Claim No. 1 - 15-11-2014

The document provides details of a progress claim for additional construction work on a two-story terrace house, including a breakdown of costs for demolition, building work, and mechanical & electrical work. It lists the original contract sum, additional costs, current contract amount, amount of work done in this claim, previous claims, deductions, and the total claim amount.

Uploaded by

pinkshallots
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views2 pages

Claim No. 1 - 15-11-2014

The document provides details of a progress claim for additional construction work on a two-story terrace house, including a breakdown of costs for demolition, building work, and mechanical & electrical work. It lists the original contract sum, additional costs, current contract amount, amount of work done in this claim, previous claims, deductions, and the total claim amount.

Uploaded by

pinkshallots
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CADANGAN TAMBAHAN DAN PINDAAN KEATAS 1 UNIT RUMAH TERES 2 TINGKAT YANG SEDIADA

DI ATAS NO. 4, JALAN ANGSANA HILIR 5, TAMAN ANGSANA HILIR, MUKIM HULU KELANG,
DAERAH AMPANG, MAJLIS PERBANDARAN AMPANG JAYA, SELANGOR DARUL EHSAN
UNTUK EN. TAUFIK

PROGRESS CLAIM NO. : 1

BQ Amount Weightage Work Done Work Done


Item Description
(RM) (%) (%) Amt. (RM)

1 Demolish work and dispose unused materials 8,742.00 6.39% 60% 5,245.20

2 BUILDING WORK

2.a Reinforced concrete structure 21,070.00 15.39% 60% 12,642.00


2.b 114mm thk sand brick in cement sand (1:3) etc. 10,200.00 7.45% 30% 3,060.00
2.c Roof structure and covering 5,200.00 3.80% 0% 0.00
2.d Plaster ceiling and frame 9,221.00 6.74% 0% 0.00
2.e Stell door frame & 'Nyatoh P' door panel 5,940.00 4.34% 0% 0.00
2.f Powder coated aluminium casement window 6,205.00 4.53% 0% 0.00
2.g 20mm thk. Cement and sand ( 1 : 3 ) rendering to floor 6,120.00 4.47% 0% 0.00
2.h Anti slip ceramic floor tiles 21,690.00 15.84% 0% 0.00
2.i 20mm thk. internal and external wall plaster 6,880.00 5.03% 0% 0.00
2.j Anti slip ceramic wall tiles 5,025.00 3.67% 0% 0.00
2.k 900mm high Mild Steel (M.S) Railing 2,600.00 1.90% 0% 0.00
2.l External & internal painting 9,760.00 7.13% 0% 0.00
2.m Externel work 820.00 0.60% 0% 0.00

TOTAL FOR BUILDING WORK 110,731.00 80.88% 11.47% 15,702.00

3 MECHANICAL & ELECTRICAL WORK

3.a cold water piping & sanitary piping 6,950.00 5.08% 0% 0.00
3.b 1 Phase electrical wiring for new extension building 10,480.00 7.66% 0% 0.00

TOTAL AMOUNT OF WORK DONE 136,903.00 100.00% 15.30% 20,947.20

CONTRACT INFORMATION

ORIGINAL CONTRACT SUM RM 136,903.00


ADDITIONAL RM +/-

CURRENT CONTRACT AMOUNT RM 136,903.00

PAYMENT & DEDUCTION

EVALUATION DATE :

1. AMOUNT WORK DONE RM 20,947.20


3. LESS PREVIOUS CLAIM NO. : RM 0.00
4. TOTAL AMOUNT OF THIS CLAIM 20,947.20
5. DEDUCTIONS ;
a. Others deductions :20% from advance payment 1st. Deduction) RM 2,800.00

TOTAL AMOUNT OF CLAIM 18,147.20

Submitted by; Received by;


ma Builder Sdn Bhd

…………………………………… ……………………………………
Mohamad Bin Arshad TAUFIK BIN SHEIKH ANIB
Principal Owner