY to us on demand, we,
_____________________________________________ ("the GUARANTOR") being the ultimate
parent company of the CONTRACTOR guarantee unconditionally and irrevocably as a primary
obligation to the COMPANY and not as a surety that the CONTRACTOR shall perform all its
obligations and liabilities contained in and in accordance with the CONTRACT.
If the CONTRACTOR shall fail to so perform any of its obligations under the CONTRACT, or to fulfil
any of its liabilities arising out of or in connection with the same, the GUARANTOR hereby
undertakes at the option of the COMPANY:
1) upon 14 (fourteen) days' notice in writing from the COMPANY of its intention to make a
claim under this Guarantee, forthwith to perform such obligations or liabilities on the
same terms and conditions as stated in the CONTRACT mobilising and using for that
purpose sufficient personnel and technical skill;
or 2) to reimburse the COMPANY the costs incurred by the COMPANY in itself performing the
said obligations and fulfilling the said liabilities;
or 3) to reimburse the COMPANY the costs incurred by the COMPANY in having the said
obligations performed and liabilities fulfilled by another contractor;
and 4) to indemnify the COMPANY in respect of any loss, costs and expense incurred as a
result of the CONTRACTOR's failure to perform the CONTRACT.
This Guarantee shall apply to the CONTRACT including all indulgences, variations, alterations,
incorrect payments, or extensions of time as may be made, given, conceded or agreed under the
CONTRACT, or any guarantee period and extension(s) thereto, whether or not the GUARANTOR
receives notice of the same and the GUARANTOR hereby waives all need for notice of the same and
shall also be valid in respect of any party to which the CONTRACT may be transferred by the
COMPANY, in whole or in part, pursuant to the terms thereof.
The giving of time by the COMPANY or the neglect or forbearance by the COMPANY in requiring or
enforcing the GUARANTOR's obligations under this Guarantee or the CONTRACTOR's obligations
under CONTRACT Number (#CON_NO#) or other indulgence shall not in any way prejudice such
obligations.
The GUARANTOR shall be jointly and severally liable to the COMPANY together with any other
guarantor who gives a similar parent company guarantee to the COMPANY. Furthermore this
guarantee shall be in addition to and shall not be in any way prejudiced or affected by any other form
of security that the COMPANY has or may at any future time have for the performance of the
CONTRACT.
This Guarantee shall be governed by and construed in accordance with English Law and all parties
agree to subject any disputes that may arise under or in connection with this Guarantee to the
jurisdiction of the courts of Negara Brunei Darussalam.
SIGNATURE ON BEHALF :
OF PARENT COMPANY
(the GUARANTOR)
SIGNATORY'S NAME :
TITLE OF SIGNATORY :
DATE :