NEOM Pre Task Briefing Form - New Format
NEOM Pre Task Briefing Form - New Format
Internal
NEOM-NPR-STD-001_FRM01
ACTIVITY BRIEFING FORM
Project Name:
Location:
Activity: Responsible
Eng./Site Mngr
Supervisor Name:
Date:
Risk Assessment:
Time:
PART 1: During the activity briefing, explain the activity and ask everyone the following:
Exclusion Zone Hot Works/Fire Energized Systems Temporary Works Drilling and Working on or near Working in Heat
Blasting Water
PART 2: Are there any other hazards involved? If yes, list the hazards and controls below:
1. Do we have the right tools and equipment to perform the job safely? ☐ Yes ☐ No
2. Have you briefed the team on emergency and welfare arrangements? ☐ Yes ☐ No
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
Supervisor: Reviewer:
(Name & (Name &
Signature) Signature)
Date: Date:
IF SOMETHING CHANGES OR IS NOT CORRECT, STOP WORK AND LET YOUR SUPERVISOR KNOW!