Block 2
Block 2
Decisions
BLOCK 2
INVESTMENT DECISIONS
UNDER CERTAINTY
89
Financial Decisions:
An Overview BLOCK 2 INTRODUCTION
Investment decisions under certainty refers to the scenario where the cash
outflows and inflows over a period of time can be predicted with fair degree
of accuracy. These techniques are being widely used in project management.
This block deals with Project Management.
Unit 4 of the block deals with Project Planning in which we discuss about
“nature and types of projects, project life cycle and project work planning.
Unit 6 deals with Project Monitoring and Control. In this unit, we discuss
about designing a monitoring control system, project control concept and
types, and control processes.
Unit 7 deals with Social Cost Benefit Analysis. In this unit, we discuss about
concept and scope of economic appraisal, social cost-benefit analysis
technique, and application of social cost-benefit analysis in project
management and role of non-financial constraints in project appraisal.
90
Project Planning
UNIT 4 PROJECT PLANNING AND and Formulation
FORMULATION
Objectives
The objectives of this unit are:
• to provide an understanding of nature and types of projects,
• to throw light on project life cycle,
• to explain how project work is planned.
Structure
4.1 Introduction
4.2 Nature of a Project
4.3 Classification of Projects
4.4 The Project Life Cycle
4.5 Project Management Defined
4.6 Planning Project Work
4.6.1 Initial Project Coordination
4.6.2 System Integration
4.6.3 Sorting Out the Project
4.6.4 The Work Breakdown Structure and Linear Responsibility Charts
4.7 Summary
4.8 Self-Assessment Questions
4.9 Further Readings
4.1 INTRODUCTION
Effective management of projects is key to the progress of an economy
because development itself is the outcome of a series successfully managed
projects. This is why project management is receiving greater attention in
developing countries like ours, so as to avoid project schedule slippages and
cost overruns, a project needs to be meticulously planned, effectively
implemented and professionally managed in order to accomplish the
objectives of time, cost and performance. This demands fairly good
understanding of nature and types of projects, project life cycle and concept
of project management.
The term ‘project’ has a wider meaning to include a set of activities. For
example, construction of a house is a project. It includes many activities like
digging of foundation pits, construction of foundations, construction of walls,
construction of roof, fixing of doors and windows, fixing of sanitary fitting,
wiring etc. Further, project is the non-routine nature of activities.
91
Investment In fact, a project is an organized programme of pre-determined group of
Decisions under
Certainty activities that are non-routine in nature and that must be completed within the
given time limit. It is a non-routine, non-repetitive, one-off undertaking,
normally with discrete time, financial and technical performance goals.
The distinguishing features of a project are:
• Purpose: A project is usually a one-time activity with a well-defined set
of desired end results. It can be divided into subtasks that must be
accomplished in order to achieve the project goals. The project is
complex enough that the subtasks require careful coordination and
control in terms of timing, precedence, cost, and performance. The
project itself must often be coordinated with other projects being carried
out by the same parent organization.
• Life Cycle : Like organic entities, projects have a life cycle. From a slow
beginning, they progress to a buildup of size, then peak, begin a decline,
and finally must be terminated. (Also like other organic entities, they
often resist termination.) Some projects end by being phased into the
normal, ongoing operations of the parent organization.
• Single Entity : A project is one entity and is normally entrusted in one
responsibility centre while the participants in the project are many.
• Interdependencies : Projects often interact with other projects carried
out simultaneously by their parent organization; but projects always
interact with the parent’s standard, ongoing operations. While the
functional departments of an organization (marketing, finance,
manufacturing, and the like) interact with one another in regular,
patterned ways, the patterns of interaction between projects and these
departments tend to be changing. Marketing may be involved at the
beginning and end of a project, but not in the middle. Manufacturing
may have major involvement throughout. Finance is often involved at
the beginning and accounting (the controller) at the end, as well as at
periodic reporting times. The project manager must keep all these
interactions clear and maintain the appropriate interrelationships with all
external groups.
• Uniqueness : Every project has some elements that are unique. No two
construction or R&D projects are precisely alike. Though it is clear that
construction projects are usually more routine than research and
development projects, some degree of customization is a distinct feature
of a project. In addition to the presence of risk, as noted above, a project
may be unique in nature, which cannot be completely reduced to routine.
The project manager’s importance is emphasized because, as a devotee
of management by exception, the manager will find there are a great
many exceptions to manage by.
• Complexity : A rich project represents complex set of activities
pertaining to diverse areas. Technology survey, choice of the appropriate
technology, procuring the appropriate machinery and equipment, hiring
the right kind of people, arranging the financial resources, execution of
the projects in time by proper scheduling of various activities contribute
92 to the complexity of the project.
• Team Work : Successful completion of a project calls for teamwork. Project Planning
and Formulation
The team is constituted of members who are specialists in relevant
fields.
• Risk and Uncertainty : Risk and uncertainty are inherent in every
project. However, degree of risk and uncertainty will depend on how a
project passes through its various life cycle phases.
• Customer Specific : A project has always to be customer specific so as
to cater to the needs of customers. As such, the organization should go
for projects that are suited to customers.
Slow finish
% Project competition
Quick momentum
Slow start
0
Time
If this hurdle is passed, activity rate increases as planning is done, and the
real work of the project gets under way. This rises to a peak and then begins
to taper off as the project nears completion, finally ceasing when evaluation
is complete and the project is terminated. In some cases, the effort may never
fall to zero because the project team, or at least a cadre group, may be
maintained for the next appropriate project that comes along. The new project
will then emerge.
The ever-present goals of performance, time, and cost are the major
considerations throughout the project’s life cycle. Early in the life cycle,
performance takes precedence. Team members focus on how to achieve the
project’s performance goals. We refer to the specific methods adopted to
94
reach these goals as the project’s technology because these methods require Project Planning
and Formulation
the application of a science or art.
When the major “how” problems are solved, project workers sometimes get
preoccupied with improving performance, often beyond the levels required
by the original specifications. This search for additional performance delays
the schedule and pushes up the costs.
The middle stages of the life cycle are typified by a growing concern with
cost control. During the latter stages of the life cycle, focus of attention is on
time. With projects nearing completion, there tends to be more flexibility in
cost and efforts are directed towards bringing things into conformity with the
approved schedule-as much as possible, even if it means cost penalties.
Activity 1
Whatever be the process, the outcome must be that : (1) technical objectives
are established (though perhaps not “cast in concrete”), (2) basic areas of
performance responsibility are accepted by the participants, and (3) some
tentative schedules and budgets are spelt out. Each individual/unit accepting
responsibility for a portion of the project should agree to deliver; by the next
project meeting a preliminary but detailed, plan about how that responsibility
will be accomplished. Such plans should contain descriptions of the required
tasks, budgets, and schedules.
These plans are then reviewed by the group and combined into a composite
project plan. The composite plan, still not completely firm, is approved by
each participating group, by the project manager, and then by senior
organizational management. Each subsequent approval “hardens” the plan
somewhat, and when senior management has endorsed it, any further
changes must be made by processing a formal change order. However, if the
project is not large or complex, informal written memoranda can substitute
97
Investment for the change order. The main point is that no significant changes in the
Decisions under
Certainty project are made, without written notice, following top management’s
approval. The definition of “significant” depends on the specific situation
and the people involved.
General Approach: This section describes both the managerial and the
technical approaches to the work. The technical discussion describes the
relationship of the project to available technologies. For example, it might
note that this project is an extension of work done by the company for an
earlier project. The subsection on the managerial approach takes note of any
deviation from routine procedure, for instance, the use of subcontractors for
some parts of the work.
Schedules : This section outlines the various schedules and lists all milestone
events. The estimated time for each task should be obtained from those who
will do the work. The project master schedule is constructed from these
inputs. The responsible person or department head should sign off on the
final, agreed- on schedule.
98
Resources: There are two primary aspects to this section. The first is the Project Planning
and Formulation
budget. Both capital and expense requirements are detailed by task, which
makes this a project budget. One-time costs are separated from recurring
project costs. Second, cost monitoring and control procedures should be
described. In addition to the usual routine cost elements, the monitoring and
control procedures must be designed to cover special resource requirements
for the project, such as special machines, test equipment, laboratory usage or
construction, logistics, field facilities and special materials.
To accomplish any specified project, there are several major activities that
must be completed. First, list them in the general order in which they would
normally occur. A reasonable number of major activities might be anywhere
between two and twenty. Break each of these major activities into two to
twenty subtasks. There is nothing sacred about the “two to twenty” limits.
Two is the minimum possible breakdown and twenty is about the largest
number of interrelated items that can be comfortably sorted and scheduled
at a given level of task aggregation. Second, preparing a network from this
information, is much more difficult if the number of activities is significantly
greater than twenty.
Each has definite beginning and ending points along with specific criteria for
evaluating performance. Each part of the project down to the smallest subtask 101
Investment elements is budge table in terms of money, man hours, and other requisite
Decisions under
Certainty resources. Each is a single, meaningful job for which individual
responsibility can be assigned. Each can be scheduled as one of the many
jobs that the organization must undertake and complete.
Defined by Facility
responsibility
Organisation
Divisional
responsibility centre Location Location
Section 1 Section 2
Departmental
responsibility
centre Responsibility
Material
Engineering
Departmental
responsibility
centre Responsibility
Installation
Construction
Departmental
responsibility
centre Responsibility
Inspection Inspection
Source: Lavold, G.D., “Developing and Using the Work Breakdown Structure”, in Cleland
D.I., and W.R. King. Project Management Handbook, Van Nostrand Reinhold, 1983.
In constructing the WBS, it is wise to contact the managers and workers who
will be directly responsible for each of the work packages. These people can
develop a hierarchical plan for the package delegated to them.
The WBS can be used to illustrate how each piece of the project is tied to the
whole in terms of performance, responsibility, budgeting, and scheduling.
The following general steps explain the procedure for designing and using
the WBS as it would be used on a large project. For small or moderate-size
projects, some of the steps might be skipped, combined, or handled less
formally than our explanation indicates, particularly if the project is of a type
familiar to the organization.
1) Using information obtained from the people who will perform the work,
break project tasks down into successively finer levels of detail.
Continue the decomposition of work until all meaningful tasks have been
identified and each task can be individually planned, scheduled,
budgeted, monitored, and controlled.
2) For each such work element:
Make up a work statement that includes the necessary inputs, the
102 specification reference, particular contractual stipulations, and specific
end results to be achieved. List any vendors, contract, and subcontractors Project Planning
and Formulation
who are or may be involved. Identify detailed end item specifications for
each work element regardless of the nature of the end item, whether
hardware, software, test results, reports, etc.
3) The WBS, budget, and time estimates are reviewed with the people or
organizations that have responsibility for doing or supporting the work.
The purpose of this review is to verify the WBS’s accuracy, budget,
schedule, and to check interdependency of tasks, resources, and
personnel. The WBS may be revised as necessary, but the planner must
be sure to check significant revisions with all individuals who have
previously made inputs. When agreement is reached, individuals should
sign off on their individual elements of the project plan.
This series of steps complete the use of the WBS as a project planning
document. The WBS is also a key document for implementing,
monitoring, and controlling the project. The remaining steps concern its
use for these purposes.
7) One can now compare required task performance and outputs specified
in the WBS with those specified in the basic project plan in order to
identify potential misunderstandings, problem, and schedule slippages,
and then design corrective actions.
8) As the project is carried out, step by step, the Project Manager can
continually examine actual resource use, by work element, work
package, task, and so on up to the full project level. By comparing actual
against planned resource usage to a given point in time, the Project
Manager can identify problems, harden the estimates of final cost, and
make sure that relevant corrective actions have been designed and are
ready to implement if needed. It is necessary to examine resource usage
in relation to results achieved because, while the project may be over
budget, the results may be further along than expected. Similarly, the
expenses may be exactly as planned, or even lower, but actual progress
may be much less than planned.
4.7 SUMMARY
105
Investment
Decisions under
UNIT 5 INVESTMENT APPRAISAL-EVALUATION
Certainty CRITERIA
Objectives
Structure
106
Project Planning
5.2 UTILITY OF CAPITAL BUDGETING and Formulation
Capital budgeting process involves several steps. The first step in the capital
budgeting process is to assemble a list of proposed new investments, together
with the data necessary to appraise them. Although practices vary from firm
to firm, proposals dealing with asset acquisitions are frequently grouped
according to the following four categories:
The planning horizon for capital budgeting programs varies with the nature
of the industry. When sales can be forecast with a high degree of reliability
for 10 to 20 years, the planning period is likely to be correspondingly long;
electric utilities are an example of such an industry. Also, when the product-
technology developments in the industry require an 8-to-10-year cycle to
develop a new major product, as in certain segments of the aerospace
industry, a correspondingly long planning period is necessary.
107
Investment After a capital budget has been adopted, funding must be scheduled.
Decisions under
Certainty Characteristically, the finance department is responsible for scheduling and
acquiring funds to meet scheduled requirements. The finance department is
also primarily responsible for cooperating with the operating divisions to
compile systematic records on the uses of funds and the installation of
equipment purchased. Effective capital budgeting programs require such
information as the basis for periodic review and evaluation of capital
expenditure decisions - the feedback and control phase of capital budgeting,
often called the post-audit review.
In most firms, there are more proposals for projects than the firm is able or
willing to finance. Some proposals are good, others are poor, and methods
must be developed for distinguishing between the good and the poor.
Essentially, the end product is a ranking of the proposals and a cutoff point
for determining how far down the ranked list to go.
Independent projects are those that are being considered for different kinds of
tasks that need to be accomplished. For example, in addition to the materials
handling system, the chemical firm may need equipment to package the end
product. The work would require a packaging machine, and the purchase of
equipment for this purpose would be independent of the equipment
purchased for materials handling. The firm may undertake any or all
independent projects.
Finally, projects may be contingent. For example, there may be only one way
to build a football stadium but two ways of housing it (in a metal structure or
a geodesic dome). Because the stadium and its housing are contingent, the
analysis requires that we consider them together. Hence, we would want to
compare the stadium within a metal structure with the alternative of the
stadium within a geodesic dome.
To distinguish among the many proposals that compete for the allocation of
the firm’s capital funds, a ranking procedure must be developed. This
procedure requires calculating the estimated cash flows from the use of
108
equipment and then translating them into a measure of their effect on Project Planning
and Formulation
shareholders’ wealth.
First, we turn our attention to the problem of estimating cash flows for capital
budgeting purposes.
Note that this definition of cash flows is unaffected by the firm’s financing
decision, for example the amount of debt which it uses. Consequently, the
investment decision and the financing decision are kept separate when we use
this definition of cash flows for capital budgeting purposes.
We focus on how the firm’s cash flows will be changed. Table 5.1 provides
an example of a pro-forma income statement which can be used to illustrate a
cash flow calculation.
To arrive at the change in after-tax cash flows created by the project, we start
with increased revenues, ∆ R, then subtract out all items which are expensable
for tax purposes (∆ VC + ∆ FCC + ∆ dep). The result is taxable income,
assuming the firm has no debt. Next, we subtract the change in taxes and add
back the change in depreciation because depreciation is not a cash
outflow. The appropriate algebraic expression is:
Note that the term in brackets is the same as the change in earnings before
interest and taxes, DEBIT; hence, the equation becomes:
The procedure described above starts with revenues at the top of the income
statement and then works down to obtain the definition of cash flows for
capital budgeting purposes. Alternately, one can start at the bottom of the
income statement, with changes in net income (WNI) and build upward to
arrive at the same definition. Sometimes this approach is easier to use. The
algebraic expression for the change in cash flows is
Activity 1
The point of capital budgeting - indeed, the point of all financial analysis - is
to make decisions that will maximize the value of the firm. The capital
budgeting process is designed to answer two questions: (1) Which of several
mutually exclusive investments should be selected? (2) How many projects,
in total, should be accepted?
Among the many methods used for evaluating investment proposals, five are
discussed here.
1) Payback method (or payback period): Number of years required to
return the original investment.
2) Return on assets (ROA) or return on investment (ROI): An
average rate of return on assets employed.
3) Net present value (NPV) method: Present value of expected future
cash flows discounted at the appropriate cost of capital, minus the cost of
the investment.
4) Internal rate of return (IRR) method: Interest rate which equates the
present value of future cash flows to the investment outlay.
5) Profitability Index (PI): It shows the relative profitability of any
project, or the present value of benefits per rupee of costs.
General Principles
1) It will select from a group of mutually exclusive projects the one which
maximizes shareholders’ wealth.
111
Investment The value additivity principle implies that if we know the value of separate
Decisions under
Certainty
projects accepted by management, then simply adding their values, V’ will
give us the value of the firm. If there are N projects, then the value of the
firm will be:
N
V v j , j 1,.....N
j 1
Table 5.2 gives the cash flows for four mutually exclusive projects. They
all have the same life, five years, and they all require the same investment
outlay, Rs.1,500. Once accepted, no project can be abandoned without
incurring the outflows indicated. For example, Project A has negative cash
flows during its fourth and fifth years. Once the project is accepted these
expected cash outflows must be incurred. An example of a project of this
type is a nuclear power plant. Decommissioning costs at the end of the
economic life of the facility can be as large as the initial construction costs
and they must be taken into account.
Year A B C D PVIF@10%
0 -1,500 -1,500 -1,500 -1,500 1.000
1 150 0 150 300 .909
2 1,350 0 300 450 .826
3 150 450 450 750 .751
4 -150 1,050 600 750 .683
5 -600 1,950 1,875 900 .621
The last column of Table 5.2 shows the appropriate discount factor for the
present value of cash flows, assuming that the appropriate opportunity cost of
capital is 10 percent. Since all four projects are assumed to have the same
risk, they can be discounted at the same interest rate.
Now we turn our attention to the actual implementation of the five above-
mentioned capital budgeting techniques (1) the payback method, (2) the
return on assets, (3) the net present value,(4) the internal rate of return, (5)
Profitability Index. We shall see that only one technique - the net present
value method - satisfies all four of the desirable properties for capital
budgeting criteria.
Cash Flows
Year G G*
0 -1,000 -1,000
1 100 900
2 900 100
because they have the same payback period. Yet no one with a positive
opportunity cost of funds would choose Project G because Project G* returns
cash much faster.
The payback method also violates the value additivity principle. Consider the
following example. Projects 1 and 2 are mutually exclusive but Project 3 is
independent. Hence, it is possible to undertake Projects 1 and 3 in
combination, 2 and 3 in combination, or any of the projects in isolation.
The only arguments in favour of using the payback method is that it is easy to
use, but with the advent of pocket calculators and computers, we feel that
other more correct capital budgeting techniques are just as easy to use.
where
Io = Initial cash outlay = Rs.1,500
n = Life of the project = 5 years.
113
Investment Substituting in the correct numbers from Table 5.2, we have
Decisions under
Certainty Rs. 1,500 Rs.0 Rs.0 Rs.450 Rs.1, 050 Rs.1,950
ROA Rs.1,500
5
Rs.1,950
Rs.1,500
5
Rs.390
26%
Rs.1,500
The ROA’s for the four projects are
Project A, - 8%
Project B, 26%
Project C, 25%
Project D, 22%
The ROA criterion chooses Project B as best. The major problem with ROA
is that it does not take the time value of money into account. We would have
obtained exactly the same ROA for Project B, even if the order of cash flows
had been reversed with Rs.1,950 received now, Rs.1,050 at the end of
Year 1, Rs.450 at the end of Year 2 and -Rs.1,500 at the end Year 5. But
no one with a positive opportunity cost of capital would be indifferent
between the alternatives. The opposite ordering of cash flows would always
be preferred.
Here CF1,CF2, and so forth represent the net cash flows; k is the firm’s cost
of capital; I0 is the initial cost of the project; and n is the project’s
expected life.
114
Year Cash Flow X PVIF = PV Project Planning
and Formulation
0 -1,500 1.000 -1,500.00
1 150 .909 136.35
2 300 .826 247.80
3 450 .751 337.95
4 600 .683 409.80
5 1,875 .621 1,164.38
NPV = 796.28
The net present value of all four projects in Table 5.2 are:
Thus, a zero net present value project is one which earns a fair return to
compensate both debt holders and equity holders, each according to the
returns which they expect for the risk they take. A positive NPV project earns
more than the required rate of return, and equity holders receive all excess
cash flows because debt holders have a fixed claim on the firm.
Consequently, equity holders’ wealth increases by exactly the NPV of the
project. It is this direct link between shareholders’ wealth and the NPV
definition which makes the net present value criterion so important in
decision making.
115
Investment 5.6.4 Internal Rate of Return Method
Decisions under
Certainty
The internal rate of return (IRR) is defined as the interest rate that equates the
present value of the expected future cash flows, or receipts, to the initial cost
outlay. The equation for calculating the internal rate of return is:
Cf1 Cf 2 Cf n
1 2 ... n I0 0
1 IRR 1 IRR 1 IRR
n
Cf t
t I0 0
t 1 1 IRR
Here we know the value of I0 and also the values of CF1,CF2,.....CFn, but we
do not know the value of IRR. Thus, we have an equation with one unknown,
and we can solve for the value of IRR. Some value of IRR will cause the sum
of the discounted receipts to equal the initial cost of the project, making the
equation equal to zero, and that value of IRR is defined as the internal rate of
return.
The internal rate of return may be found by trial and error. First, compute the
present value of the cash flows from an investment, using an arbitrarily
selected interest rate - for example, 10 percent. Then compare the present
value so obtained with the investment’s cost. If the present value is higher
than the cost figure, try a higher interest rate and go through the procedure
again. Conversely, if the present value is lower than the cost, lower the
interest rate and repeat the process. Continue until the present value of the
flows from the investment is approximately equal to its cost. The interest rate
that brings about this equality is defined as the internal rate of return.
Table 5.3 shows computation for the IRR for Project D in Table 5,2 and
Figure 5.1 graphs the relationship between the discount rate and the NPV of
the project.
Table 5.3: IRR for Project D
116
NPV Project Planning
and Formulation
Rs. 2,000
Rs. 1,00
IRR = 25.4%
0
10% 20% 30% 40% 50%
Rs. -1,000
If K→∞, then NPV →Rs. -1,500
Rs. -2,000
Figure 5.1: NPV of Project D at Different Discount Rates
In Figure 5.1 the NPV of Project D’s cash flows decreases as the discount
rate is increased. If the discount rate is zero, there is no time value of money
and the NPV of a project is simply the sum of its cash flows. For Project D,
the NPV equals Rs.1,650 when the discount rate is zero. At the opposite
extreme, if the discount rate is infinite, then the future cash flows are
valueless and the NPV of Project D is its current cash flow, –Rs.1,500.
Somewhere between these two extremes is a discount rate which makes the
NPV equal to zero. In Figure 5.1, we see that the IRR for Project D is 25.4
per cent. The IRR’s for each of the four projects in Table 1 are given
below.
Project A IRR = - 200%
Project B IRR = 20.9%
Project C IRR = 22.8%
Project D IRR = 25.4%
If we use the IRR criterion and the projects are independent, we accept any
project which has an IRR greater than the opportunity cost of capital, which
is 10 percent. Therefore, we would accept Projects B, C, and D. However,
since these projects are mutually exclusive, the IRR rule leads us to accept
Project D as best.
Present value methods had the merit of simplicity in as much as it helps the
management in choosing the most profitable proposal. Further, while
evaluating and ranking projects it focuses on one of the primary objectives of
a firm, i.e., increasing value of the firm.
117
Investment However, main drawback of this approach is that it does not take into
Decisions under
Certainty consideration size of investment outlay and net cash benefits together while
ranking projects. This may at times lead to faulty decisions.
Here CIFt represents the expected cash inflows, or benefits, and COFt
represents the expected cash outflows, or costs. The PI shows the relative
profitability of any project, or the present value of benefits per rupee costs.
The PI for Project C, based on a 10 percent cost of capital is:
Similarly:
Project A PI = 0.59
Project B PI = 1.51
Project D PI = 1.52
A project is acceptable if its PI is greater than 1.0, and the higher the PI, the
higher the project ranking. Mathematically, the NPV, the IRR, and the PI
methods must always reach the same accept/reject decisions for independent
projects: If a project’s NPV is positive, its IRR must exceed k and its PI must
be greater than 1.0. However, NPV, IRR, and PI can give different rankings
for pairs of projects. This can lead to conflicts between the three methods
when mutually exclusive projects are being compared.
Activity 2
The above discussion leads us to conclude that IRR, NPV and PI methods
will result in the same decision, except in certain cases involving mutually
exclusive projects or non-normal cash flows. The question that arises which
capital budgeting techniques do firm actually use in practice. Lawrence
Gitman and John Forester conducted a survey to help answer this question.
Gitman and Forester received 103 usable responses from a survey sent to 268
major companies known to make large capital expenditures. They found that
the responsibility for capital budgeting analysis generally rests with the
finance department. The respondents also stated that defining projects and
estimating their cash flows were the most difficult and the most critical steps
in the capital budgeting process.
119
Investment Table 5.4: Capital Budgeting Methods Used
Decisions under
Certainty
Primary Secondary
Method Number Percent Number Percent
IRR 60 53.6% 13 14.0%
ROA 28 25.0 13 14.0
NPV 11 9.8 24 25.8
Payback period 10 8.9 41 44.0
PI 3 2.7 2 2.2
Total 112 100.0% 93 100.0%
It may also be noted that almost all the respondents used at least two methods
in their analysis, and as evidenced by the 112 primary methods from 103
respondents, some firms use more than one primary method. Although the
questionnaire did not bring this point out, we suspect that many of the
analysts of firms which use the IRR as the primary method recognize its
drawbacks, yet use it anyway because it is easy to explain to non-financial
executives but
5.8 SUMMARY
For any economy/company, there are many avenues of investments, but one
can’t go and invest in all of these avenues. This gives rise to problem of
selection of a particular project out of the many available. Here capital
budgeting techniques play an important role in deciding which project to
select & which to reject. Capital budgeting technique involves matching of
expected net cash inflows from the project with anticipated cost of the
project. Capital budgeting techniques are broadly classified in two categories.
Discounted and non discounted the major difference between these two is
that in former the future cash flows are discounted at appropriate discount
rate (usually cost of capital) to get net present value of future cash flows.
120
Project Planning
5.9 SELF ASSESSMENT QUESTIONS and Formulation
i) Are there conditions under which a firm might be better off if it chose a
machine with a rapid payback rather than one with the largest rate of
return?
ii) Company X uses the payback method in evaluating investment proposals
and is considering new equipment whose additional net after-tax
earnings will be Rs.150 a year. The equipment costs Rs.500, and its
expected life is ten years (straight-line depreciation). The company uses
a three-year payback as its criterion. Should the equipment be purchased
under the above assumptions?
iii) What are the most critical problems that arise in calculating a rate of
return for a prospective investment?
iv) What other factors in addition to rate of return analysis should be
considered in determining capital expenditures?
v) A firm has an opportunity to invest in a machine at a cost of Rs.6,56,670.
The net cash flows after taxes from the machine would be Rs.2,10,000
per year and would continue for five years. The applicable cost of capital
for this project is 12 percent.
a) Calculate the net present value for the investment.
b) What is the internal rate of return for the investment?
c) Should the investment be made?
Berk, J., De Marzo, P., Venanzi, D. (2009). Capital budgeting. Italy: Pearson.
Dayananda, D., Herbohn, J., Harrison, S., Irons, R., Rowland, P. (2002). Capi
tal Budgeting: Financial Appraisal of Investment Projects. United
Kingdom: Cambridge University Press
Herbst, A. F. (2003). Capital Asset Investment: Strategy, Tactics and
Tools. Germany: Wiley.
121
Investment
Decisions under UNIT 6 PROJECT IMPLEMENTATION
Certainty
AND CONTROL
Objectives
Structure
6.1 Introduction
6.2 Designing of the Monitoring System
6.3 How to Collect Data
6.4 Information needs and the Reporting Process
6.5 Report Types
6.6 Project Control
6.7 Types of Control Processes
6.7.1 Cybernetic Control
6.7.2 Go/No-go Control
6.7.3 Post Control
6.1 INTRODUCTION
The first step in setting up any monitoring system is to identify the key
factors to be controlled. Clearly, the project manager wants to monitor
performance, cost, and time but must define precisely which specific
characteristics of performance, cost, and times should be controlled and then
establish exact boundaries within which control should be maintained. And
there may also be other factors of importance worth noting, at least at
certain points in the life of the project. for example, the number of labour
hours used, the number or extent of engineering changes, the level of
customer satisfaction, and similar items may be worthy of note on individual
projects.
But the best source of items to be monitored is the project Action Plan -
actually, the set of Action Plans that describe what is being done, when, and
the planned level of resource usage for each task, work package, and work
unit in the project. The monitoring system is a direct connection between
planning and control. If it does not collect and report information on some
significant element of the plan, control can be faulty or missing. The
measured and reported to the control system, but it is not sufficient. For
example, the project manager might want to know about changes in the
client’s attitudes toward the project. Information on the morale of the project
team might be useful in preparing for organizational or personnel changes
on the project. These two latter items may be quite important, but are not
reflected in the project’s action plan.
Given all this, performance criteria, standards, and data collection procedures
must be established for each of the factors to be measured. The criteria and
data collection procedures are usually set up for the life of the project. The
standards themselves, however, may not be constant over the project’s life.
They may change as a result of altered capabilities within the parent
organization or a technological breakthrough made by the project team; but,
perhaps more often than not, standards and criteria change because of factors
that are not under the control of the project manager.
123
Investment Next, the information to be collected must be identified. This may consist of
Decisions under
Certainty accounting data, operating data, engineering test data, customer reactions,
specification changes, and the like. The fundamental problem in this regard is
to determine precisely which of all the available data should be collected. It is
worth repeating that the typical determinant for collecting data too often
seems to be simply the ease with which it can be gathered. Of course, the
nature of the required data is dictated by the project plan, as well as by the
goals of the parent organization, and by the fact that it is desirable to improve
the process of managing projects.
Therefore, the first task is to examine the project plans in order to extract
performance, time, and cost goals. These goals should relate to some fashion
to each of the different levels of detail; that is, some should relate to the
project, some to its tasks, some to the work packages, and so on. Data must
be identified that measure achievement against the goals, and mechanisms
designed for gathering and storing such data. Similarly, the process of
developing and managing projects should be considered and steps taken to
ensure that information relevant to the diagnosis and treatment of the
project’s organizational infirmities and procedural problems are gathered.
Given that we know what type of data we want to collect, the next question is
how to collect this information. At this point in the construction of a
monitoring system, it is necessary to define precisely what pieces of
information should be gathered and when. In most cases, the project
manager has options questions then arise. Should cost data be gathered
before or after some specific event? Is it always mandatory to collect time
and cost information at exactly the same point in the process? What do we do
if a specific piece of desirable data is difficult to collect because the data
source (human) fears reporting any information that might contribute to a
negative performance evaluation? What do we do about the fact that some
use of time is reported as “hours charged” to our project, and we are quite
aware that our project has been charged for work done on another project that
is over budget? Are special forms needed for data collection? Should we set up
quality control procedures to ensure the integrity of data transference from its
source to the project information system? Such questions merely indicate the
broad range of knotty issues that must be handled.
A large proportion of the data collected may take one of the following forms,
each of which is suitable for some types of measures.
After data collection has been completed, reports on project progress should
be generated. These include project status reports, time/cost reports, and
variance reports, among others. Causes and effects should be identified and
trends noted. Plans, charts, and tables should be updated on a timely basis.
Where known, “comparables” should be reported, as should statistical
distributions of previous data if available. Both help the project manager (and
others) to interpret the data being monitored.
The purpose of the monitoring system is to gather and report data. The
purpose of the control system is to act on the data. To aid the project
controller, it is helpful for the monitor to carry out some data analysis.
Significant variances from plan should be highlighted or “flagged” so that
they cannot be overlooked by the controller. The methods of statistical
quality control are very useful for determining what size variances are
“significant” and sometimes even help in determining the probable cause(s)
of variances. Where causation is known, it should be noted. Where it is not
known, an investigation may be in order. The decisions about when an 125
Investment investigation should be conducted, by whom, and by what methods are the
Decisions under
Certainty prerogative of the project controller, although the actual investigation may be
conducted by the group responsible for monitoring.
In creating the monitoring system, some care should be devoted to the issues
of honesty and bias. The former is dealt with by setting in place an internal
audit. The audit serves the purpose of ensuring that the information gathered
is honest. No audit, however, can prevent bias. All data are biased by those
who report them, advertently or inadvertently. The controller must
understand this fact of life. The first issue is to determine whether or not the
possibility of bias in the data matters significantly. If not, nothing need be
done. Biased findings and correcting activities are worthwhile only if data
with less or no bias are required.
Everyone concerned with the project should be tied into the project reporting
system. The monitoring system ought to be so constructed that it addresses
every level of management, but reports need not be of the same depth or at
the same frequency for each level. Lower-level personnel have a need for
detailed information about individual tasks and the factors affecting such
tasks. Report frequency is usually high. For the senior management levels,
overview reports describe progress in more aggregate terms with less
individual task detail. Reports are issued less often. At times, it may be
necessary to move information among organizations, as illustrated in Figure
6.1, as well as among managerial levels.
Reports must contain data relevant to the control of specific tasks that are
being carried out according to a specific schedule. The frequency of reporting
should be great enough to allow control to be exerted during or before the
period in which the task is scheduled for completion.
Company
Consultant
V.P.
Ventures
Steering
Committee
Marketing
Project Project
Manager Manager
Technical
Assistant
For the purposes of project management, we can consider three distinct types
of reports: routine, exception, and special analysis. The routine reports are
those issued on a regular basis; but, as we noted above, regular does not
necessarily refer to the calendar. For senior management, the reports will
usually be periodic, but for the project manager and lower-level project
personnel, milestones may be used to trigger routine reports.
Exception reports are useful in two cases. First, they are directly oriented to
project management decision making and should be distributed to the team
members who will have prime responsibility for decisions or who have a
clear “need to know.” Second, they may be issued when a decision is made
on an exception basis and it is desirable to inform other managers as well as
to document the decision - in other words, as part of a sensible procedure for
protecting oneself.
Special analysis reports are used to disseminate the results of special studies
conducted as part of the project or as a response to special problems that arise
during the project. Usually they cover matters that may be of interest to other
project manager, or make use of analytic methods that might be helpful on
other projects. Studies on the use of substitute materials, evaluation of
alternative manufacturing processes, availability of external consultants,
capabilities of new software, and descriptions of new governmental
regulations are all typical of the kind of subjects covered in special
analysis reports. Distribution of these reports is usually made to anyone who
might be interested.
128
Because the project plan is described in terms of performance, time, and cost, Project
Implementation
variances are reported for those same variables. Project variance reports and Control
usually follow the same format used by the accounting department, but at
times, they may be presented differently.
This variance report shows the ratio of the material estimated to the material
used in projects. As a result of this information, the program manager decides
that it would be less expensive for the company to carry small inventories in
a few of the commonly used high alloys, and to estimate (and price) material
use closer to actual expectations.
Thus far, we have covered monitoring for parts of projects. The monitoring of
performance for the entire project is also crucial because performance is the
raison d’etre of the project. Individual task performance must be monitored
carefully because the timing and coordination between individual tasks is
important. But overall project performance is the crux of the matter and must
not be overlooked. One way of measuring overall performance is by using an
aggregate performance measure called earned value.
planned cost for that task. The result is the amount that “should” have been
spent on the task thus far. This can then be compared with the actual amount
spent. A graph such as that shown in Figure 6.2 can be constructed and
provides a basis for evaluating cost and performance to date. If the planned
(baseline) total value of the work accomplished is in balance with the planned
cost (i.e., minimal scheduling variance), then top management has no
particular need for a detailed analysis of individual tasks. Thus, the concept
of earned value combines cost reporting and aggregate performance reporting
into one comprehensive chart.
129
Investment
Decisions under
Certainty
Rupees
Actual
Cost Total
Variance Spending Variance
of Cost Overrun
Schedule (quantity and price)
Variance
Value Completed
1 2 3
Time Variance
(10 day delay)
Three variances can be identified on the earned value chart. The spending
variance is the actual cost less the value completed, the schedule variance is
the value completed less the baseline plan, and the total variance is the sum
of the two: actual less planned cost. Top management, as mentioned above, is
usually most concerned with the schedule (or time) variance, whereas the
project controller is probably concerned with the spending variance (cost
overrun) and the controller of the parent will track the total variance. The
project manager is concerned with all the three, of course.
If the earned value chart shows a cost overrun or performance under-run, the
project manager must figure out what to do to get the system back on target.
Options include such things as borrowing resources for activities performing
better than expected, or holding a meeting of project team members to see if
anyone can suggest solutions to the problems, or perhaps, notifying the client
that the project may be late or over budget.
Activity 1
a) List out the steps that you would take to design the monitoring system
for the organization.
............................................................................................................
............................................................................................................
............................................................................................................
............................................................................................................
............................................................................................................
130
b) How would you collect the required data for monitoring purposes? Project
Implementation
............................................................................................................ and Control
............................................................................................................
............................................................................................................
............................................................................................................
c) What information would you provide in your Report to the Managing
Director?
............................................................................................................
............................................................................................................
............................................................................................................
Nature of Control
Control is the act of comparing the planned performance with the actual and
reducing the difference between the two. It is also the last element in the
implementation cycle of planning-monitoring-controlling. Information is
collected about system performance, compared with the desired (or planned)
level, and action taken if actual and desired performance differ sufficiently
that the controller (manager) wishes to decrease the difference. Note that
reporting performance, comparing the differences between desired and actual
performance levels, and accounting for why such differences exist are all
parts of the control process.
Physical asset control requires of the use of these assets. It is concerned with
the asset maintenance, whether preventive or corrective. At issue also is the
timing of maintenance or replacement as well as the quality of
maintenance.
No matter what our purpose in controlling a project, there are three basic
types of control mechanisms that we can use: cybernetic control, go/no-go
control, and post control. In this section, we will describe these three types of
control and briefly discuss the information requirements of each.
Figure 6.3 shows that a system is operating with inputs being subjected to a
process that transforms them into outputs. It is this system that we wish to
control. In order to do so, we must monitor the system output. This
function is performed by a sensor that measures one or more aspects of the
output, presumably those aspects one wishes to control. Measurements taken
by the sensor are transmitted to the comparator, which compares them with a
set of predetermined standards. The difference between actual and standards.
The difference between actual and standard is sent to the decision maker,
which determines whether or not the difference is of sufficient size to deserve
correction. If the difference is large, enough to warrant action, a signal is sent
to the effector, which acts on the process or on the inputs to produce output
that conform more closely to the standard.
The project plan, budget, and schedule are all control documents, so the
project manager has a predesigned control system complete with pre-
specified milestones as control checkpoints. Control can be exercised at any
level of detail that is supported by detail in the plans, budgets, and schedules.
The parts of a new jet engine, for instance, are individually checked for
quality conformance. These are go/no-go controls. The part passes or it does
not, and every part must pass its own go/no-go test before being used in
an engine.
While cybernetic controls are automatic and will check the operating systems
continuously or as often as designed to do so, go/no-go controls operate only
when the controller uses them. In many cases, go/no-go controls function
periodically, at regular, preset intervals. The intervals are usually determined
by clock, calendar, or the operating cycles of some machine system. Such
periodicity makes it easy to administer a control system, but it often allows
errors to be compounded before they are detected. Things begin to go awry
just after a quarterly progress check, for instance, and by the time the next
quarterly check is made, some items may be seriously out of control. Project
milestones do not occur at neat, periodic intervals; thus, controls should be
linked to the actual plans and to the occurrence of real events, not simply
to the calendar.
Not only do most projects result in outputs that are more or less satisfactory,
most projects operate with a process that is more or less satisfactory. The
concern here is not on what the project did but rather on how it did it.
Basically descriptive, this part of the final report should cover project
organization, an explanation of the methods used to plan and direct the
project, and a review of the communication networks, monitoring systems,
and control methods, as well as a discussion of intraproject interactions
between the various working groups.
Activity 2
President of an MNC has asked you to develop control system for his
organization:
a) List out the activities that you would cover while developing control
system for the organization.
............................................................................................................
............................................................................................................
............................................................................................................
............................................................................................................
b) List out the various assets of the organization that would require
control.
............................................................................................................
............................................................................................................
136
............................................................................................................ Project
Implementation
............................................................................................................ and Control
c) List out the three basic types of control mechanisms that you would
employ in the organization.
............................................................................................................
............................................................................................................
............................................................................................................
............................................................................................................
Irrespective of the type of control used, there are some important questions to
be answered while designing any control system: who sets the standards?
How realistic are the standards? How clear are they? Will they achieve the
project’s goals? What output, activities, behaviours should be monitored?
Should we monitor people? What kinds of sensors should be used? Where
should they be placed? How timely must be monitoring be? How rapidly
must it be reported? How accurate must sensors be?
If the control system is to be, acceptable to those who will use it and those
who will be controlled by it, the system must be designed so that it appears to
be sensible. Standards must be achievable by the mechanical systems
used. Control limits must be appropriate to the needs of the client that is, not
merely set to show “how good we are.” Like punishment, rewards and
penalties should “fit the crime.”
In addition to being sensible, a good control system should also possess some
other characteristics as set out below:
No matter how designed, all of the control systems described above use
feedback as a control process. Let us now consider some more specific
aspects of control. To a large extent, the Project Manager is trying to
anticipate problems or catch them just as they begin to occur. The Project
Manager wants to keep the project out of trouble because upper
management often bases an incremental funding decision on a review of the
project. This review typically follows some particular milestone and, if
acceptable, leads to a follow- on authorization to proceed to the next review
point. If not all is going well, other technological alternatives may be
recommended; or if things are going badly, the project may be terminated.
Thus, the project manager must monitor and control the project quite
closely.
The control of performance, cost, and time usually requires different input
data. To control performance, the project manager may need such specific
documentation as engineering change notices, test results, quality checks,
rework tickets, scrap rates, and maintenance activities. For cost control, the
manager compares budgets to actual cash flows, purchase orders, labour hour
charges, amount of overtime worked, absenteeism, accounting variance
reports, accounting projections, income reports, cost exception reports, and
the like. To control the schedule, the project manager examines bench mark
reports, periodic activity and status reports, exception reports, PERT/CPM
networks, Gantt charts, the master project schedule, earned value graphs, and
probably reviews the Action Plans.
Some of the most important analytical tools available to the project manager
to use in controlling the project are variance analysis and trend projection.
If this ratio is exactly one, then the activity is probably on target. If the ratio
differs from one, then the activity may need to be investigated. The closer the
ratio is to one, the less important is the investigation. Consider Table 6.1 for
example.
We can see that the first task is being scheduled but below budget. If delay is
no problem for this activity, the project manager need take no action. The
second task is on budget but its physical progress is lagging. Even if there is
slackness in the activity, the budget will probably be overrun. The third task
is on schedule but cost is running higher than budget, creating another
138
probable cost overrun. The fourth task is on budget but ahead of schedule. A Project
Implementation
cost saving may result. Finally, the fifth task is on schedule and is running and Control
under budget, another probable cost saving.
Task 4 and 5 have critical ratios greater than one and might not concern some
project manager but the thoughtful manager would like to know why they are
doing so well (and the project manager may also want to check the
information system to validate the unexpectedly favourable findings). The
second and third activities need attention, and the first task may need
attention also. The project manager may set some critical-ratio control limits
intuitively.
Some brief attention should be paid to the special case of controlling research
and development projects, design projects, and similar processes that depend
intimately on the creativity of individuals and teams. First, the more
creativity involved, the greater the degree of uncertainty surrounding
outcomes. Second, too much control tends to inhibit creativity. Control is not
necessarily the enemy of creativity; nor, popular myth to the contrary, does
creative activity imply complete uncertainty. While the exact outcomes of
creative activity may be more or less uncertain, the process of getting the
outcome is usually not uncertain.
In order to control creative projects, the project manager must adopt one or
some combination of three general approaches to the problem: (1) progress
review, (2) personnel reassignment, and (3) control of input resources.
The progress review focuses on the process of reaching outcomes rather than
on the outcomes per se. Because the outcomes are partially dependent on the
process used to achieve them - uncertain though they may be - the process is
subjected to control. For example, in the case of research projects the
researcher cannot be held responsible for the outcome of the research, but can
most certainly be held responsible for adherence to the research proposal, the
budget, and the schedule. The process is controllable even if the precise
results are not.
139
Investment
Decisions under
6.11 PERSONNEL REASSIGNMENT
Certainty
This type of control operates in a very straightforward way. Individuals who
are productive are retained. Those who are not to be retained are moved to
other jobs or to other organizations. Problems with this technique can arise
because it is easy to create an elite group. While the favoured few are highly
motivated to further achievement, everyone else tends to be demotivated. It is
also important not to apply control with too fine an edge. While it is not
particularly difficult to identify those who falls in the top and bottom
quartiles of productivity, it is usually quite hard to make clear distinctions
between people in the middle quartiles.
Sound judgment argues for some blend of these three approaches when
controlling creative projects. The first and third approaches concentrate on
process because process is observable and can be affected. But process is not
the matter of moment; results are. The second approach requires us to
measure (or at least to recognize) output when it occurs. This is often quite
difficult. Thus, the wise project manager will use all three approaches:
checking process and method, manipulating resources, and culling those
who cannot or do not produce.
6.13 SUMMARY
Project control is the act of comparing the planned performance with the
actual and reducing the difference between the two. Project control has
three domains 1) Physical Asset Control, 2) Human Resource Control, 3)
Financial Resource Control.
140
Project
6.14 SELF ASSESSMENT QUESTIONS Implementation
and Control
1) What is the purpose of control? To what is, it directed?
2) What are the three main types of control systems? What questions should
a control system answer?
3) What tools are available to the project manager to use in controlling a
project? Identify some characteristics of a good control system.
4) What is the mathematical expression for the critical ratio? What does it
tell a manager?
5) How might the project manager integrate the various control tools into a
project control system?
6) How could a feedback control system be implemented in project
management to anticipate client problems?
7) Define monitoring. Are there any additional activities that should be part
of the monitoring function?
8) Calculate the critical ratios for the following activities and indicate which
activities are probably on target and which need to be investigated.
Activity Actual Scheduled Budgeted Actual
Cost Progress Progress Cost
A 4 days 4 days Rs. 60 Rs. 40
B 3 days 2 days Rs. 50 Rs. 50
C 2 days 3 days Rs. 30 Rs. 20
D 1 day 1 day Rs. 20 Rs. 30
E 2 days 4 days Rs. 25 Rs. 25
a) Give the following information, which activities are on time, which are
early, and which are behind schedule?
141
Investment
Decisions under UNIT 7 SOCIAL COST BENEFIT
Certainty
ANALYSIS (SCBA)
Objectives
The objectives of this unit are to:
• provide an overview Social Cost Benefit Analysis
• explain the concept of market efficiency
• explain the conceptual foundation of SCBA
• explain the pricing mechanism in absence of market price
Structure
7.1 Introduction
7.2 Concept of Market Efficiency
7.3 Market Failures
7.4 Types of SCBA
7.5 Basic Steps of SCBA
7.6 Conceptual Foundation of SCBA
7.7 Valuation Methods
7.8 Summary
7.9 Self-Assessment Questions
7.10 Further Readings
7.1 INTRODUCTION
The starting point for any project/policy formulation is the economic analysis
involving estimation of cost and benefits. Estimation of cost and benefits is
core of any economic analysis and is the natural way in which individuals
and commercial enterprises take decisions before allocating resources for any
economic activity. However when governments and multilateral development
organizations decides about project and policies and allocating resource for
them, economic analysis is not the sole guiding criteria. Apart from the
economic analysis, they are much more interested in gains accruing to the
society as a whole by executing the project/policy.
In order to estimate the gains accruing to the society Social Cost Benefit
Analysis technique is used. This technique is based on the branch of
economics known as welfare economics. Welfare economics analyses the
“public decisions that impact the economic interest of more than one person
or society at large”. The issues, which SCBA tries to address, are “what
social choices/decisions are best when the available choice will affect welfare
of different sections of society differently or even oppositely”? For e.g. in
construction of multipurpose dam the beneficiaries are labour construction
materials market, farmers in the downstream area flood control tourism and
142 electricity market whereas people residing near the upstream area are going
to be adversely effected as their homes and agricultural land would be Social Cost Benefit
Analysis (SCBA)
submerged and they would be displaced from their original habitat. In general
Cost Benefit Analysis (CBA) is used by private sector and unit of
measurement is monetary units for revenue and expenses used to evaluate the
opportunity cost to investors. Financial CBA fails to add social perspective
and macro economic impact. When social perspective and macroeconomic
effects are added to CBA it is known as Social Cost Benefit Analysis
(SCBA). In SCBA in addition to financial perspective we incorporate the
following aspects:
Now if MSB> MSC it would lead to more investment as both consumers and
producers would gain additional surplus leading to higher social surplus. In
case if MSC> MSB this would lead to withdrawal of investment as the cost is
higher than the benefits leading to withdrawal of existing investment and no
new investment leading to underinvestment..
Step 3: Identify the cost and benefits (the impact categories), classify
them and select measurement indicators
Cost and benefits (C&B) needs to the identified comprehensively as possible
given the constraints and shall be characterized in terms of impact on people
that are measureable preferably in monetary terms. For e.g. in India
government are running programmes on universal immunization, polio
eradication, TB eradication and more recently on Covid 19 vaccine. Here
impact should not be measured in terms of cost incurred by the government
but by the cost saving by the population as a whole due to decrease in infant
and maternal mortality, reduced mortality, savings in medical expenses and
increased earnings of individuals due to non-occurrence of these diseases.
As a general principle only real cost and benefits which affect real resources
should be taken in consideration. In this context
• Avoided cost or benefits that are there due to project & policy should be
included along with the opportunity cost of resources likely to be used in
project
In nutshell, only those cost and benefits that are directly attributable to the
project or policy shall be included and if they occur without project/policy
intervention, they shall not be included in CBA analysis.
Step 4: Predict the impact quantitatively over the life of the project
Once the cost and benefits (impacts) have been identified the next logical
step is to quantify the impact for each time period during the life of the
project. This step is important but at the same time is difficult and complex
when projects are unique, have long time horizon and the relationship
between various variables (inputs and outputs) are complex.
Step 6: Discount benefits and costs to obtain present values and compute
NPV.
In order to assess the total impact of the project we discount the cash flows
occurring in different time periods in order to calculate the present value of
the impact due to the project. Here one important consideration is about the
discount rate to be used.
For a project with a life span of n years the present value of benefits PV (B)
and present value of costs PV (C) is estimated as follows:
n
Bt
PV (B) = t
t 0 1 s
n
Ct
PV (B) = t
t 0 1 s
Where Bt and Ct are benefits and costs in year t and S is the social discount
rate. Once the present value of benefits and cost is computed the net present
value (NPV) would be
If the project/policy has no alternative and is measured against the status quo
then projects having positive NPV should be accepted. In case more than one
alternative is being examined the alternative in relation to status quo and each
of the alternatives is mutually exclusive then the alternative with highest
positive NPV should be selected. Negative NPV would result in rejection of
all the alternatives and the status quo would be maintained.
149
Investment sensitivity analysis may reveal that under what circumstances the projects
Decisions under
Certainty
with the highest NPV may not be feasible.
If the projects have positive social net benefits then it is possible to estimate a
set of transfers or side payments that are Pareto efficient. These set of
transfers will make at least one person better off without making any one else
worse off.
The linkage between SCBA and Pareto efficiency can be explained in terms
of how benefits and costs are measured in SCB. The benefits/output of a
policy/project is measured through the Willingness To Pay (WTP) and
Willingness to Accept (WTA) principle. The WTP of an individual is the
amount s/he is willing to pay for an incremental unit of goods or services. It
measures the economic value to the individual and aggregate of these
economic values is economic benefit to the society. Conversely WTA is the
minimum amount of money an individual is willing to accept for not
receiving the benefits of proposed policy/project. These concepts expressed
in terms of utility are Equivalent Variation (EV) and Compensating Variation
(CV).
EV is used when goods and services are provided and is similar to WTP
where as CV is used when there is a reduction in goods and services and is
similar to WTA.
Now let us discuss now producer surplus and consumer surplus is calculated
with help of demand and supply curves. Before we proceed further let us
briefly discuss the basic characteristics of demand and supply curves and
how they are related to consumer and producer surplus.
Demand Curves
Individual demand curves slope down (have a negative slope) due to
diminishing marginal utility. The market demand curve is the horizontal sum
of individual demand curves. It also slopes down.
SUPPLY CURVES
The upward sloping segment of a firm’s marginal cost curve above its
average variable cost curve is its supply curve (below the average variable
cost, the firm would shut down). The marginal cost curve indicates the
additional cost to produce each additional unit of the good. The area under
the curve represents the total variable cost of producing a given amount of
the good. Producer surplus is the supply-side equivalent of consumer surplus.
It is the difference between total revenues and total variable costs.
Diagrammatically, it is the area between the price and the supply curve.
Consumer Surplus: Consumer surplus is the difference between the amount
consumers is willing to pay for the goods and services and the amount
actually paid by the consumer. Now let us derive CS form a demand curve.
As shown in fig 7.2 the demand curve depicts the maximum amount a
consumers are willing to pay for a given market quantity of the goods and as
the quantity of goods increase in the market how progressively the prices
come down the price line. The prices revealed by the demand curve represent
the consumer’s marginal willingness to pay. The area OCDE under the
demand curve CD represents of two parts rectangle OBDE, which represents
consumer total expenditure, and Area BCD, which is formed under the
demand curve and above the price line from the origin to the quantity
purchased. Area BCD is consumer surplus and is the difference between the
areas representing consumer’s total benefit and total consumer expenditure.
151
Investment
Decisions under
Certainty
SOURCE FOR FIG.7.2, 7.3 and 7.4 Lumen Learning, "ECON Open
Course,"
2015.[Online].available:https://lumen.instructure.com/courses/196787/pages/
Section9-10?module_item_id=4541568
Until now, we have ignored the role of government surplus/deficit in our
analysis, but in most cases, project and policies have impact on government
revenues. If the output of the project is priced at market price as in the case of
toll roads, the projects are going to result in government surplus due to
additional taxes arising out of increased economic activity due to the
project/policy. However if the output is not priced at market price as in case
of irrigation projects, healthcare projects and policies the projects are likely
to contribute to government fiscal deficit. So in any case these impacts shall
also be factored in while conducting SCBA.
In this analysis it is assumed that the functional forms of demand and supply
curves are known in the relevant market before and after the changes induced
by policy/project but that is not the case form most of the projects and
policies. For this kind of situation other techniques are used which we are
going to discuss in next section.
155
Investment b) Choice Modeling Method: Any project or policy can be
Decisions under
Certainty
characterized as a handle of attributes, some attributes being more
desirable than others. For e.g. Project to clean rivers may have
certain attributes take clean water, reduction in odour, development
of aquatic life, development of inland waterways etc and each of
these attributes will have different utility for different people. In this
method to estimate the value of the attributes the questioner presents
respondents with a series of alternative description of project and
policy and each alternative description varies the level of attributes –
and then respondents are asked to rank (contingent ranking) chose
(choice experiments), rate (contingent rating) or chose then rate
(paired comparison) the alternative description. From these
responses WTA and WTP estimates are made.
4. Benefit Transfer Method: in this method, information from already
done studies is taken as a proxy for the value of non market goods.
However these estimates cannot be exactly the same under all
circumstances. Before using estimate from other studies following
precaution should be taken
a) The reference study should be of the same nature as the present
project/policy
b) WTP and WTA should be comparable to the project/policy issue.
7.8 SUMMARY
Economic evaluation of project and policies is done through cost benefit
analysis. Cost benefit analysis is primarily based on observable and
measureable costs and benefits but many of the projects have cost and
benefits which are not measurable, their impact is also borne by the
stakeholders who are in no way associated with the project/policy. In order to
estimate the gains accruing to the society Social Cost Benefit Analysis
technique is used. This technique is based on the branch of economics known
as welfare economics. Welfare economics analyses the “public decisions that
impact the economic interest of more than one person or society at large”.
SCBA is a technique through which projects and policies are evaluated in
macro perspective taking into consideration both the direct as well as indirect
impact on society. This technique is little complex as many assumptions are
to be made regarding pricing of benefits for which market prices are not
available.
156
Social Cost Benefit
7.10 FURTHER READINGS Analysis (SCBA)
Toh, R., Quah, E. (2011). Cost-Benefit Analysis: Cases and Materials. United
Kingdom: Taylor & Francis.
157
Investment
Decisions under
Certainty
158