one)days, i.e., from 22nd day after the dateof issueof LOA. In case the
contractor fails to submit the requisite PG even after60days from the
date of issue of LOA, the contract liable to be terminated. Incase
contract is terminated railway shall be entitled to forfeit EMD and
other dues payable against that contract. The failed contractor shall be
debarred from participating in re-tender for that work.
The entire work shall be completed within 8 month from the date
of issue of Letter of Acceptance.
3: The Rates accepted are inclusive of all lead, lift, royalty, GST and all
other Taxes/charges leviable by Central/State Government and local
bodies.
Item Item Desc Item Item Qty Unit Escl. Advt.Value Bid Rate/ Bid Amount
Sno. Code Qty Unit Rate(Rs) (%) (Rs) Unit Rate (Rs)
Schedule A-Execution of Items (Item Directory - Not %
Applicable) Above
Execution of
1 View Details At Par
Items
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 3/11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
Schedule Totals
Schedule B-Supply of Items (Item Directory - Not %
Applicable) Above
1 Supply of Items View Details At Par
Schedule Totals
Total Value
Rebate on Total Value
(%)
Net Bid Value
Item Breakup
Schedule A-Execution of Items
Item - 1 Execution of Items
Item
S No. Description of Item Unit Qty Rate Amount
No
Transportation, installation,
8 08 configuration, migration and Job 1
commissioning of High end Server.
Transportation including
loading/unloading of HDPE pipe from the
stores of SSE
(SIG/Tele)/BIA/R/BYT/DRZ to work site,
laying of the same (with 4 mm nylon rope
11 11 pre inserted inside the HDPE pipe) in Kilometre 0.2
excavated trench/already laid GI/RCC
pipes/tubes, jointing,levelling and end
sealing the pipes. HDPE pipe, couplers and
end caps shall be supplied by Railway.
Nylon rope and other required materials
shall be supplied by the Contractor.
Transportation, loading/unloading of OFC
from the stores of railway to the work site
with care, pushing/pulling OFC through the
HDPE pipes, sealing of the duct by sealling
/caps plugs. The cable is to be laid by
mechanised means. At inaccessible places
where mechanised laying is not possible,
the cable is to be laid manually by pulling
12 12 through pre inserted rope. This also Kilometre 0.2
includes testing of cable drums in the store
premises before transportation and
submissions of results thereof. Empty
cable drums to be returned by the
contractor. The cable drums with unused
cable at site to be returned by the
contractor to the stores depot of
Consignee.
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 5/11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
installation accesories (as required) as
detailed in technical specification and
advised by Railway's Engineer-at-
site.This also includes End to End testing
of all fibres of the optical fibre cable
terminated between cable hut to cable
hut of each station.
Total
Schedule B-Supply of Items
Item - 1 Supply of Items
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 6/11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
Item
S No. Description of Item Unit Qty Rate Amount
No
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 7/11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
Samsung/LG/Sony with all fittings
accessories and interconnection with NVR
for display data. Inspection by
representative of Sr.DSTE/R.
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 8/11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 9/11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
https://www.ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterId=896… 10/
11
3/1/24, 10:37 AM ireps.gov.in/epsn/works/tds/publishLOAWorksLetter.do?Action=ViewPublishedLetter&nitOId=73034598&tdId=1921130&letterI…
Total