This document provides material estimates for the proposed design of a two-story health center. It includes tables with estimates for excavation, backfilling, gravel bedding, concrete works, formworks, and reinforcing steel. Dimensions and quantities of materials are given for items like column footings, beams, slabs, and more.

Uploaded by

Ninyasumergido
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

COMPUTATION

This document provides material estimates for the proposed design of a two-story health center. It includes tables with estimates for excavation, backfilling, gravel bedding, concrete works, formworks, and reinforcing steel. Dimensions and quantities of materials are given for items like column footings, beams, slabs, and more.

Uploaded by

Ninyasumergido
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

MATERIALS ESTIMATE COMPUTATION

Proposed Design of Two-Storey Health Center at Barangay Dungon B, Jaro Iloilo City

EXCAVATION

MARK length (m) width (m) height (m) Area (m2) Volume (m3) units V
TOTAL REMARKS

F1C1 EXTERIOR 1.40 1.40 1.50 2.94 12 35.28 COLUMN FOOTING


F1C1 INTERIOR 1.50 1.50 1.50 3.38 4 13.50 COLUMN FOOTING
FTB 108.00 0.20 0.30 6.48 1 6.48 FOOTING TIE BEAM
WF 12.60 0.20 0.10 0.25 1 0.25 WALL FOOTING
SEPTIC TANK 5.85 1.20 2.20 15.44 1 15.44 SEPTIC TANK
TOTAL VOLUME OF SOIL EXCAVATED 70.96 m3

BACKFILLING

MARK length (m) width (m) height (m) Area (m2) Volume (m3) units V
TOTAL REMARKS

F1C1 EXTERIOR 1.40 1.40 1.10 2.16 12 25.87 COLUMN FOOTING


F1C1 INTERIOR 1.50 1.50 1.20 2.70 4 10.80 COLUMN FOOTING
TOTAL VOLUME OF BACKFILL 36.67 m3

GRAVEL BEDDING

MARK length (m) width (m) height (m) Area (m2) Volume (m3) units V
TOTAL REMARKS

F1C1 EXTERIOR 1.40 1.40 0.10 0.20 12 2.35 COLUMN FOOTING


F1C1 INTERIOR 1.50 1.50 0.10 0.23 4 0.90 COLUMN FOOTING
SOG 15.00 12.00 0.10 18.00 1 18.00 SLAB ON GRADE
TOTAL VOLUME OF GRAVEL BEDDING 21.25 m3
CONCRETE WORKS

MARK length (m) width (m) height (m) Area (m2) Volume (m3) units V
TOTAL REMARKS

F1C1 EXTERIOR 1.40 1.40 0.30 0.59 12 7.06 COLUMN FOOTING


F1C1 INTERIOR 1.50 1.50 0.30 0.68 4 2.70 COLUMN FOOTING
FTB 108.00 0.20 0.30 6.48 1 6.48 FOOTING TIE BEAM
WF 12.60 0.20 0.10 0.25 1 0.25 WALL FOOTING
SEPTIC TANK 3.00 1.20 0.10 0.36 2 0.72 SEPTIC TANK
C1 GD 0.30 0.30 4.80 0.43 16 6.91 COLUMN
C1 2nd 0.20 0.20 3.20 0.13 16 2.05 COLUMN
2ND FLOOR B1 12.00 0.20 0.35 0.84 4 3.36 BEAM
2ND FLOOR B (GRID C) 5.50 0.275 0.50 0.76 1 0.76 BEAM
2ND FLOOR B (GRID C) 2 4.00 0.20 0.38 0.30 1 0.30 BEAM
2ND FLOOR B (GRID D) 4.50 0.25 0.45 0.51 1 0.51 BEAM
2ND FLOOR B (GRID D) 3 4.00 0.20 0.40 0.32 1 0.32 BEAM
RD B1 4.00 0.20 0.35 0.28 1 0.28 BEAM
RD B (GRID C) 5.50 0.25 0.50 0.69 1 0.69 BEAM
RD B (GRID C) 2 4.00 0.20 0.35 0.28 1 0.28 BEAM
RD B (GRID D) 4.50 0.23 0.40 0.41 1 0.41 BEAM
RD B (GRID D) 3 4.00 0.20 0.40 0.32 1 0.32 BEAM
GROUND FLOOR SLAB 12.00 15.00 0.10 18.00 1 18.00 SLAB
4.00 4.00 0.10 1.60 1 1.60 SLAB
4.00 2.00 0.10 0.80 1 0.80 SLAB
2ND FLOOR SLAB 12.00 9.50 0.10 11.40 1 11.40 SLAB
6.20 4.00 0.10 2.48 1 2.48 SLAB
CONCRETE DECK SLAB 12.00 15.40 0.10 18.48 1 18.48 SLAB
TOTAL VOLUME OF CONCRETE + 20% ALLOWANCE 103.37 m3

FORMWORKS

MARK length (m) width (m) QTY Area (m2) PCS

COLUMN 1.20 8.00 16.00 153.60 54


BEAM 1.00 108.00 1.00 108.00 38
2ND FLR SLAB 12.00 9.50 1.00 114.00 40
6.00 4.00 1.00 24.00 9
ROOF DECK SLAB 12.00 15.40 1.00 184.80 65
TOTAL AREA OF FORMWORKS 584.40 m2
NUMBER OF USAGES 2
292.20 m2
AREA OF 1 SHEET OF PLYWOOD 2.97 m2
TOTAL NUMBER OF PLYWOOD 98 sheets

SCAFFOLDINGS

MARK length (m) width (m) QTY Area (m2) PCS


COLUMN 1.20 8.00 16.00 153.60 54
BEAM 1.00 108 1 108.00 38
2ND FLOOR SLAB 12.00 9.5 1 114 40
6.00 4 1 24.8 9
ROOF DECK SLAB 12.00 15.4 1 184.8 65
TOTAL PCS OF SCAFFOLDINGS 206

REINFORCING STEEL

DESCRIPTION DIAMETER, mm LENGTH,m QTY TOTAL LENGTH WEIGHT, kgs


COLUMNS 20 9 144 1,296.00 3,200.00
FTB 20 10.5 45 472.5 1,166.67
WF 12 30 3 90 80.00
BEAM 2F 16 10.5 20 210 331.85
BEAM 2F 20 10.5 45 472.5 1,166.67
COLUMN TIES 10 1 560 560 345.68
STIRRUPS (TB) 10 1.56 795 1240.2 765.56
BEAM STIRRUPS 10 1.56 1590 2480.4 1,531.11
LINTEL BEAM & CHB 10 6 190 1140 703.70
SOG 10 10.5 180 1890 1,166.67
SLAB 2ND FLR 10 10.5 520 5460 3,370.37
SLAB ROOF DECK 10 10.5 470 4935 3,046.30
STAIRS 10 9 500 4500 2,777.78
BEAM ROOF DECK 20 10.5 42 441 1,088.89
BEAM ROOF DECK 16 10.5 7 73.5 116.15
SEPTIC TANK 12 9 160 1440 1,280.00
22,137.38
10 mm ⌀ 12 mm ⌀ 16 mm ⌀ 20 mm ⌀
TOTAL KGS OF REINFORCING STEEL + 10% EXTRA KGS
15,077.88 1,496.00 492.80 7,284.44
CHB WALLS

DESCRIPTION HEIGHT WIDTH (m) OPENING Area (m2) NO. OF CHB REMARKS
FRONT ELEV. GD - RD (EXTERIOR) 7.8 12 43.02 50.58 633 #6
RIGHT ELEV. GD - RD (EXTERIOR) 7.8 15 10.59 106.41 1331 #6
LEFT ELEV. GD - RD (EXTERIOR) 7.8 15 17 100.00 1250 #6
REAR ELEV. GD - RD (EXTERIOR) 7.8 12 15.14 78.46 981 #6
INTERIOR WALLS - GD 3.2 47.7 21.48 131.16 1640 #4
INTERIOR WALLS - 2ND FLR 3.2 50.8 13.02 149.54 1870 #4
TOTAL NO. OF CHB 4" + 10% EXTRA CHB 3861
TOTAL NO. OF CHB 6" + 10% EXTRA CHB 4614.5

PLASTERING

DESCRIPTION HEIGHT WIDTH (m) OPENING Area (m2)


FRONT ELEV. GD - RD (EXTERIOR) 7.4 12 43.02 91.56
RIGHT ELEV. GD - RD (EXTERIOR) 7.4 15 10.59 200.82
REAR ELEV. GD - RD (EXTERIOR) 7.4 12 15.14 147.32
LEFT ELEV. GD - RD(EXTERIOR) 7.4 15 17 188.00
INTERIOR WALLS - GD 3.2 47.7 21.48 262.32
INTERIOR WALLS - 2ND FLR 3.2 50.8 13.02 299.08
TOTAL AREA FOR PLASTERING + 10% EXTRA 1308.01 m2
TOTAL BAGS OF CEMENT FOR MORTAR & PLASTERING 1483 bags
VOLUME OF WASHED SAND FOR MORTAR & PLASTERING 125 m3

PAINTING
DESCRIPTION HEIGHT WIDTH (m) OPENING Area (m2)
FRONT ELEV. GD - RD (EXTERIOR) 7.4 12 43.02 91.56
RIGHT ELEV. GD - RD (EXTERIOR) 7.4 15 10.59 200.82
REAR ELEV. GD - RD (EXTERIOR) 7.4 12 15.14 147.32
LEFT ELEV. GD - RD(EXTERIOR) 7.4 15 17 188.00
INTERIOR WALLS - GD 3.2 47.7 21.48 262.32
INTERIOR WALLS - 2ND FLR 3.2 50.8 13.02 299.08
CEILING GF 14.1 12 40 129.20
CEILING 2F 14.1 12 40 129.20
COLUMNS 1.20 8.00 153.60
TOTAL AREA FOR PAINTING + 10% EXTRA 1761.21 m2
TOTAL GALLON OF PAINT (FLAT LATEX) 80 gallons
TOTAL GALLON OF PAINT (SEMIGLOSS) 30 gallons
TOTAL SKIM COAT 160 bags

CEILING
DESCRIPTION LENGTH WIDTH (m) OPENING AREA
GROUND FLOOR 12 15 36.8 143.2
2ND FLOOR 12 15 180
TOTAL AREA 323.2 m2
4.5 MM FIBER CEMENT BOARD 109 pcs
METAL FURRING 647 pcs
WALL CLIP 3879 pcs
CARRYING CHANNEL 324 pcs

TILES
DESCRIPTION LENGTH WIDTH (m) OPENING AREA
GROUND FLOOR 12 15 13.8 166.2
2ND FLOOR 12 15 13.44 166.56
GROUND FLOOR (Comfort Room) 25.8 1.5 38.7
2ND FLOOR (Comfort Room) 15.8 1.5 23.7
TOTAL AREA OF 60X60 TILES 1017 m2
TOTAL AREA OF 30X30 TILES 763 m2
TOTAL BAGS OF TILE ADHESIVE 80 bags
TOTAL BAGS OF CEMENT 80 bags
TOTAL VOLUME OF FINE SAND 6.4 m3

DOORS
DESCRIPTION HEIGHT WIDTH (m) SETS AREA
D1 2.2 1 1 2.2
D3 2.4 1.3 1 3.12
D4 2.4 1 6 14.4
D6 PVC DOOR 2 1 1 2
D7 PVC DOOR 2 0.7 4 5.6
D8 2 0.7 1 1.4
TOTAL AREA IN SQ. FT 308.98 sq. ft

WINDOWS
DESCRIPTION HEIGHT WIDTH (m) SETS AREA
W1 9 12 4 432
W2 5 6 9 270
W3 5 5 1 25
W4 3 6 6 108
W5 3 4 1 12
D2 8 6 2 96
D5 8 4 1 32
D1 8 2 2 32

ELECTRICAL PLUMBING
DESCRIPTION QTY UNIT DESCRIPTION QTY UNIT
PIN LIGHT 78 pcs Water Closet w/ Complete 7.00 PCS
PANEL BOARD 2 pcs Stainless Floor Drain 6.00 PCS
CIRCULAR LAMP 4 pcs Lavatory 9.00 PCS
FLUORESCENT LIGHT 1 pcs PVC Wye 4"x4" 24.00 PCS
OUTLET 21 pcs PVC Elbow 45 4" 24.00 PCS
ACU 6 pcs PVC Elbow 90 4" 37.00 PCS
EXHAUST FAN 5 pcs PVC Tee 4"x4" 11.00 PCS
SWITCH 30 pcs PVC Clean out 4" 8.00 PCS
WIRINGS 300 m PVC Wye 4"x2" 15.00 PCS
PVC Tee 4"x2" 27.00 PCS
PVC Elbow 45 2" 12.00 PCS
PVC Elbow 90 2" 54.00 PCS
PVC P-Trap 2" 26.00 PCS