Installation Checklist & Maintenence Report.
Installation Checklist & Maintenence Report.
DRILLING CONTRACTOR
Certificate of Completion
BOREHOLE PUMP INSTALLATION
Date:…………/………………/…………………
Location: …………………………………………………………………………………………………………………………………….
Borehole Details:
2 Borehole Depth:……………………………………………………………………………………………………………….…Mtr
5 Tested Yield:…………………………………………………………………………………………………………………….m³/hr
6 Electrodes:…………………………………………………………………………………………….………………………...….Pair
8 Riser Pipe(Type):……………………….……………………………….…………inches……………………………..…...Mtr
18 Warranty Period:……………………………………………………………………………………………………………Months
Remarks:……………………………………………………………………………………………………………………………………
Signature:…………………………………………………………………….. Signature:………………………………………………………….
Technician:…………..…………………………………………..
EXPORT-HYDRO GROUP
DRILLING CONTRACTOR
Date:…………/………………/…………………
Location: …………………………………………………………………………………………………………………………………….
Borehole Details:
2 Borehole Depth:……………………………………………………………………………………………………………….……...Mtr
5 Tested Yield:………………………………………………………………………………………………………………………....m³/hr
Material List:
6 Electrodes:…………………………………………………………………………………………….………………………...………...Pair
8 Riser Pipe(Type/Size):……………………….……………………………….………...Inches……………………………..…….Pcs
10 Steam Socket(Size):…………………………………………………..inches………………………………………………………….Pcs
Rawl Plugs:…………………………………………………………………………………………………………………………………..Pcs
Saddle Clips:…………………………………………………mm..……………………………………………………………………...Pcs
Shrouds:………………………………………………………………………………………………………………………………………..Pcs
2 Tee (Type/Size)…………………………………………………………….inches………………………...…………………………..Pcs
3 Bend (Type/Size):………………………………………………………….inches………………………………………………….....Pcs
4 Elbow (Type/Size):…………………………………………………………inches………………………………………………….....Pcs
5 Union (Type/Size):………………………………………………………….inches………………………………………………...….Pcs
6 Hex-Nipple (Type/Size)…………………………………………………..inches…………………………………………………....Pcs
10 Socket (Type/Size):…………………………………………………..inches…………………………………………………………..Pcs
11 Plug (Type/Size):………………………………………………………inches…………………………………………………………..Pcs
15 Thread Tape:…………………………………………………………………………………………………………………………………..Pcs
16 Insulation Tape:……………………………………………………………………………………………………………………………..Pcs
17 Bosswhite:……………………………………………………………………………………………………………………………………..Tins
18 Bitumen:…………………………………………………………………………………………………………………………………………Ltrs
19 Cable Ties(Size):…………………………………………………mm…………………………………………………………………….Pkts
20 Red Oxide
22 Turpentine:…………………………………………………………………………………………………………………………………….Ltrs
23 Cement:…………………………………………………………………………………………………………………………………………Bags
24 Sand:……………………………………………………………………………………………………………………………..Wheelbarrows
25 Ballast:………………………………………………………………………………………………………………………….Wheelbarrows
Site In Charge:………………………………….……………………
PREVENTIVE MAINTENANCE REPORT
PERTINENT DATA
Borehole Drilled Depth (m)
Static Water Level (m)
Pumping Water Level (m)
Drawdown (m)
Total Available Water Column (m)
Total Available Pumping Water Column (m)
Pump Setting Depth (m)
Pump Type;kW & HP
Overload Relay Setting (Amps)
Pump Testing Yield After Drilling (m3/hr)
CONTROL UNITS
Incoming power supply Contractor Unit
Main MCB
Overload Realay Unit
Phase Failure Relay Unit Set over-voltage@……….
Set under-voltage@……
Water Level Relay Unit Set sensitivity@…… Good
Ammeter
Auto-Off-Hand Selector Switch
Voltmeter
Pump Running Indicator
Water Available Indicator
Trip Light Indicator
MAINS CABLE
Incoming power supply Contactor Unit
Main MCB
Overload Relay Unit
Terminal Connectors
Ammeter
CONTROL CABLES
MCB Control Unit
Phase Failure Unit
Water Level Relay Unit
Overload Relay Unit
Contactor Unit
Connectors
Pump Running Indicator
Water Available Indicator
Trip Light Indicator
ELECTRICAL TESTS
Insulation Resistance (Mega Ohms)
Blue vs. Earth
Red vs. Earth
Yellow vs. Earth
Motor Windings (Ohms)
Red and blue
Blue and Yellow
Voltage Output (Volts) - Between Phases
Red and Yellow
Red and Blue
Blue and Yellow
Voltage Input (Volts) - Between Neutral
Red and Neutral (Earth)
Yellow and Neutral (Earth)
Blue and Neutral (Earth)
CONCLUSION:
Fault Finding
REMARKS